PT. REKAYASA INDUSTRI REV.

0 1 2
PROJECT : RCC OFFGAS TO PROPYLENE PROJECT BY KHO
CLIENT : PT PERTAMINA CHKD AHP
JOB NO. : 081803 APPVD SGH
REKAYA
SA DOC NO. : ROP-E-2153-001-R-E-0 DATE 19-Aug-08
TECHNICAL BID EVALUATION
SHELL AND TUBE HEAT EXCHANGER AND DOUBLE PIPE HEAT EXCHANGER
NO. DESCRIPTION UNIT REKAYASA'S
PT SURYA BESINDO SAKTI
REQUIREMENT
###
1 VENDOR PT. SURYA BESINDO SAKTI
###
2
###
3 MECHANICAL DESIGN
###
4 Code - ASME VIII Div 1, TEMA Class R ASME VIII Div 1, TEMA Class R ü
###
5 Code Stamp "U" - No No ü
###
6 Item No. 34-A-102-E-101A/B, stacked 34-A-102-E-101A/B, stacked ü
7 Description SWS Feed Bottom Exchanger, sour service onSWS
tubeside
Feed Bottom Exchanger, sour service on tubeside
ü
8 Quantity Nos 2.00 2 ü
9 Exchanger Type H - AES H - AES ü
###
10 Operating Pressure (shell/tube) Kg/Cm2G 1.85 / 6.5 1.85 / 6.5 ü
###
11 Operating Temperature o
C 127.5 / 90 127.5 / 90 ü
###
12 Design Pressure (shell) Kg/Cm2G 4 4 ü
13 Design pressure (tube) 11 11 ü
###
14 Design Temperature (shell/tube) o
C 150 / 110 150 / 110 ü
###
15 Min Thickness Shell
16 Shell mm 10 9.52 ü
17 Channel cylinder mm 5 6.35 ü
18 Channel cover mm 31 32 ü
19 Front head mm 10 9.52 nom ü
20 Shel cover mm 10 12.7 ü
21 Tie rod diameter mm 10 ü
22 Partition plate mm 7 10 ü
23 Fixed Tubesheet mm 25 26 ü
24 Floating tubesheet mm 25 26 ü
###
25 Tube (OD / Thickness) mm 19.05 / 1.651 19.05 / 1.651 ü
###
26 Inside Diameter of shell mm 410 410 ü
###
27 Length of shell tube mm 6000 6000 ü
28 Number of tube 312, total for two exchanger 156/Shell (312, total for two exchanger) ü
29 Baffle spacing mm 300, for each shell 300, for each shell ü
30 Number of tie rod - 6, for each exchanger 6, for each exchanger ü
###
31 Radiography (shell/tube) - ( Spot / Full) ( Spot / Full) ü
32 Radiography floating head - 100% 100% ü
###
33 Joint Efficiency (Shell/ tube) - 0.85 / 1.00 0.85 / 1.00 ü
###
34 Corrosion Allowance (shell / tube) mm 3/0 3/0 ü
###
35 PWHT (Shell / Tube / floating head) - No / No / No No / No / No ü
###
36 Stress Relieve for U Tube - N/A N/A ü
37 Nozzle Rating (shell / tube) - 150# / 150# 150# / 150# ü
38 Charpy Impact Test - N/A N/A ü
###
39 Support Type - Saddle Saddle ü
###
40 Strength Guarantee - YES YES ü
###
41 Hydrostatic Test - As per code As per code (to Detail Later) ü
###
42 Material for all internal part - Same quality with Vessel Material Same quality with Vessel Material ü
###
43 Standard Drawing - Vendor to be comply with Rek's Standard Dwg
Yes comply with Rek's Standard Dwg for Vesselü
44
### Lifting Lug calculation - for Yes
Vessel Yes ü
###
45 Type of Nozzle - WNRF WNRF ü
###
46 Stacked Exchanger - Yes Yes ü
47 Tube to tubesheet - Light expand and seal welded Light expand and seal welded ü
48 Impingement N/A N/A ü
###
49 MATERIAL SPECIFICATION SA- (ASME) MATERIAL SA- (ASME) MATERIAL ü
###
50 Shell - SA 516 Gr 60N SA 516 Gr 70 ü
###
51 Tube - SA 213 TP 304 (seamless) SA 213 TP 304 (seamless) ü
52 Tubesheet (fixed / floating) - SA 336 F304 / SA 336 F 304 SA 336 F304 / SA 336 F 304 ü
