Professional Documents
Culture Documents
FIDIC Training
and
Dispute Resolution Mechanisms
in Project Administration
Gwyn Owen
BSc MSc CEng FICE FConsE FCIArb
Chartered Arbitrator, Adjudicator, Mediator
www.gwynowen.com
Contents
Introduction Plant & Materials
FIDIC Documents Commencement
Risk Delays
Procurement Taking Over
Strategy Measurement
First 100 days Guarantees
Responsibilities Claims
Nominated s/c Short Form
Staff & labour Disputes
FIDIC
AN INTRODUCTION
Founded in 1913
Expanded in 1945 to include 40 national
associations
Published first Conditions of Contract in
1957
In 2004 has 64 member associations
Headquarters in Switzerland
Web Site : www.fidic.org
FIDIC
AN INTRODUCTION
Acknowledgements
Foreword & Charts
General Conditions
DAB Conditions
Guidance Notes
Forms of Agreement
Appendix to Tender
FIDIC Document Usage
Conditions of Contract for
Construction
Works designed by Employer or
Engineer
Contractor Constructs in accordance
with designs provided
May include some design elements
FIDIC Document Usage
Conditions of Contract for
Plant & Design Build
General Comments:
• Contractor will economise
• Employer will supervise
• No good for Employer Variations
• Good for Lump Sum
• Design Savings
• Employer responsible for ER errors
• Risk Shared
FIDIC Document Usage
Conditions of Contract for
EPC/Turnkey Projects
General Comments
• Not suitable when:
No time to tender
Much underground works
If Employer wishes to supervise
If payments need to be administered
FIDIC Document Usage
Short Form of Contract
Cl.1.3:
• Approvals, Certificates, Consents,
Determinations, Notices, Requests
In Writing
Delivered
Not be unreasonably withheld or
delayed
Copies
RISK
ALLOCATION OF RISK
Scope / Cost of Change
CONTRACTUAL RISKS
Design by Employer
Works to be Re-Measured
Employer appoints Engineer
Engineer can vary the works – but
not change the Contract
Engineer’s “Determinations” Cl.3.5
DAB appointed within 28 days
Contract Selection
Basic Principles – Red Book
Employers Requirements
Contractor Designs & Builds
ER errors – Employer’s risk
Fixed sum contract
Administered by Engineer
Variations by Engineer
Cl.5 & 12 differ from Red Book
PROCUREMENT
PROCUREMENT PROCEDURE
Establish Strategy
Procurement method
Form of Tender
Time Schedules
Prequalify
Invitation
Documents
Analysis
Selection
Notify
PROCUREMENT PROCEDURE
Prepare tender Documents
Issue
Site Visit
Questions
Submission & Opening
Adjudication
PROCUREMENT PROCEDURE
Award Contract
Issue Letter of Acceptance
Performance Security
Contract Agreement
Notify unsuccessful tenderers
PROJECT STRATEGY
Definitions
General Provisions Cl.1
• Definitions of words
• Persons include corporations & other
legal entities
• Letter of Acceptance
• Employer’s Requirements (YB)
• Goods – Contractor
Cl.1.3
PROJECT STRATEGY
Definitions
Cl.12.1 Measurement
Cl.13 Variations & Value Engineering
Cl.14 Payments
• Planning
• Funding & Budget
• Disbursement approval
Cl.18 Insurances
Cl.20 Contractor’s Claims / Records
FIDIC -
THE FIRST 100 DAYS
AN INTRODUCTION
The First Hundred Days of a New
FIDIC contract
Cl.14.3 Application
• 6 copies
• In a form approved (Cl.4.9)
• Cl.4.21
• List of items (a) – (g)
• Note : Cl.20 items included
Interim Payment
Cl.16.1 Suspension
• Engineer fails to certify
• Employer does not provide Cl.2.4 details
• Non payment
• 21 days notice
Cl.16.2 Termination
Guarantees & Bonds
Basic Principles:
• Exceptional event
• Not reasonably provided against
• Not reasonable to overcome / avoid
• Not attributable to either party
• Beyond control of affected party
Force Majeure
Cl.19.1 Definitions
• (i) – (iv) man made
Cl.19.4 Consequences
• EoT
• Man made – cost
• Man made in country – cost
• Cl.19.6 Termination
CLAIMS &
CONTRACTUAL
PROCEDURES
CAUSES OF CLAIMS FOR
CONTRACTORS
Unforeseeable ground conditions
Delayed drawings
Delayed payment
Lack of possession of site
Consequence of risk
Suspension
Force Majeure
CONTRACTOR’S CLAIM
PROCEDURE
Clause 20.1
o Sets out Contractor procedure
o Condition Precedent
o Not later than 28 days
o Sets out Engineer procedure
CONTRACTOR’S CLAIM
PROCEDURE
Contractor gives notice
o Within 28 days
Contractor keeps contemporary records
o Engineer may monitor
o Engineer may instruct further records
Fully detailed claim
o Supporting documents
o Within 42 days of event
CAUSES OF CLAIMS FOR
EMPLOYERS
Engineer’s Response:
o Within 42 days of receiving claim
o Approval / Disapproval
o Detailed comments
May ask for further details
Proceed with Cl.3.5
May certify interim sums
CLAUSE 3.5 DETERMINATIONS
Dispute resolution
• Amicable settlement
• Adjudication
• Dissatisfaction – 28 days
• Arbitration
Alternative Dispute
Resolution
ADR - Overview
Alternative Dispute Resolution
ADR - Overview
Confrontational
Litigation
Win – Win methods
ADR Methods:
• Mediation
• Conciliation
• Adjudication
• Arbitration
DISPUTE RESOLUTION
under FIDIC
“Dispute” not defined by FIDIC
o Where 2 parties can not agree
o Where something needs to be decided
Certificates, Determinations,
Instructions, Variations
FIDIC encourages resolution by
agreement – Cl.3.5
No agreement - Dispute
Amicable Settlement
Cl.20.5 – no definition
• 56 days
• Direct negotiation
• Conciliation
• Mediation
• Do not involve the DAB
• Consensual
• No obligation – costs ??
Mediation
No facility in FIDIC contracts
Consensual procedure
Confidential
Very successful
Short time frame
Low cost
Involve decision makers
ENGINEERS DECISION
QUALITIES
o Experience o Qualifications
o Contract Knowledge o Availability
o Language o Impartiality
o DR Experience o Independence
o Procedural Knowledge o Lawyers
WARRANTIES & OBLIGATIONS
General Conditions Cl.3 & 4
Warranties:
o Experienced in Work
o Experienced in Documentation
o Fluent in Language of communications
Obligations:
o Independent
o Confidential
o Available
PAYMENT OF MEMBERS
General Conditions Cl.6
Retainer per calendar month
Daily Fee
Reasonable expenses
Taxes in country of contract
Retainer reduced by 50% after
taking over
Ad hoc DAB – no retainer
PAYMENT OF MEMBERS
Payment method:
o Retainer & airfares - quarterly in
advance
o Other fees after site visits / hearing
Contractor pays in full within 56 days
Employer reimburses Contractor
ANNEX : PROCEDURAL RULES
Monitor progress reports against project
documents
Site visits
o Timing
o Agenda / scheduling / travel arrangements
o Keep up to date
o Progress
o Problems
o Claims
ANNEX : PROCEDURAL RULES