You are on page 1of 27

Renewable Energy Cheaper than Oil

Mario Milanese, Kitenergy srl


Kitenergy technology

 Kitenergy srl was established in November 2010 to respond to a


main challenge that mankind will be facing in the near future.

Production of energy from renewable source at


lower costs than from fossil sources in order to face:
– the increasing world energy demand
– the increasing costs of fossil sources
– the geopolitical risks in fossil sources supply
– the increasing pressure on the energy industry in relation to
climate change issues
Limits of present renewable technologies

 High production costs incentives are required for installations


 Large occupation of land

Without significant breakthroughs, even reaching the objectives posed


by many countries (e.g. 20% for 2020 in EU) is a difficult challenge
Challenges Targets

 Energy production costs


lower than from fossil  < 50 €/MWh
sources

 Power density comparable  > 20 MW/Km2


to thermal/nuclear plants

 Source available  CF > 0.5


anywhere

 …………………….  ………………
Kitenergy project

 A radical innovation in wind technology, aimed at generating


renewable energy at cost lower than from fossil sources
 Exploiting the altitude wind: a renewable energy source largely
available anywhere

 Earth’s atmosphere transforms part of the Sun heating into


mechanical energy of wind.

Sun heating 150.000 TW

Wind 3.500 TW
Mankind primary power needs 14 TW
Altitude vs. ground wind

 Wind power is already extremely promising at 200-800 meters over


the ground, where the average wind speed is estimated at 7.2 m/s
 The related wind power is almost 4 times the one globally
available at 50-150 meters over the ground for wind towers

Altitude Wind Speed Wind Power

800 m 7.2 m/s 205 W/m2


80 m 4.6 m/s 58 W/m2
The problem

 Wind at 200-800 m is out of the reach of current and future


aerogenerating towers, already struggling at 150 m
 The structure holding up the rotors becomes exponentially heavier,
more unstable and expensive
 The actual 3-MW wind turbines
have towers 100-m high,
with 90-m-diameter rotors and
a weight of 370 t.
 The average power/km2 of a
wind farm in a ‘good’ site
(CF=0.35) is 3.5 MW/km2 Sketch of a wind tower and of a wind farm
The Kitenergy solution

 A radical shift of perspective: no longer heavy and static structures,


but light, dynamic and intelligent machines

 Altitude wind power is channelled


to ground through automatically
controlled tethered airfoils (kites)
Kitenergy key technology

 The core is the system of automatic control of the kite flight, called
KSU (Kite Steering Unit)

kite
on board sensors ground sensors
(kite position and speed) (wind speed and
direction,
line strength ,…)

cables
control
software

actuation unit
(electric drives, winches,..)
Kitenergy key technology

 In wind towers, the outermost 20% of the blades contributes for 80% of
the power
Wind turbine Kitenergy

Torre eolica

 The kite acts as the outermost part of the blades without requiring the
heavy tower
High tech cables

 Connecting each power kites to the units at ground level for power
generation, 2 composite cables transmit the traction force and are
differentially adjusted for manouvering

Traction force: 10 t / cm2


Weight: 100 kg /km*cm2

Traction force/Weight:
15 times higher than steel
Energy generation: yoyo configuration

1. Wind moves the power kites


pulling the cables out of the
winches. Rotation is
transmitted to the generator for
the production of electricity

2. Cables are pulled back by the


winches, this time moved by
the engines, with a minimal
power consumption

 POSITIVE BALANCE (~92%):


Energy produced during phase
1 is more than the energy
spent during phase 2
Flight paths

 The kite is driven to fly fast in


crosswind direction, with “figure
Generation phase
eight” trajectories
 Model Predictive Control
techniques are applied to:
– keep stability of the airfoil
Recovery phase
– maximize the net generated
energy
Z – satisfy physical constraints
(keep the kite far from the
ground, avoid line entangling,
Y
maximal cable strength, ….)
X – attenuate the effects of wind
KSU
Wind turbolence
direction
Capacity Factor

 Due to wind variability, a wind generator is able to produce in


average only a fraction of its rated power, called “Capacity Factor”

Pav = Pmax ⋅ CF
 The Capacity Factor depends on:
power curve of the generator probability of wind speed