53 Channel cylinder - SA 240 304 SA 240 304 ü
54 Channel cover - SA 336 F 304 SA 336 F 304 ü
55 Shell cover - SA 516 Gr 70 SA 516 Gr 70 ü
56 Partition Plate - SA 240 304 SA 240 304 ü
57 Flanges -
58 Channel cover - SA 336 F304 SA-182-F304 ü
59 Girth flanges - SA 336 F 304 SA-182-F304 ü
###
60 Nozzle for shell side -
###
61 - Pipe - SA 106 Gr B SA 106 Gr B ü
###
62 - Flange - SA 105 SA 105 ü
63 Nozzle for tube side -
64 - Pipe - SA 240 304 SA 240 304 ü
65 - Flange - SA 182 304 SA 182 304 ü
###
66 Reinforcement Pad on Saddle - SA 516 Gr 70 SA 516 Gr 70 ü
###
67 Reinforcement pad on Nozzle - Same as channel/shell material Same as channel/shell material ü
###
68 Saddle - SA 283 C SA 283 C ü
###
69 Bolt / Nut : -
###
70 - Internal - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
###
71 - External - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
72
### Gasket for girth flanges - Metal Jacketed with SS 304 Metal Jacketed with SS 304 ü
73
### Gasket for shell and channel Nozzle - Spiral wound with inner and outer ring SS 304
Spiral wound with inner and outer ring SS 304
###
74 Name Plate - YES, SS YES, SS ü
###
75 Liner Plate - YES YES ü
###
76 Anchor Bolt / Fondation bolt - SA 307 B/ SA 563 A SA 307 B/ SA 563 A ü
###
77 Backing device - SA 336 F 304 SA-182-F304 ü
78 Expansion joints - N/A N/A ü
79 Tie Rod - SA 36 / SA 53 Gr B SA 36 / SA 53 Gr B ü
80
###
81 PACKING AND SHIPPING
###
82 Preparation for shipment - Refer to Specification Refer to Specification ü
###
83 Shipping mark - Yes Yes ü
###
84 Approval before shipping - YES YES ü
###
85 Dessiccant internal protection - Yes Yes ü
###
86 Protection device from load/unload - Yes Yes ü
###
87 Special Tools - By vendor (if any) By vendor (if any) ü
88 PMI for alloy material Yes Yes
###
89
###
90 COATING / PAINTING
###
91 External (Primer, intermediate, top coat) Yes, as painting spect Yes, as painting spect ü
###
92 Internal Coating No No ü
###
93 Touch up painting Yes (5%), shell side Yes (5%), shell side ü
###
94
###
95 SCHEDULE
###
96 Delivery Term - Ex Work, Free on Truck comply ü
###
97 Delivery Time Week 36 weeks comply ü
###
98
### ABBREVIATION: ACCEPTABILITY:
### ü Comply with requirement A: acceptable
### DA Deviation accepted B: acceptable with note A
### X Deviation not accepted C: not acceptable
### ? To be clarified
### → Follow with requirement
Note

Page 7 of 16
PT. REKAYASA INDUSTRI REV. 0 1 2
PROJECT : RCC OFFGAS TO PROPYLENE PROJECT BY KHO
CLIENT : PT PERTAMINA CHKD AHP
JOB NO. : 081809 APPVD SGH
REKAYA
SA DOC NO. : ROP-E-2153-001-R-E DATE 19-Aug-08
TECHNICAL BID EVALUATION
SHELL AND TUBE HEAT EXCHANGER AND DOUBLE PIPE HEAT EXCHANGER
NO. DESCRIPTION UNIT REKAYASA'S
PT SURYA BESINDO SAKTI
REQUIREMENT
###
1 VENDOR PT. SURYA BESINDO SAKTI
###
2
###
3 MECHANICAL DESIGN
###
4 Code - ASME VIII Div 1, TEMA Class R ASME VIII Div 1, TEMA Class R ü
###
5 Code Stamp "U" - No No ü
###
6 Item No. 34-A-102-E-102 34-A-102-E-102 ü
7 Description SWS Side Reflux Cooler, sour service on shell
