Professional Documents
Culture Documents
CHAPTER 5
Project-1 Project-2
MinE424 - Project Management in Mining 3
5.1. Objectives of Project Control
Task 1 Defining a Specific Topic in a Broad Sense Task 10 Re-arranging the Topic Boundary and Methodology
Task 2 Literature Review Task 11 Re-performing the Modified Methodology Steps
Task 3 Finding the Gaps of Topic in the Literature Task 12 Technical Check of the Whole Thesis
Task 4 Re-arranging the Topic Boundary Task 13 Finding and Correcting the Gaps/Missing Points in the Thesis
Task 5 Setting the Problem Statement Task 14 Discussing and Interpreting the Results
Task 6 Setting the Objectives and Scopes Task 15 Conclusion
Task 7 Setting the Research Methodology Task 16 Structural Check of the Whole Thesis
Task 8 Setting the Study Motivation and Its Industrial Contributions Task 17 Preparation of the Defense Presentation
Task 9 Performing the Steps of the First-Identified Methodology Task 18 Thesis Defense
Dummy Activities
Dummy Activities
Dummy Activities
Dummy Activities
Example 5.1: Draw the (AOA) diagram so that the following precedence relation is satisfied:
i) E is preceded by B and C and ii) F is preceded by A and B.
Solution:
Dummy Activities
Example 5.2: Draw the (AOA) diagram so that the following precedence relation is satisfied:
i) G is preceded by A, ii) E is preceded by A and B, and iii) F is preceded by B and C
Solution:
Dummy Activities
Example 5.3: The following table gives the precedence relations between activities when
changing a flat tire of a car. Draw the AoA diagram for the given information.
Preceding node Following node Estimated Duration, min
Description of activity
(i) (j) (Tij)
1 2 1.0 Remove coats
2 3 1.0 Procure jack and lug wrench
2 7 2.0 Procure spare
3 4 1.5 Remove hub cap, loosen nuts
3 5 0.5 Position jack
4 5 0 Dummy
4 6 1.0 Remove lug nuts
5 6 2.0 Jack up car
6 7 0.5 Remove flat
7 8 0.5 Place spare
7 11 2.0 Put flat away
8 9 1.0 Lower car
8 10 1.5 Tighten lug nuts
9 10 0 Dummy
9 11 1.0 Put jack away
10 11 2.0 Final tighten, replace hub cap
11 12 2.0 Clean up, put on coats
Dummy Activities
Solution:
4 6 8 10
9
3 5
1 2 7 11 12
The major difference between the two is that CPM assumes that the
activity times are deterministic, while PERT views the time to
complete an activity as a random variable that can be characterized
by an optimistic, a pessimistic, and a most likely estimate of its
durations.
The process of dividing a task into activities and activities into sub
activities should be performed carefully to strike a proper balance
between size and duration. The following guidelines are recommended:
• Critical activities that fall below this range should be included. For
example, a critical design review that is scheduled to last 2 days on a
3- year project should be included in the activity list because of its
pivotal importance.
• If the number of activities is very large (say, above 250), the project
should be divided into subprojects, and individual schedules
developed for each. Schedules with too many activities quickly
become awkward and are difficult to monitor and control.
Deterministic Approach
When past data for an activity similar to the one under
consideration are available and the variability in performance
is negligible, the duration of the activity may be estimated by
its mean; that is, the average time it took to perform the
activity in the past.
A problem arises when no past data exist. This problem is
common in organizations that do not have an adequate
information system to collect and store data, and in R&D
projects where an activity is performed for the first time.
To deal with this situation, three techniques are available: the
modular technique, the benchmark job technique, and the
parametric technique.
Deterministic Approach
Modular Technique
This technique is based on decomposing each activity into sub activities (or
modules), estimating the performance time of each module, and then
totaling the results to get an approximate performance time for the activity
Deterministic Approach
Parametric Technique
Stochastic Approach
Only in rare instances is the exact duration of a planned
activity is known in advance. Therefore, to gain an
understanding of how long it will take to perform an activity, it
is logical to analyze past data and to construct a frequency
distribution of related activity durations (distribution fitting).
