DETAILS OF THE COURSE


Subject IT Project Management Code COM 3053
Pre-requisite Subject - Code -
Programme BBA (Hons) In Technology Management
Year / Semester Year 3 / Semester 6 Session 2010/2011

TOPICS
Weeks Details Hours
L T Lab
1 Introduction to IT project management 2 1 -
- What is a Project
- What is Project Management
- Relation to Other Management Disciplines
- Related endeavors
2 The Project Management and Information Technology 2 1 -
Context
- Project Phases and the Project Life Cycle
- Project Stakeholders
- Organization Influence
- Key General Management Skills
- Social-Economic-environmental Influences
3 The Project Management Process Groups 2 1 -
- Project Processes
- Process Group
- Process Interactions
- Customizing Process Interactions
- Mapping of Project Management Processes
4 Project Integration Management 2 1 -
- Project Plan Development
- Project Plan Execution
- Integration Change Control

Quiz 1 (5%)
5 Project Scope Management 2 1 -
- Initiation
- Scope Planning
- Scope Definition
- Scope Verification
- Scope Change Control
6 Project Time Management 2 1 -
- Activity Definition
- Activity Sequencing
- Activity Duration Estimating
- Schedule Development
- Schedule Control
7 Project Cost Management 2 1 -
- Resource Planning
- Cost Estimating
- Cost Budgeting
- Cost Control
8 Submission of group assignments (10%)
Mid-term examination (10%)
9 Project Quality Management 2 1 -
- Quality Planning
- Quality Assurance
- Quality Control
10 Project Human Resource Management 2 1 -
- Organizational Planning
- Staff Acquisition
- Team Development
11 Project Communications Management 2 1 -
- Communications Planning
- Information Distribution
- Performance Reporting
- Administrative Closure

Quiz 2 (5%)
12 Project Risk Management 2 1 -
- Risk Management Planning
- Risk Identification
- Qualitative Risk Analysis
- Quantitative Risk Analysis
- Risk Response Planning
- Risk Monitoring and Control
13 Project Procurement Management 2 1 -
- Procurement Planning
- Solicitation Planning
- Solicitation
- Source Selection
- Contract Administration
- Contract Closeout
14 Submission of individual assignments & Presentations
(15%)
15 Revision for the exam
16 Final Examination (40%)

Text Books
1. Kathy Schwalbe, (2007) Information Technology Project Management, Sixth Edition
2. Jack T. Marchewa, (2003) Information Technology Project Management : Providing Measureable
Organization Value, Second Edition
Assessment
Bil. Type of Assessment Topic of the Week Date Percentage
Assessment
1. Quiz 1 Topic 1-3 4 5%
2. Quiz 2 Topic 8 - 10 11 5%
3. Midterm Topic 1-7 8 10%
4. Final Exam All chapters 16 40%
5. Group Assignment Topic will 8 10%
related with
subject
6. Individual Assignment + Topic will 14 15%
Presentation related with
subject
7. Tutorial All topics Every week 5%
8. Attendance - Every week 5%
9. Class Participation In class activity Every week 5%
TOTAL 100%

Policy
Lecturer Monalissa Muharam
Department / Faculty / Centre Faculty of Business and Finance
Telephone No. 012-7320765
Email monalissa.muharam@yahoo.com
Website http://www.alphaitsubjects.blogspot.com/

Prepared by Checked by Approved by


Signatures
Name Monalissa Bt. Muharam Ramlah Bt. Karsan Hashim B. Haron
Post Lecturer Academic Coordinator / Assistant Chief
Lecturer Executive Officer