SWS side
Side Reflux Cooler, sour service on shell side
ü
8 Quantity Nos 1.00 1 ü
9 Exchanger Type H - AES H - AES ü
###
10 Operating Pressure (shell/tube) Kg/Cm2G 3.61 / 3.5 3.61 / 3.5 ü
###
11 Operating Temperature o
C 120 / 45 120 / 45 ü
###
12 Design Pressure (shell) Kg/Cm2G 8.00 8 ü
13 Design pressure (tube) 7.5 / FV 7.5 / FV ü
###
14 Design Temperature (shell/tube) o
C 150 / 120 150 / 120 ü
###
15 Min Thickness Shell
16 Shell mm 7 9.52 ü
17 Channel cylinder mm 12 12.7 ü
18 Channel cover mm 62 52 ü
19 Front head mm 12 12.7 ü
20 Shel cover mm 12 12.7 ü
21 Tie rod diameter mm 13 ü
22 Partition plate mm 13 13 ü
23 Fixed Tubesheet mm 44 44 ü
24 Floating tubesheet mm 44 44 ü
###
25 Tube (OD / Thickness) mm 25.4 / 1.651 25.4 / 1.651 ü
###
26 Inside Diameter of shell mm 845 845 ü
###
27 Length of shell tube mm 6000 6000 ü
28 Number of tube 450 450 ü
29 Baffle spacing mm 250 250 ü
30 Number of tie rod - 8 8 ü
###
31 Radiography (shell/tube) - ( 100% / spot) ( 100% / spot) ü
32 Radiography floating head - 100% 100% ü
###
33 Joint Efficiency (Shell/ tube) - 1 / 0.85 1 / 0.85 ü
###
34 Corrosion Allowance (shell / tube) mm 0/3 0/0 ü
###
35 PWHT (Shell / Tube / floating head) - No / No / No No / No / No ü
###
36 Stress Relieve for U Tube - N/A N/A ü
37 Nozzle Rating (shell / tube) - 150# / 150# 150# / 150# ü
38 Charpy Impact Test - N/A N/A ü
###
39 Support Type - Saddle Saddle ü
###
40 Strength Guarantee - YES YES ü
###
41 Hydrostatic Test - As per code As per code ü
###
42 Material for all internal part - Same quality with Vessel Material Same quality with Vessel Material ü
###
43 Standard Drawing - Vendor to be comply with Rek's Standard Dwg
Yes comply with Rek's Standard Dwg for Vessel
ü
44
### Lifting Lug calculation - for Yes
Vessel Yes ü
###
45 Type of Nozzle - WNRF WNRF ü
###
46 Stacked Exchanger - No No ü
47 Tube to tubesheet - Light expand and seal welded Light expand and seal welded ü
48 Impingement Protection Yes, plate rectangular Yes, plate rectangular ü
###
49 MATERIAL SPECIFICATION SA- (ASME) MATERIAL SA- (ASME) MATERIAL ü
###
50 Shell - SA 240 304 SA 240 304 ü
###
51 Tube - SA 213 TP 304 (seamless) SA 213 TP 304 (seamless) ü
52 Tubesheet (fixed / floating) - SA 336 F 304 / SA 336 F 304 SA 336 F 304 / SA 336 F 304 ü
53 Channel cylinder - SA 516 Gr 70 SA 240 304 ü
54 Channel cover - SA 516 Gr 70 SA 336 F304 ü
55 Shell cover - SA 240 304 SA 240 304 ü
56 Partition Plate - SA 516 Gr 70 SA 240 304 ü
57 Flanges -
58 Channel cover - SA 224 Cl 4 SA 336 F304 ü
59 Girth flanges - SA 336 F 304 SA 336 F 304 ü
###
60 Nozzle for shell side -
###
61 - Pipe - SA 312 TP 304 SA 312 TP 304 ü
###
62 - Flange - SA182 F 304 SA 336 F 304 ü
63 Nozzle for tube side -
64 - Pipe - SA 106 Gr B SA 312 TP304 ü
65 - Flange - SA 105 SA 182 F304 ü
###
66 Reinforcement Pad on Saddle - SA 240 304 SA 240 304 ü
###
67 Reinforcement pad on Nozzle - same as shell/channel material same as shell/channel material ü
###
68 Saddle - SA 283 C SA 283 C ü
