Professional Documents
Culture Documents
Developing
a Project Plan:
Preparing Schedule
1
11/3/2022
Network Analyses:
Critical Path Method (CPM) Analysis: It is used for the activities
having deterministic or Certain completion times (One time
estimate)
Program Evaluation and Review Technique (PERT) Analysis: It is
used for the activities having probabilistic or Uncertain completion
times (Three time estimate)
Graphical Evaluation and Review Technique(GERT) Analysis: It
is used in probabilistic network where there can be many
alternative paths and loops.
2
11/3/2022
3
11/3/2022
4
11/3/2022
USE OF LAGS
Finish-to-Start Relationship
Start-to-Start Relationship
USE OF LAGS
(CONT’D)
5
11/3/2022
USE OF LAGS
(CONT’D)
Finish-to-Finish
Relationship
Start-to-Finish
Relationship
Combination
Relationship
6
11/3/2022
HAMMOCK ACTIVITIES
Hammock Activity
Spans over a segment of a project.
Has a duration that is determined after the network plan is drawn.
Is used to aggregate sections of the project to facilitate getting the right
amount of detail for specific sections of a project.
Is very useful in assigning and controlling indirect project costs.
7
11/3/2022
PERT Analysis
PERT stands for Program Evaluation Review Technique
It was used in designing and producing major weapons
systems for the U.S. Military Establishment.
It is helpful in the projects where activities are subjected to
higher degree of Uncertainty in completion time thus It is
difficult to find the reasonable estimate for activity time due
to such uncertainty.
PERT estimates the expected activity time using three time
estimates using Beta Probability distribution.
15
PERT—PROGRAM EVALUATION
REVIEW TECHNIQUE
8
11/3/2022
9
11/3/2022
Example
10
11/3/2022
11
11/3/2022
HYPOTHETICAL NETWORK
HYPOTHETICAL NETWORK
(CONT’D)
12
11/3/2022
13
11/3/2022
14
11/3/2022
GERT : Motivation
30
15
11/3/2022
GERT : Motivation
31
32
16
11/3/2022
33
34
17
11/3/2022
35
36
18
11/3/2022
37
38
19
11/3/2022
KEY TERMS
Activity Gantt chart
Activity-on-arrow (AOA) Hammock activity
Activity-on-node (AON) Lag relationship
Burst activity Merge activity
Concurrent engineering Parallel activity
Critical path Sensitivity
Early and late times Total slack
Free slack
Questions?
hasmukh@iimidr.ac.in
40
20