Professional Documents
Culture Documents
Project Scheduling
TRANSPARENCIES
0 A 6 6 B 11 Lag 4 15 C 22
Spec Design Design Check Blueprinting
6 5 7
10.2 FINISH TO FINISH NETWORK RELATIONSHIP
30 R 36
Wiring
31 S 33 33 T 36 36 U 42
Plumbing HVAC Interior Const.
2 3 6
10.3 START TO START NETWORK RELATIONSHIP
30 R 36
Wiring
33 T 36 36 U 42
3 days HVAC Interior Const.
3 6
31 S 33
Plumbing
2
10.4 START TO FINISH NETWORK RELATIONSHIP
20 W 26
6
3 days
20 Y 23 23 Z 29
3 6
18 X 20
2
10.5 BENEFITS OF GANTT CHARTS
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
10.7 SAMPLE TRACKING GANTT CHART WITH CRITICAL PATH A-C-D-F-H
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
10.8 GANTT CHART WITH RESOURCES IDENTIFIED FOR EACH TASK
Microsoft product screen shot(s) reprinted with permission from Microsoft Corporation.
10.9 CRASHING PROJECTS – UNDER WHAT
CONDITIONS?
f) Fast-tracking by:
g) Overtime
Crash
Point
Crashed
Cost
Normal
Point
Normal
Crashed Normal
Activity Duration
10.12 CRASHING ACTIVITIES – AN EXAMPLE
SUPPOSE:
8–5 3
10.13 SAMPLE AOA NETWORK DIAGRAM
A
1 2
4
10.14 PARTIAL AOA NETWORK ILLUSTRATING DUMMY ACTIVITIES
3
B
A
1 2
C
4
DISCUSSION QUESTIONS
10.1 Explain what the term “lag” means by explaining the differences between the four
logical relationships presented in this chapter:
a. Finish to start
b. Finish to finish
c. Start to start
d. Start to finish
A ‘lag’ represents a relationship between the start and finish of one activity to another.
They allow project managers to demonstrate some flexibility within the network diagram
(for example, if task A [5 day duration] was a predecessor task to task B, and it was
noted that task B could start 2 days after task A had started, a lag would be use to
highlight this within the network diagram). The following demonstrates the different
relationships and lag can be added to these.
a. Finish to start activities – Task does not start until a previous task has finished.
b. Finish to finish activities – Requires two linked activities to share a similar finish
point.
c. Start to start activities – Two activities can start at the same time or later task does
not start until a previous task has started.
d. Start to finish – Successors finish is dependent upon a predecessors start.
10.2 Explain how Gantt charts are used. What are the benefits of using this planning
tool?
Gantt charts are used as an alternative tool for project managers to create the project
network and organize tasks. Project tasks feature down the left hand side of the chart,
with the time displayed across the top. Each task is represented by a bar and
dependencies represented by arrows. Project managers are also able to illustrate
milestones on the Gantt chart. An additional feature of Gantt charts is the ability to use it
as a tracking tool.
The main benefits of using Gantt charts are that they are easy to create, they act as a live
document and can be easily updated to show the progress of tasks. Another benefit of
Gantt charts is the ability for project managers to create a ‘baseline’ so it is clear for team
members to identify when tasks should start and finish, with their current status
illustrated. Resources can also be easily allocated to the Gantt chart and therefore it
enables the Project Manager to create, allocate and load/level resources as part of the
planning process.
10.3 What are the advantages in the use of Gantt charts over PERT diagrams? In what
ways might PERT diagrams be advantageous?
Gantt charts display the project baseline. Each activity can then easily be referenced at
any point during the project to see if progress is on target. Gantt charts are also more
useful because the use of resources can be added to the charts. Finally, Gantt Charts are
visually appealing and easily understandable. PERT diagrams offer a means to convey
complex network relationships more completely and make the identification of
predecessor and successor relationships easy to recognize.