###
69 Bolt / Nut : -
###
70 - Internal - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
###
71 - External - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
72
### Gasket for girth flanges - Metal Jacketed with SS 304 Metal Jacketed with SS 304 ü
73
### Gasket for shell and channel Nozzle - Spiral wound with inner and outer ring SS 304
Spiral wound with inner and outer ring SS 304
ü
###
74 Name Plate - YES, SS YES, SS ü
###
75 Liner Plate - YES YES ü
###
76 Anchor Bolt / Fondation bolt - SA 307 B/ SA 563 A SA 307 B/ SA 563 A ü
###
77 Backing device - SA 336 F 304 SA 336 F 304 ü
78 Expansion joints - N/A N/A ü
79 Tie Rod - SA 312 TP 304 / SA 479 304 SA 312 TP 304 / SA 479 304 ü
80
###
81 PACKING AND SHIPPING
###
82 Preparation for shipment - Refer to Specification Refer to Specification ü
###
83 Shipping mark - Yes Yes ü
###
84 Approval before shipping - Yes Yes ü
###
85 Dessiccant internal protection - Yes Yes ü
###
86 Protection device from load/unload - Yes Yes ü
###
87 Special Tools - By vendor (if any) By vendor (if any) ü
88 PMI for alloy material Yes Yes
###
89
###
90 COATING / PAINTING
###
91 External (Primer, intermediate, top coat) Yes, as painting spect Yes, as painting spect ü
###
92 Internal Coating No No ü
###
93 Touch up painting Yes (5%), shell side Yes (5%), shell side ü
###
94
###
95 SCHEDULE
###
96 Delivery Term - Ex Work, Free on Truck comply ü
###
97 Delivery Time Week 36 weeks comply ü
###
98
### ABBREVIATION: ACCEPTABILITY:
### ü Comply with requirement A: acceptable
### DA Deviation accepted B: acceptable with note A
### X Deviation not accepted C: not acceptable
### ? To be clarified
### → Follow with requirement
Note

Page 8 of 16
PT. REKAYASA INDUSTRI REV. 0 1 2
PROJECT : RCC OFFGAS TO PROPYLENE PROJECT BY KHO
CLIENT : PT PERTAMINA CHKD AHP
JOB NO. : 081803 APPVD SGH
REKAYA
SA DOC NO. : ROP-E-2153-001-R-E DATE 19-Aug-08
TECHNICAL BID EVALUATION
SHELL AND TUBE HEAT EXCHANGER AND DOUBLE PIPE HEAT EXCHANGER
NO. DESCRIPTION UNIT REKAYASA'S
PT SURYA BESINDO SAKTI
REQUIREMENT
###
1 VENDOR PT. SURYA BESINDO SAKTI
###
2
###
3 MECHANICAL DESIGN
###
4 Code - ASME VIII Div 1, TEMA Class R ASME VIII Div 1, TEMA Class R ü
###
5 Code Stamp "U" - No No ü
###
6 Item No. 34-A-102-E-103 34-A-102-E-103 ü
7 Description SWS Stripper Reboiler SWS Stripper Reboiler ü
8 Quantity Nos 1 1 ü
9 Exchanger Type H - BXU H - BXU ü
###
10 Operating Pressure (shell/tube) Kg/Cm2G 1.85 / 3.2 1.85 / 3.2 ü
###
11 Operating Temperature o
C 127.5 / 210 127.5 / 210 ü
###
12 Design Pressure (shell) Kg/Cm2G 4 / FV 4 / FV ü
13 Design pressure (tube) 7 / FV 7 / FV ü
###
14 Design Temperature (shell/tube) o
C 150 / 325 150 / 325 ü
###
15 Min Thickness Shell
16 Shell mm 13 12.7 ü
17 Channel cylinder mm 13 12.7 ü
18 Channel cover mm 13 12.7 nom ü
19 Front head mm N/A N/A ü
20 Shel cover mm 13 12.7 nom ü
21 Tie rod diameter mm 13 12.70 ü
22 Partition plate mm 13 13 ü
23 Fixed Tubesheet mm 75 80 ü
24 Floating tubesheet mm -
###
25 Tube (OD / Thickness) mm 19.05 / 2.109 19.05 / 2.109 ü
