Professional Documents
Culture Documents
Tennessee
Valley
Authority
The East Tennessee Section of the American Society of Mechanical Engineers gratefully acknowledges the efforts of
those who helped organize the landmark dedication of the Hiwassee unit 2.
ASME National History & Heritage Committee ASME East Tennessee Section
James M. Patterson, Manager, Marketing Services Paul Rieland, Large Rotating Apparatus Division
Hydro-Turbine Division
Lloyd Zellner, Public Relations
This integration of pump and turbine was the first of many to be installed
in power plant systems in the United States; it was the largest and most
powerful in the world.
As a "pump storage" unit in the Tennessee Valley Authority's system
it offered significant economies in the generation of electrical energy.
The unit was designed by engineers of the Tennessee Valley Authority
and the Allis-Chalmers Company. It was built by Allis-Chalmers
Company.
The Hiwassee unit 2 is the 61st landmark designated by the American Society of Mechanical Engineers. For a
complete listing of landmarks, please contact the Public Information Department, ASME, 345 E. 47th St.,
New York, NY 10017.
HIWASSEE POWER PLANT BACKGROUND
The Hiwassee dam and power plant on the Hiwassee River near Murphy, North
Carolina, was built by TVA between 1936 to 1940 as a flood control and electrical generat-
ing facility. The initial power installation consisted of a single conventional Francis turbine
driving a generator with a rating of 57,600 kW, placed in service in May 1940. Space was
provided in the powerhouse for later installation of a second unit.
When studies were begun for the installation of a second generating unit in the late
1940’s, a reversible pump-turbine was considered. Installation of a pump-turbine was
selected to provide additional generating capacity during periods of system daily peak
loads, especially during the months of January through March which at that time corre-
sponded to TVA’s seasonal peak period. Apalachia Reservoir, immediately downstream
from Hiwassee, provided sufficient storage for approximately 27 hours of pumping with
the pump-turbine. The pump-turbine selected has a generator rating of 59,500 kW and a
pump capacity of 3900 cfs at 205-foot total head (102,000 hp).
The pump-turbine unit was installed and placed in operation in May 1956 after ex-
tensive commissioning tests. Performance tests for both pumping and generating operation
were made in April 1957, using the Allen salt-velocity method for measuring discharge, and
again in March 1958, utilizing Apalachia reservoir for volumetric flow measurement. These
tests showed that both the turbine guaranteed efficiency of 88.4 percent and pump guaran-
teed efficiency of 90.0 percent were met or exceeded.
HISTORICAL SIGNIFICANCE
Hiwassee unit 2 was the first reversible pump-turbine installed in this country solely
for the purpose of storing electrical energy in a pumped storage plant. An earlier pump-
turbine, installed in 1954 at the Flatiron Power and Pumping Plant in Colorado, was used
primarily for irrigation rather than electrical energy storage. It was much smaller than the
Hiwassee pump-turbine and had a somewhat specialized design, providing no control of
turbine power output.
Pumped storage plants had been in use for electrical energy storage in Europe for
some years prior to operation of Hiwassee unit 2. But these plants employed either
completely separate motor-driven pumps and turbine-generators or a pump, a turbine,
and a generator/motor all on a single shaft. They did not use reversible pump-turbines
which are now standard for pumped storage plants.
Finally, there were a few instances of pumps being retrofitted for reverse operation
as turbines prior to the introduction of reversible pump-turbines. These machines were
designed as pumps and had less-than-optimum performance when operated as turbines.
UNIQUE FEATURES
The Hiwassee pump-turbine was the first reversible pump-turbine built and installed
in this country using wicket gates for control of turbine output power and improved pump
efficiency. The unit also was much larger and more powerful than any reversible pump-
turbine in service in the world at the time it went into operation. The rated turbine power
output of 80,000 hp was over four times greater than the next largest pump-turbine,
installed at the Pederia power plant in Brazil in 1953.
With a diameter of 266 inches, the impeller/runner was the largest water wheel
in the world for either a pump-turbine or conventional Francis turbine at the time
it was built. The impeller was so large that it had to be shipped in three sections and
assembled at the power plant site. Operating as a pump, it had more than three times
the capacity of each pump serving the Grand Coulee irrigation project, which then
had the world’s largest pumps.
WHEN WEAR RINGS were fitted onto this 266-inch diameter FROM THE 18-FOOT diameter penstock,
three-piece runner, strip heaters were used to expand the rings, water will fill the scroll case, surround the
water spray to contract the runner for the shrink-fit. (FIGURE 4) stay ring and wicket gates. (FIGURE 5)
LOW WATER in Hiwassee Lake during
months of high system load will be
alleviated by the pump-turbine. (FIG. 1)
PUMP-TURBINE (Unit 2)
GENERATORS
Number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 1
Unit 1 Generator
Manufacturer . . . . . . . . . . Allis-Chalmers Manufacturing Co.
Manufacturer . . . . . . . . . . . . W estinghouse Electric Corp.
As Turbine As Pump T y p e . . . . . . . . . . . . . . . . Enclosed, water-cooled, verti-
Type. . . . . . . . . . . . . . Vertical Francis Centrifugal cal-shaft; vertical cylindrical
Rated horse- concrete wall of housing, and
power . . . . . . . . . . . 80,000 102,000 removable weather cover, fur-
Rated head. . . . . . . . . 190 ft net 205 ft net nished by TVA
Rated dis- Rating. . . . . . . . . . . . . . . 6 4 , 0 0 0 k V A , 5 7 , 6 0 0 k W ,
charge . . . . . . . . . . . . 4,180 cfs 3,900 cfs 2864 A, 60 degrees C rise,
Rated speed . . . . . . 105.9 r/min 105.9 r/min 0.9 pf, 13.8 kV, 3 ph, 60 Hz
Maximum run- Capacity . . . . . . . . . . . . . 7 3 , 6 0 0 k V A , 6 6 , 2 4 0 k W ,
away speed. . . . . . 161 r/min 121 r/min 3086 A, 80 degrees C rise
CONSTRUCTION DATA
PERSONNEL
Dam and Reservoir Dam Construction Unit 2
Construction Only Addition
Peak employed . . . . . . . . . . . . 1,600 1,200 128
Total man-hours . . . . . . . . . . . 7,682,640 5,424,683 468,114
Number of injuries . . . . . . . . . . 205 141 6
Days lost . . . . . . . . . . . . . . 16,509 15,589 2,749
Fatalities . . . . . . . . . . . . . 2 2 0
Accident frequency . . . . . . . . . 26.7 26.0 12.82
Accident severity . . . . . . . . . . 2,149 2,874 5,873
SUMMARY OF PRINCIPAL FEATURES
HOUSING FACILITIES
(Initial Project)
QUANTITIES
Unit 2
Initial Project Addition
Dam and power facilities:
Earth excavation . . . . . 64,700 cu. yd -
Rock excavation . . . . . 294,500 cu. yd 125 cu. yd
Unclassified
excavation . . . . . . 19,500 cu. yd -
Concrete . . . . . . . . . 792,956 cu. yd 7,830 cu. yd
Structural steel . . . . . 535 tons 23 tons
Reinforcing steel . . . . 1,972 tons 156 tons
Highway and railroad:
Excavation . . . . . . . . 960,000 cu. yd -
NOTE