10.4 How do concepts such as Brook’s Law and the effects of sustained overtime cause
us to rethink the best ways to accelerate a project? Is it particularly ironic that these
“acceleration” efforts can actually lead to serious delays?
not to rely too heavily on overtime, as the more hours of sustained overtime required per
week of resources, the lower their overall productivity, due to fatigue and fatigue-induced
errors requiring rework. The irony is that some of the most widely-used methods to
accelerate a project are actually common causes of project delays.
Crashing may be desirable if initial time estimates are inaccurate, the project falls behind
schedule, or the project completion date is moved up. n these cases, the project cannot be
completed on time given the original schedule. Crashing would expedite the
project/activities to meet new completion dates. Another scenario occurs when late fees
or penalties may be incurred. It may be more cost effect to crash activities than to pay the
additional fees.
10.6 In crashing a project, we routinely focus on those activities that lie on the critical
path, not activities with slack time. Explain why this is the case.
The critical path is the longest path through the network. Crashing activities on the
critical path reduces the overall project duration time. Crashing activities outside of the
CP (those with slack time) will increase overall costs, but only reduce the time to
complete that single activity, not the overall time of the project. Therefore, it is more
efficient, when trying to expedite the entire project, to crash activities that lie on the CP.
10.7 What are some of the advantages in the use of AOA notation as opposed to AON?
Under what circumstances does it seem better to apply AON methodology in network
development?
Advantages of the AOA notation include: its prevalence in some specialized business
fields; its clearer depiction of complex projects; and event nodes/milestones in AOA are
easier to identify. The AON methodology is more suitable when there are several merge
points within the network. Merges make AOA notation convoluted (requiring the use of
dummy activities) due to tasks being listed on arrows connecting activities in the
diagram. AON is also more applicable when computer scheduling is desired because
AON notation is used in most PM computer software packages.
10.8 Explain the concept of the forward and backward pass calculations in AON. Why
does the calculation need to be done in this way?
The calculation for determining the critical path and any float or slack using AON is the
forward and backward pass. The forward pass is the process of moving forward through
the network to calculate the total expected duration of the project. Moving backward
through the network allows the project manager to identify slack or float associated with
project tasks and the critical path. Trying to go back to the start of the network diagram to
calculate slack or float will result in an inaccurate critical path and calculation.
10-21
10.9 “Networks can become too large and complex to be meaningful.” Do you agree or
disagree with this statement? Justify your answer.
This question should encourage debate amongst students in relation to the size and
complexity of projects and how they are illustrated within a project network. For larger
projects, there are actions a project manager can take to try and reduce the level of
complexity associated with network diagrams. Scaling the time associated with particular
components of the project will help team members to follow network diagrams more
easily. For example, if working on a four year project, you may detail the network
diagram in terms of days or weeks for the first 6/7 months (or according to the first
milestone), with the remainder of the project represented as months. It is debatable as to
whether a project manager can plan in a specific level of detail for a four year project
(especially in dynamic project environments where change in scope is a likely factor).
PROBLEMS
10.1 Suppose you are a project manager and have been asked to develop the network
activity diagram and identify the critical path for a project based on the following
information. Draw the activity network as a Gantt chart. What is the expected
duration of the project?
10.3 Reconfigure the Gantt chart in problem 2 to include some different predecessor
relationships.
a. Assume that activities B and C are linked with a “finish to finish” relationship.
Does that change the expected completion date for the project?
b. For activity F, add a lag of three days to its predecessor relationship with
activity D. By adding the 3-day lag to F, what is the new expected duration for
the project?
c. Suppose you now added a start to start relationship between activities F and G
to the new Gantt chart. How does this additional relationship change the
expected completion date for the project?
10.4 Consider a project with the following information. Construct the project activity
network using AOA methodology and label each node and arrow appropriately.
Identify all dummy activities required to complete the network.
Normal Crashed
Activity Duration Cost Duration Cost
A 6 days $150 3 days $350
a. Complete the table. How many days would you advise the project should be
crashed? Why?
b. Suppose direct costs of crashing the project only increased $5,000 per day
crashed at a steady rate (starting with $125,000 on day 60). How many days
would you advise that the project be crashed? Show your work.