###
26 Inside Diameter of shell mm 1250 1250.00 ü
###
27 Length of shell tube mm 4500 4500.00 ü
28 Number of tube 853U, full support at U-bend 853U, full support at U-bend ü
29 Baffle spacing mm 550 550.00 ü
30 Number of tie rod - 8 8.00 ü
###
31 Radiography (shell/tube) - ( 100% / Spot ) ( 100% / Spot ) ü
32 Radiography floating head - N/A N/A ü
###
33 Joint Efficiency (Shell/ tube) - 1.00 / 0.85 1.00 / 0.85 ü
###
34 Corrosion Allowance (shell / tube) mm 3/3 3/3 ü
###
35 PWHT (Shell / Tube / floating head) - Yes / No / NA Yes / No / NA ü
###
36 Stress Relieve for U Tube - Yes Yes ü
37 Nozzle Rating (shell / tube) - 150# / 150# 150# / 150# ü
38 Charpy Impact Test - N/A N/A ü
###
39 Support Type - Saddle Saddle ü
###
40 Strength Guarantee - YES YES ü
###
41 Hydrostatic Test - As per code As per code ü
###
42 Material for all internal part - Same quality with Vessel Material Same quality with Vessel Material ü
###
43 Standard Drawing - Vendor to be comply with Rek's Standard Dwg
comply with Rek's Standard Dwg for Vessel
ü
44
### Lifting Lug calculation - for Yes
Vessel Yes ü
###
45 Type of Nozzle - WNRF WNRF ü
###
46 Stacked Exchanger - No No ü
47 Tube to tubesheet - Light expand and seal welded Light expand and seal welded ü
48 Impingement Protection Yes Yes ü
###
49 MATERIAL SPECIFICATION SA- (ASME) MATERIAL SA- (ASME) MATERIAL ü
###
50 Shell - SA 516 Gr 70 SA 516 Gr 70 ü
###
51 Tube - SA 179 SA 179 ü
52 Tubesheet (fixed / floating) - SA 266 CL 4 / NA SA 266 CL 4 / NA ü
53 Channel cylinder - SA 516 Gr 70 SA 516 Gr 70 ü
54 Bonnet - SA 516 Gr 70 SA 516 Gr 70 ü
55 Shell cover - SA 516 Gr 70 SA 516 Gr 70 ü
56 Partition Plate - SA 516 Gr 70 SA 516 Gr 70 ü
57 Flanges -
58 Channel cover - N/A N/A ü
59 Girth flanges - SA 266 Cl 4 SA 266 Cl 4 ü
###
60 Nozzle for shell side -
###
61 - Pipe - SA 106 Gr B SA 106 Gr B ü
###
62 - Flange - SA 105 SA 105 ü
63 Nozzle for tube side -
64 - Pipe - SA 106 Gr B SA 106 Gr B ü
65 - Flange - SA 105 SA 105 ü
###
66 Reinforcement Pad on Saddle - SA 516 Gr 70 SA 516 Gr 70 ü
###
67 Reinforcement pad on Nozzle - Same as shell/channel material Same as shell/channel material ü
###
68 Saddle - SA 283 C SA 283 C ü
###
69 Bolt / Nut : -
###
70 - Internal - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
###
71 - External - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
72
### Gasket for girth flanges - Metal Jacketed with SS 304 Metal Jacketed with SS 304 ü
73
### Gasket for shell and channel Nozzle - Spiral wound with inner and outer ring SSSpiral
304 wound with inner and outer ring SS 304
ü
###
74 Name Plate - YES, SS YES, SS ü
###
75 Liner Plate - YES YES ü
###
76 Anchor Bolt / Fondation bolt - SA 307 B/ SA 563 A SA 307 B/ SA 563 A ü
###
77 Backing device - N/A N/A ü
78 Expansion joints - N/A N/A ü
79 Tie Rod - SA 36 / SA 53 Gr B SA 36 / SA 53 Gr B ü
80
###
81 PACKING AND SHIPPING
###
82 Preparation for shipment - Refer to Specification Refer to Specification ü
###
83 Shipping mark - Yes Yes ü
