Professional Documents
Culture Documents
Schedule Precedence
Management Plan. Diagramming
Activity List Method(PDM) Project Schedule
Activity Network Diagram
Attributes Dependency
Determination
Project Scope
Statement PMIS
EEFs
OPAs Leads & Lags
Mandatory Dependencies :
-- The order in which activities MUST be done, due to the inherent
nature of the work; also called "hard logic" .
Discretionary Dependencies :
--The order in which the organization has CHOSEN that activities be
performed; also called "preferred;' "preferential;' or "soft logic" .
External Dependencies:
--Dependencies based on the needs of a party OUTSIDE the project .
--Regulatory dependencies .
Internal Dependencies:
--Dependencies based on the needs of the project; may be under the
control of the project team .
Cont.
PERT/ Time & PERT/Cost
PERT is a management tool for defining and integrating events; a process
which must be accomplished in time to assure completing project objectives
on schedule.
Objectives: PERT’s objectives are: To provide, through applying an
integrated management information system (which contains a balanced
combination of the basic elements of time, cost, and performance),
coordinated planning and control information at the proper levels so that
timely managerial judgments will meet all established project objectives.
Scheduling may be defined as translating a project plan into a timetable
with specific calendar dates governing the beginning and completion of all
project efforts. Scheduling is a way of realistically timing a project and its
inherent activities. It calls for skill and knowledge of the time and resource
requirements of all activities and their relevant capacities and efficiencies.
Scheduling is the manager’s way of determining the resources required by
several (perhaps competing) projects
Critical Path : The longest path through the network diagram with Zero Float
It shows the project manager the shortest time in which the project can be
completed .
It shows the project manager where to focus his or her time .
Backwards Pass
o The next step is to calculate the latest dates at which each of the activities can
start and finish. The process of doing this is called a backward pass.
o The formula for calculating late start is 𝐥𝐟 − d + 1 = 𝐥𝐬
o The formula for calculating late finish of the predecessor activity is 𝐥𝐬𝐬 − 1 = 𝐥𝐟𝐩
o Total float (tf) - the time an activity may be delayed or extended without
affecting the total project duration or violating a target finish date.
o Free float (ff) – the time an activity may be delayed or extended without
affecting the start of a successor activity.
LS LF LS LF LS LF
Critical Chain Method is a schedule network analysis tool that builds in buffers at
critical milestones .
The critical chain method (CCM) is a schedule method that allows the project
team to place buffers on any project schedule path to account for limited
resources and project uncertainties.
Project Buffer : One buffer, placed at the end of the critical chain, is known
as the project buffer and protects the target finish date from slippage along the
critical chain.
Feeding Buffer : Additional buffers known as feeding buffers which are
placed at each point where a chain of dependent activities that are not on the critical
chain feeds into the critical chain.
Feeding buffers thus protect the critical chain from slippage along the feeding chains.
Crashing &
Fast tracking .
Crashing :
Adding or adjusting resources in order to compress the schedule while
maintaining the original project scope .
Crashing works only for activities on the critical path.
Crashing may result in increased risk and/or cost.
Fast tracking :
Compressing the schedule by doing more critical path activities in parallel.
Fast tracking may result in rework and increased risk.
PROCUREMENT MANAGEMENT 26
Types of Contracts
Fixed Price Contracts : This category of contracts involves setting a fixed total price
for a defined product, service, or result to be provided.
Time & Materials Contracts :Time and material contracts are a hybrid type of
contractual arrangement that contain aspects of both cost-reimbursable and fixed-
price contracts
PROCUREMENT MANAGEMENT 27
FIXED –PRICED CONTRACTS
PROCUREMENT MANAGEMENT 28
COST – REIMBURSABLE CONTRACTS
Payment to the sellers for all legitimate actual cost incurred , plus a fee.
PROCUREMENT MANAGEMENT 29
TIME AND MATERIAL CONTRACTS ( T & M)
Staff augmentation
Acquisition of experts,
Any outside support
Schedule Variance
Schedule Variance is the difference between Earned Value (EV) and Planned Value (PV).
Schedule Variance = Earned Value – Planned Value
SV = EV – PV
Cost Variance
Cost Variance is the difference between Earned Value (EV) and Actual Cost (AC).
Cost Variance = Earned Value – Actual Cost
CV = EV – AC
CPI = EV/AC
BAC = $10000
AC= $3,500
PV= BAC * %Work Planned = 10,0000 * 60% = 10,0000 * 60/100= $6000
EV=BAC* % Actual Work Performed = 10000 * 40/100 = 4000
SV= EV – PV = 4000 – 6000 = (-2000)
CV = EV – AC = 4000 – 3500 = 500
SPI= EV / PV = 4000 / 6000 = 4/6 = .67
CPI = EV / AC = 4000 / 3500 = 1.14