Stochastic Approach
Example 5.4: For an activity repeated previously, the company has the
given frequency table. After building the frequency graph (given in the
previous slide), you realize that the data may be fitted into Normal
distribution due to its symmetry. Find the expected duration of activity
and its spread (standard deviation).
fi, frequency 1 2 4 4 6 8 5 3 3 2 1 1
xi, duration 10 15 20 25 30 35 40 45 50 55 65 70
Mode, the most frequently observed data
Stochastic Approach
Solution:
1 ∑ 1 × 10 + 2 × 15 + ⋯ + (1 × 70) 1410
= = = = = = 35.25
∑ (1 + 2 + ⋯ + 1) 40
1
= ( − )
Note: Sample dataset is comparatively a small portion of population dataset. Then, the sum of squares of errors should be divided into (n-1).
1 1
= ( − ) = ( − )
−1 −1
1(10 − 35.25) +2(15 − 35.25) + ⋯ + 1(70 − 35.25)
= = 176.86 → = 176.86 = 13.3
39
Stochastic Approach
While the normal distribution is symmetrical and easy to work
with, the distribution of activity durations is likely to be
skewed. Furthermore, the normal distribution has a long left
hand tail while actual performance time cannot be negative. A
better model of the distribution of activity lengths has proven
to be the beta distribution.
Stochastic Approach
In project scheduling by utilizing the PERT method,
probabilistic considerations are incorporated by assuming that
the time estimate for each activity can be derived from three
different values:
a= optimistic time, which will be required if execution goes extremely well
m= most likely time (mode), which will be required if execution is normal
b= pessimistic time, which will be required if everything goes badly
Statistically speaking, (a) and (b) are estimates of the lower and
upper bounds of the frequency distribution, respectively. If the
activity is repeated a large number of times, only in about 0.5%
of the cases would the duration fall below the optimistic
estimate, (a), or above the pessimistic estimate,(b). The most
likely time, m, is an estimate of the mode (the highest point) of
the distribution.
MinE424 - Project Management in Mining 37
5.4. Estimating the Duration of Project Activities
Stochastic Approach
To convert m, a, and b into estimates of the expected value E(x)
and variance (S2) of the elapsed time required by the activity,
two assumptions are made. The first is that the standard
deviation, s (square root of variance), equals one-sixth the
range of possible outcomes. The rationale for this assumption
is that the tails of many probability distributions (such as the
normal distribution) are considered to lie about 3 standard
deviations from the mean, implying a spread of about 6
standard deviations between tails (99% conf. interval for
normal distribution). In industry, statistical quality control
charts are constructed so that the spread between the upper
and lower control limits is approximately 6 standard
deviations.
−
=
6
MinE424 - Project Management in Mining 38
5.4. Estimating the Duration of Project Activities
Stochastic Approach
The second assumption concerns the form of the distribution
and is needed to estimate the expected value, E(x). In this
regard, the definition of the three time estimates above provide
an intuitive justification that the duration of an activity may
follow a beta distribution with its unimodal point occurring at
m and its end points at a and b.
+4 +
( )=
6
Three cases of the beta distribution: (a) symmetric;(b) skewed to the right: (c) skewed to the left
MinE424 - Project Management in Mining 39
5.5. Critical Path Method (CPM)
EET
When drawing a critical path diagram, it is
recommended to use node (event) circles with the
EET in the top right quadrant and the LET in the
bottom right quadrant.
Node label LET
Critical Path
It means that Activity E may start 9 Thus there is no slack or “spare” time in
weeks late, finish 9 weeks early or occupy activity D – if it starts late or the duration
9 weeks extra time without increasing the increases by any amount, the TPT will be
TPT (total project time). increased.
MinE424 - Project Management in Mining 43
5.5. Critical Path Method (CPM)
Critical Path
The activities with no slack/float/spare time are called critical activities. For
the diagram above, B, D, and H are critical activities where late start of
these activities or any increase in their durations affect the TPT (total project
time). Therefore, Activities B, D, and H which have zero float determine the
critical path.
Critical Path
There are two types of floats; the total float and the free float.
= − −
= − −
Where
Critical Path
The total float is the measure of time interval within which an activity
may be started providing all preceding activities are completed as early
as possible and all following activities are completed as late as possible.
The activities on a critical path have zero total floats.
The free float is the free time in scheduling that activity providing that
both its predecessor and its successor events take place as early as
possible.
The critical path is conventionally indicated by heavy dark or red
colored lines connecting the critical path.
It is also important to note that four simple factors characterize the
critical path:
• It starts at the first node.
• It is continuous.
• It ends at the last node.
• It has no floats.
MinE424 - Project Management in Mining 46