Project Management Project Scheduling
Course Structure
Introduction
Projects and Strategy
Project Selection and Portfolio Management
Project Cost Estimation and Budgeting
Project Scheduling: Networks, Duration estimation, and Critical
Path
Project Scheduling: Lagging, Crashing and Activity Networks
Risk Management
Resource Management
Project Evaluation and Control
Agile Project Management
Critical Chain Project Scheduling
Project Management Project Scheduling
0 A 6 6 B 11 Lag 4 15 C 22
Spec Design Design Check Blueprinting
6 5 7
10-4
Project Management Project Scheduling
31 A 33 33 B 36 36 C 42
Plumbing HVAC Inspection
2 3 6
10-5
Project Management Project Scheduling
30 D 36
Wiring
6
Lag 3
33 B 36 36 C 37
31 A 33 HVAC Inspection
Plumbing 5 1
6 10-6
Project Management Project Scheduling
22 A 28 28 B 33 33 C 34
Plumbing HVAC Inspection
6 5 1 10-7
Project Management Project Scheduling
10-8
Project Management Project Scheduling
Gantt Charts
Task ES EF LS LF
Task Time Pred Task Time Pred Z 0 8 0 8
Z 8 -- U 3 W Y 8 13 11 16
X 8 16 8 16
Y 5 Z T 6 V
W 16 20 16 20
X 8 Z S 7 U,T V 20 25 20 25
U 20 23 28 31
W 4 Y,X R 9 S
T 25 31 25 31
V 5 W S 31 38 31 38
R 38 47 38 47
10-10
Project Management Project Scheduling
Gantt Chart With Resources in MS Project
10-11
Project Management Project Scheduling
Crashing
10-12
Project Management Project Scheduling
Crashing
• Project duration can be reduced by assigning
more resources to project activities. But, doing
this would somehow increase our project cost!
10-13
Project Management Project Scheduling
Crashing
2 6(3)
5 (1)
3
1
5(0)
10-16
Project Management Project Scheduling
Crashing
4(0) 3(0)
2 6(3)
5 (1)
3
1
5(0)
If we used all 4 days, then path 1-2-3 has
(5-1) + (6-3) = 7 completion weeks
Now, we need to check if the completion time for path 1-3 has lesser than 7
weeks (why?)
Now, path 1-3 has (5-0) = 5 weeks
Since path 1-3 still shorter than 7 weeks, we used up all 4 crashed weeks
• We can only reduce total time for path 1-2-3 = path 1-3, that is
8 weeks
• If the cost for path 1-2 and path 2-3 is the same then we can
random pick them to crash so that its completion time is 8
weeks
10-19
Project Management Project Scheduling
TIME-COST TRADE-OFF
Slope = crash cost – normal cost
normal time – crash time
Crash point
Normal point
Solution
32,000 −12,000 20,000
or = 10,000 per week
5 −3 2
10-21
Project Management Project Scheduling
Example
Find the minimum possible time of the project and the cost
associated with this.
Project Management Project Scheduling
Solution
10-23
Project Management Project Scheduling
Solution
Solution