###
84 Approval before shipping - YES YES ü
###
85 Dessiccant internal protection - Yes Yes ü
###
86 Protection device from load/unload - Yes Yes ü
###
87 Special Tools - By vendor (if any) By vendor (if any) ü
88 PMI for alloy material N/A N/A ü
###
89
###
90 COATING / PAINTING
###
91 External (Primer, intermediate, top coat) Yes, as painting spect Yes, as painting spect ü
###
92 Internal Coating No No ü
###
93 Touch up painting Yes (5%) Yes (5%) ü
###
94
###
95 SCHEDULE
###
96 Delivery Term - Ex Work, Free on Truck Comply ü
###
97 Delivery Time Week 36 weeks Comply ü
###
98
### ABBREVIATION: ACCEPTABILITY:
### ü Comply with requirement A: acceptable
### DA Deviation accepted B: acceptable with note A
### X Deviation not accepted C: not acceptable
### ? To be clarified
### → Follow with requirement
Note

Page 9 of 16
PT. REKAYASA INDUSTRI REV. 0 1 2
PROJECT : RCC OFFGAS TO PROPYLENE PROJECT BY KHO
CLIENT : PT PERTAMINA CHKD AHP
JOB NO. : 081809 APPVD SGH
REKAYA
SA DOC NO. : ROP-E-2153-001-R-E-0 DATE 19-Aug-08
TECHNICAL BID EVALUATION
SHELL AND TUBE HEAT EXCHANGER AND DOUBLE PIPE HEAT EXCHANGER
NO. DESCRIPTION UNIT REKAYASA'S
PT SURYA BESINDO SAKTI
REQUIREMENT
###
1 VENDOR PT. SURYA BESINDO SAKTI
###
2
###
3 MECHANICAL DESIGN
###
4 Code - ASME VIII Div 1, TEMA Class R ASME VIII Div 1, TEMA Class R ü
###
5 Code Stamp "U" - No No ü
###
6 Item No. 34-A-102-E-104 34-A-102-E-104 ü
7 Description SWS Bottom Cooler SWS Bottom Cooler ü
8 Quantity Nos 1 1 ü
9 Exchanger Type H - AES H - AES ü
###
10 Operating Pressure (shell/tube) Kg/Cm2G 11.04 / 3.5 11.04 / 3.5 ü
###
11 Operating Temperature o
C 80.11 / 40 80.11 / 40 ü
###
12 Design Pressure (shell) Kg/Cm2G 12.50 12.5 ü
13 Design pressure (tube) 7.50 7.5
###
14 Design Temperature (shell/tube) o
C 150 / 120 150 / 120 ü
###
15 Min Thickness Shell
16 Shell mm 12 12.7 ü
17 Channel cylinder mm 12 12.7 ü
18 Channel cover mm 59 60 ü
19 Front head mm 16 15.88 nom ü
20 Shel cover mm 12 12.7 nom ü
21 Tie rod diameter mm 12.7 ü
22 Partition plate mm 13 12.7 ü
23 Fixed Tubesheet mm 45 45 ü
24 Floating tubesheet mm 45 45 ü
###
25 Tube (OD / thickness) mm 19.05 / 2.108 19.05 / 2.108 ü
###
26 Inside Diameter of shell mm 770 770 ü
###
27 Length of shell tube mm 6096 6096 ü
28 Number of tube 576 576 ü
29 Baffle spacing mm 250 250 ü
30 Number of tie rod - 10 10 ü
###
31 Radiography (shell/tube) - ( 100% / Spot) ( 100% / Spot) ü
32 Radiography floating head - 100% 100% ü
###
33 Joint Efficiency (Shell/ tube) - 1.00 / 0.85 1.00 / 0.85 ü
###
34 Corrosion Allowance (shell / tube) mm 3/3 3/3 ü
###
35 PWHT (Shell / Tube / floating head) - Yes / NA / NA Yes / NA / NA ü
###
36 Stress Relieve for U Tube - N/A N/A ü
37 Nozzle Rating (shell / tube) - 150# / 150# 150# / 150# ü
38 Charpy Impact Test - N/A N/A ü
###
39 Support Type - Saddle Saddle ü
###
40 Strength Guarantee - YES YES ü
###
41 Hydrostatic Test - As per code As per code ü
###
42 Material for all internal part - Same quality with Vessel Material Same quality with Vessel Material ü