KITEnrg
Capacity Factor examples

De Bilt (NL) Linate (IT)


200-800 m 200-800 m
50-150 m 50-150 m

Linate (IT) B. Aires (AR) Cagliari (IT) Leba (PO) Brindisi (IT) De Bilt (NL)
0.006 0.18 0.31 0.32 0.31 0.36
0.33 0.63 0.56 0.68 0.60 0.71
Capacity factors of wind tower (black) and of KITEnrg-yoyo (orange) in some locations
Wind data taken from the NOAA/ESRL Radiosonde Database
KITEnrg Farm

 In a farm layout several KITEnrg-yoyos are displaced in order to


avoid kite collision and aerodynamic interferences
Power density of KITEnrg Farms

In a “windy” site:
 Kitenergy Technology
– 16 KITEnrg-yoyo/km2
– 32 MW/km2 (rated)
– 22 MW/km2 (average)

 Actual wind technology


– 4.5 towers/km2
– 9 MW/km2 (rated)
– 3.4 MW/km2 (average)
Energy production costs

 The Kitenergy technology has the potential of generating renewable


energy at lower cost than energy generated from fossil sources

Source Min. Estimated Max. Estimated Av. Estimated cost


cost (€/MWh) cost (€/MWh) (€/MWh)
Coal 23 46 31
Gas 34 56 44
Nuclear 19 29 27
Wind 32 88 53
Solar 167 463 301
Kitenergy 14 46 24

Projected cost in 2030 (levelised in 2003 Euros per MWh) of energy from different sources compared
with the estimated cost of Kitenergy
Source: International Energy Agency (IEA), Projected Cost of Generating Energy – 2005 update.
Paris, France: IEA PUBLICATIONS, 2008
Kitenergy development status

 The project started in 2005 at the Complex Systems Modeling &


Control group of Politecnico di Torino in collaboration with small hi-
tech companies
 It has been supported by Regione Piemonte, Ministero della Ricerca
and European Union
 Advanced modeling and computer simulations have been performed
to assess the energy generation potentials
 A 40 kW peak power prototype has been built and first tested in
September 2006, able to generate energy with 1 km cable length
 The tests until now performed allowed to experimentally verify the
simulation results
 Kitenergy srl was established in 2010 with the aim of developing
further the technology towards the industrialisation phase
The prototype – KSU1

 The prototype has been constructed to produce energy in KE-yoyo


configuration:
– max power: 40 kW
– lines length: 1000 m
– kite area: up to 20 m2

 During 2007-2009 the


prototype was successfully
tested to experimentally
verify the simulation results
Experimental vs. simulation

 Test 1  Test 2
– turbulent wind of about 3-4 m/s at ground – wind of about 1-2 m/s at ground level
level – Kite effective area: 10 m2
– kite effective area: 5 m2, – maximum line length: 800 m
– maximum line length: 300 m

Simulated Simulated
Measured Measured
KSU prototype signal pattern
KSU prototype data acquisition

Acquire experimental data in order to validate the mathematical


models
 Kite heading and position with respect to the ground station
 Meteorological data to improve the wind models
 Generated and consumed power during the yo-yo cycles
KSU software tools

 Control and data acquisition systems has been implemented


with Real-Time Labview, exploiting the multiprocessor function
of NI-PXI
 A first processor manages data acquisition, prefiltering, control
actuation
 A second processor implements the Fast Model Predictive
Control for kite flight control at a sampling time of 100 ms
 The low-level motor drive control is performed by a FPGA board
at a sampling time of 10 ms
Future development plan

The future development plan of Kitenergy is composed of 3 main phases.


1. The first phase is on-going and is focused on completing the
experimental tests on an improved prototype implementing the full
automatic control. The output expected by October 2011 will be energy
generation for periods exceeding the 24 hours with minimal human
assistance
2. The second phase will last 20 months and will be focused on the
design, development and construction of an industrial prototype with
200 kW nominal power. The output will be the industrial prototype
successful tests and operation.
3. The third phase will be focused on the industrialization of the KITEnrg
yo-yo plants. The third phase will require the establishment of robust
industrial partnerships.
Contacts

 mario.milanese@kitenergy.net

 www.kitenergy.net

You might also like