You are on page 1of 20

11/3/2022

Developing
a Project Plan:
Preparing Schedule

WHERE WE ARE NOW

1
11/3/2022

DEVELOPING THE PROJECT PLAN


The Project Network
A flow chart that graphically depicts the sequence, interdependencies,
and start and finish times of project activities
o Provides the basis for scheduling labor and equipment.
o Enhances communication among project participants.
o Provides an estimate of the project’s duration.
o Provides a basis for budgeting cash flow.
o Identifies activities that are critical.
o Highlights activities that are “critical” and can not be delayed.
o Help managers get and stay on plan.

Network Analyses:
Critical Path Method (CPM) Analysis: It is used for the activities
having deterministic or Certain completion times (One time
estimate)
Program Evaluation and Review Technique (PERT) Analysis: It is
used for the activities having probabilistic or Uncertain completion
times (Three time estimate)
Graphical Evaluation and Review Technique(GERT) Analysis: It
is used in probabilistic network where there can be many
alternative paths and loops.

2
11/3/2022

Steps for CPM Analysis:


STEP 1: Draw the Network Diagram.
STEP 2: Forward Pass Calculations:
 Compute Early Start Time (EST) and Early Finish Time (EFT) for each activity.
STEP 3: Backward Pass Calculations:
 Compute Late Start Time (LST) and Late Finish Time (LFT) for each activity.
STEP 4: Compute Total Float for each activity
STEP 5: Find out the Critical Activities.
STEP 6: Find out the Critical Path
STEP 7: Compute the Project Duration.

Practice Problem: GREENDALE STADIUM CASE

3
11/3/2022

EXTENDED NETWORK TECHNIQUES


TO COME CLOSE TO REALITY
Laddering
Activities are broken into segments so the following
activity can begin sooner and not delay the work.
Lags
The minimum amount of time a dependent activity
must be delayed to begin or end.
o Lengthy activities are broken down to reduce the delay
in the start of successor activities.
o Lags can be used to constrain finish-to-start, start-to-start,
finish-to-finish, start-to-finish, or combination relationships.

EXAMPLE OF LADDERING USING


FINISH-TO-START RELATIONSHIP

4
11/3/2022

USE OF LAGS
Finish-to-Start Relationship

Start-to-Start Relationship

USE OF LAGS
(CONT’D)

Use of Lags to Reduce


Project Duration

5
11/3/2022

USE OF LAGS
(CONT’D)

Finish-to-Finish
Relationship

Start-to-Finish
Relationship

Combination
Relationship

NETWORK USING LAGS

6
11/3/2022

HAMMOCK ACTIVITIES
Hammock Activity
Spans over a segment of a project.
Has a duration that is determined after the network plan is drawn.
Is used to aggregate sections of the project to facilitate getting the right
amount of detail for specific sections of a project.
Is very useful in assigning and controlling indirect project costs.

HAMMOCK ACTIVITY EXAMPLE

7
11/3/2022

PERT Analysis
PERT stands for Program Evaluation Review Technique
It was used in designing and producing major weapons
systems for the U.S. Military Establishment.
It is helpful in the projects where activities are subjected to
higher degree of Uncertainty in completion time thus It is
difficult to find the reasonable estimate for activity time due
to such uncertainty.
PERT estimates the expected activity time using three time
estimates using Beta Probability distribution.

15

PERT—PROGRAM EVALUATION
REVIEW TECHNIQUE

Assumes each activity duration has a range


that statistically follows a beta distribution.
Uses three time estimates for each activity:
optimistic, pessimistic, and most likely to
represent activity durations.
Knowing the weighted average and variances for
each activity allows the project planner to compute
the probability of meeting different project durations.

8
11/3/2022

ACTIVITY AND PROJECT


FREQUENCY DISTRIBUTIONS

ACTIVITY TIME CALCULATIONS


The weighted average activity time is computed by
the following formula:

9
11/3/2022

ACTIVITY TIME CALCULATIONS


(CONT’D)

The variability in the activity time estimates is


approximated by the following equations:
The standard deviation for the activity:

The standard deviation for the project:

Note the standard deviation of the activity is squared in this equation;


this is also called variance. This sum includes only activities on the
critical path(s) or path being reviewed.

Example

10
11/3/2022

ACTIVITY TIMES AND VARIANCES

PROBABILITY OF COMPLETING THE


PROJECT
The equation below is used to compute the “Z” value found in
statistical tables (Z = number of standard deviations from the
mean), which, in turn, tells the probability of completing the
project in the time specified.

11
11/3/2022

HYPOTHETICAL NETWORK

HYPOTHETICAL NETWORK
(CONT’D)

12
11/3/2022

POSSIBLE PROJECT DURATION


Probability project is completed before scheduled time (TS) of 67 days

Z VALUES AND PROBABILITIES

13
11/3/2022

Practice Problem: Consolidation Project

Compute the expected project duration and its variance.

Practice Problem: Consolidation Project

What is the probability of completing the project in 116 days ?

14
11/3/2022

Practice Problem: Consolidation Project

What is the probability of completing “Negotiate with Unions” by day 90?

GERT : Motivation

30

15
11/3/2022

GERT : Motivation

31

GERT: Output Side Symbols

32

16
11/3/2022

GERT: Input Side Symbols

33

GERT: Few Examples

34

17
11/3/2022

GERT: Few Examples

35

GERT: Few Examples

36

18
11/3/2022

GERT: Few Examples

37

GERT : Space Company Example

38

19
11/3/2022

KEY TERMS
Activity Gantt chart
Activity-on-arrow (AOA) Hammock activity
Activity-on-node (AON) Lag relationship
Burst activity Merge activity
Concurrent engineering Parallel activity
Critical path Sensitivity
Early and late times Total slack
Free slack

Questions?
hasmukh@iimidr.ac.in

40

20

You might also like