###
43 Standard Drawing - Vendor to be comply with Rek's Standard Dwg
comply with Rek's Standard Dwg for Vessel
ü
44
### Lifting Lug calculation - for Yes
Vessel Yes ü
###
45 Type of Nozzle - WNRF WNRF ü
###
46 Stacked Exchanger - No No ü
47 Tube to tubesheet - Light expand and seal welded Light expand and seal welded ü
48 Impingement Protection Yes, rectangular Plate Yes, rectangular Plate ü
###
49 MATERIAL SPECIFICATION SA- (ASME) MATERIAL SA- (ASME) MATERIAL ü
###
50 Shell - SA 516 Gr 70 SA 516 Gr 70 ü
###
51 Tube - SA 179 SA 179 ü
52 Tubesheet (fixed / floating) - SA 266 CL 4 / SA 266 CL 4 SA 266 CL 4 / SA 266 CL 4 ü
53 Channel cylinder - SA 516 Gr 70 SA 516 Gr 70 ü
54 Channel cover - SA 516 Gr 70 SA 516 Gr 70 ü
55 Shell cover - SA 516 Gr 70 SA 516 Gr 70 ü
56 Partition Plate - SA 516 Gr 70 SA 516 Gr 70 ü
57 Flanges -
58 Channel cover - SA 266 CL 4 SA 266 CL 4 ü
59 Girth flanges - SA 266 Cl 4 SA 266 Cl 4 ü
###
60 Nozzle for shell side -
###
61 - Pipe - SA 106 Gr B SA 106 Gr B ü
###
62 - Flange - SA 105 SA 105 ü
63 Nozzle for tube side -
64 - Pipe - SA 106 Gr B SA 106 Gr B ü
65 - Flange - SA 105 SA 105 ü
###
66 Reinforcement Pad on Saddle - Same as shell material Same as shell material ü
###
67 Reinforcement pad on Nozzle - Same as shell/channel material Same as shell/channel material ü
###
68 Saddle - SA 283 C SA 283 C ü
###
69 Bolt / Nut : -
###
70 - Internal - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
###
71 - External - SA 193 Gr B / SA 194 Gr 2H SA 193 Gr B / SA 194 Gr 2H ü
72
### Gasket for girth flanges - Metal Jacketed with SS 304 Metal Jacketed with SS 304 ü
73
### Gasket for shell and channel Nozzle - Spiral wound with inner and outer ring SSSpiral
304 wound with inner and outer ring SS 304
ü
###
74 Name Plate - YES, SS YES, SS ü
###
75 Liner Plate - YES YES ü
###
76 Anchor Bolt / Fondation bolt - SA 307 B/ SA 563 A SA 307 B/ SA 563 A ü
###
77 Backing device - SA 516 Gr 70 SA 516 Gr 70 ü
78 Expansion joints - N/A N/A ü
79 Tie Rod - SA 36 / SA 53 Gr B SA 36 / SA 53 Gr B ü
80
###
81 PACKING AND SHIPPING
###
82 Preparation for shipment - Refer to Specification Refer to Specification ü
###
83 Shipping mark - Yes Yes ü
###
84 Approval before shipping - YES YES ü
###
85 Dessiccant internal protection - Yes Yes ü

10 of 16
###
86 Protection device from load/unload - Yes Yes ü
###
87 Special Tools - By vendor (if any) By vendor (if any) ü
88 PMI for alloy material N/A N/A
###
89
###
90 COATING / PAINTING
###
91 External (Primer, intermediate, top coat) Yes, as painting spect Yes, as painting spect ü
###
92 Internal Coating No No ü
###
93 Touch up painting Yes (5%) Yes (5%) ü
###
94
###
95 SCHEDULE
###
96 Delivery Term - Ex Work, Free on Truck Comply ü
###
97 Delivery Time Week 36 Weeks Comply ü
###
98
### ABBREVIATION: ACCEPTABILITY:
### ü Comply with requirement A: acceptable
### DA Deviation accepted B: acceptable with note A
### X Deviation not accepted C: not acceptable
### ? To be clarified
### → Follow with requirement
Note