Professional Documents
Culture Documents
Cost
Scope
Drafting document
Consider Risk of all parties
Reasonable & fair for all the parties
Types of Standard Contract Documents used in
construction contracts Introduction
Introduction to FIDIC
•Minor Works
•Construction
•EPC/Turnkey
•Design-Build-Operate
Standard contracts for civil engineering & construction works
•Construction
•Plant and Design-Build
•EPC/Turnkey
Larger and more complex than minor works projects, traditional plant projects
involve the design, manufacture, delivery, erection, testing, etc. of plant by a
contractor to an outline or performance specification prepared by the Employer.
Recommended also for the building of engineering works, if most (or all) of the
Works are to be designed by (or on behalf of) the Contractor.
Follows the same procedure as for construction works, however with certain
significant differences:
• much of the plant is manufactured off-site;
(i) a higher degree of certainty of final time and price is required and
(ii) the Contractor takes total responsibility for the design and
execution of the project, with little involvement of the Employer. Under
the usual arrangements for turnkey projects, the Contractor carries out
all the Engineering design, Procurement and Construction (EPC),
providing a fully equipped facility, ready for operation (at the turn of a
key).
Each of the 2017 FIDIC contract documents includes:
•General Conditions (first part)
•Guidance for the Preparation of the Particular Conditions (second part)
•Forms (third part), e.g. Letter of Tender, Contract Agreement and Dispute
Adjudication Agreements
In any project, it will often be necessary to carry out additional work. Usually,
the Contractor spends money and claims it back from the Employer.
It is then necessary to decide whether the Employer must pay. The initial
decision will normally be made by the Engineer or, in the case of the Silver
Book, the Employer’s Representative. This may be an interim decision subject
to appeal to the DAB, possibly followed by a formal arbitration procedure or
even the courts.
FIDIC’s
GOLDEN PRINCIPLES
Some of the more significant General Considerations underlying the Golden
Principles:
The terms of the Contract are comprehensive and fair to both contracting Parties
The legitimate interests of both contracting Parties are appropriately considered
and balanced.
No Party shall take undue advantage of its bargaining power
This contracting technique requires the Contractor to submit a lump sum price
to complete a project as opposed to bidding on individual pay items with
quantities provided.
The contingency pay item is recommended on a Lump Sum project. This tool is
used to compensate the Contractor for any additional work requested, which is
not covered in the contract documents.
Lump Sum contracting should be used on simple projects.
“Simple” is defined by the work activity, not by the project
cost. “Simple” projects are:
Principle Differences
• Design responsibility
• Risk allocation
• Contract administration
Employer Red book
Employer’s representative
Silver book
Sequential process
Architect/Consulting Engineer first, then Contractor
• A/CE completes design and prepares tender documents
Competitive tender after design complete
• Design specifications
Contractor charged with delivery of the completed construction [Red Book]
• Contractor not responsible for design, but partial contractor design possible
o Fitness for purpose only when contractor designs (SC 4.1(e))
• Contract administration -- Engineer
• Engineer reviews Contractors documents for contractual compliance
and certifies payments
• Engineer is no longer stated to be ‘impartial’
• Deemed to act for the Employer, except when fair determinations
are required (sub-clause 3.7.2),
DAB to decide disputes
Only one contract for both design and construction
do not form part of the documents forming the Contract for the Silver
Book
The reason is that the SB is typically used for projects where the
tender / proposal (offer) / award process is replaced by a negotiated
contract.
Sub-Clause 4.12 [Unforeseeable Difficulties]
RED / Yellow:
“If and to the extent that the Contractor encounters
physical conditions which are Unforeseeable, …, and
suffers delay and/or incurs Cost due to these conditions, the
Contractor shall be entitled to EoT and additional Costs.”
Silver:
“4.12 (c) the Contract Price shall not be adjusted to take
account of any unforeseen difficulties or costs.”
Under the RB the Design is done by the Employer, even though limited
parts may be given to the Contractor.
Under the Yellow and Silver Books, the Design is carried out by the
Contractor as follows:
Yellow Book:
Upon receiving notice to Commence, the Contractor shall scrutinize the
Employer’s Requirements, and shall give notice to the Engineer of any
error, fault or defect found. He may be entitled to compensation.
Silver Book:
The Contractor is deemed to have scrutinized the Employer’s
requirements prior to Base Date, and he is totally responsible for the
accuracy, completeness, etc. The Employer takes no responsibility.
Sub-Clause 7.5 [Rejection]
• The Contractor has to submit to the Engineer the as-built documents and the
operation and maintenance manuals in accordance with Sub-Clauses 5.6
and 5.7 before the commencement of the Tests on Completion and all the
other documents mentioned in Sub-Clause 4.1.
• The last paragraph of this Sub-Clause stipulates: “If, for reasons not
attributable to the Contractor, a Test after Completion on the Works or any
Section cannot be completed during the Defects Notification Period (or any
other period agreed upon by both Parties), then the Works or Section shall
be deemed to have passed this Test after Completion”.
Sub-Clause 12.3 [Retesting]
• The final paragraph of this Sub-Clause states that after the Engineer (RB &
YB) or Employer (SB) instructs/approves a Variation, he shall proceed in
accordance with the provisions of Sub-Clause 3.5 to agree or determine
“adjustments to the Contract Price and the Schedule of Payments”,
adjustments which shall include reasonable profit and shall consider the
Contractor’s proposals made pursuant to Sub-Clause 13.2 [Value
Engineering], if applicable.
Sub-Clause 14.1 [The Contract Price]
Unless otherwise stated in the Particular Conditions of the Contract:
• The Contract Price is a lump sum accepted by the Employer at Tender
stage;
• The quantities which may be comprised in a Schedule are only
estimated quantities and shall not be considered the actual and final
quantities of the Works.
• “Any quantities or price data which may be set out in a Schedule shall
be used for the purposes stated in the Schedule any may be inapplicable
for other purposes”.
If payment for part of the works is to be determined based on the
quantities supplied or work performed, the provisions for measurement
and evaluation shall be provided in the Particular Conditions of the
Contract. ”The Contract Price shall be determined accordingly, subject
to adjustments in accordance with the Contract”.
Sub-Clause 14.3 [Application for Interim Payment
Certificates]
The 2017 Red Book, the Yellow Book and the Silver Book contain
provisions in respect of how to pay to the Contractor the Retention
Money.
Under the Yellow & Silver Book, the first half of the Retention Money
shall be certified by the Engineer for payment only after the Taking-
over Certificate has been issued for the Works and the Works passed all
the required tests, including the Tests after Completion. The Red book
only requires that the Taking-over Certificate has been issued for the
Works.
Within the Appendix to Tender it shall be stated the relevant percentage for
each Section. If there is no percentage stated in the Appendix to Tender, “no
percentage of either half of the Retention Money shall be released under this
Sub-Clause in respect of such Section”
Sub-Clause 17.3 [Intellectual and Industrial Property Rights]
In both 2017 Red, Yellow & Silver Books, this Sub-Clause deals with the
protection of the intellectual and industrial property rights of the Parties.
The difference between the Yellow & Silver books and the Red Book is
the following new wording:
• The Employer shall indemnify and hold the Contractor harmless against
and from any claim “alleging an infringement which is or was (…) an
unavoidable result of the Contractor’s compliance with the Employer’s
Requirements”.
• The Contractor shall indemnify and hold the Employer harmless against
and from any claim “alleging an infringement which is or was (…)
• (i) the Contractor’s design, manufacture, construction or execution
of the Works,
• (ii) the use of Contractor’s Equipment, or
• (iii) the proper use of the Works”.
Thank you