Professional Documents
Culture Documents
David Platt
Type of Contract
• Power almost invariably uses “lump sum turnkey”
Why?
– Nature of the technology – no processes to match to
equipment (as for refineries). Hence contractors can give full
support
– Tendency to use project finance – banks hate risk and insist
on maximum risk transfer to contractor
FORM OF CONTRACT
• Industry standard forms -
– FIDIC Silver Book
– ENAA Model Form
– Institute of Chemical Engineers (IChemE) Green Book
– and many others
• Weakness
Typically a power project is based in a power purchase
agreement which will have (possibly extensive) requirements
on construction. These must be passed through and it is
likely to be as difficult to amend a standard form as to draft a
“purpose built” contract.
A LESSON LEARNED
How not to do it
•A large utility’s first international IPP
•The business development team worked on the PPA and other
documents
•But the construction projects department worked on the EPC
Contract
•Each department hired separate legal advisers
•The teams did not communicate
•Technical changes driven from the PPA negotiations did not get
passed to EPC Team
Result:
•The technical specifications of the EPC Contract did not
match the PPA
A LESSON LEARNED
How not to do it (2)
•But it gets worse
•Lenders reviewed a mismatched set of contracts
•Lenders’ engineer and lawyers chiefly responsible for redraft
•Result increased price, (massively) increased legal fees
adversarial negotiation, pressure from lenders on sponsors
(“You got the project into this mess so you need to take more
risk”)
•Banks are not project managers!
Nicholas Brown
AVOIDING DISPUTES
1. Pre-Contract
– 1.1 Letters of Intent
– 1.2 Representations
• 1.2.1 Drafting
• 1.2.2 Entire Agreement Clauses
• 1.2.3 Battle of the Forms
2. Contract Administration
– 2.1 Notices
– 2.2 Records
– 2.3 Managing Key Project Risks
1.1 PRE-CONTRACT: LETTERS OF INTENT
• Risk Areas:
• If you must use one, monitor it, manage it, and don’t
exceed its boundaries
33
2.3 CONTRACT ADMINISTRATION:
PRACTICAL TIPS
• Project team – be familiar with contract and don’t be scared to
issue a Notice
PPA BASICS
David Platt
Agenda
1. Nature and purpose of PPA
2. Geothermal projects – alternatives to PPAs
3. Key risk issues
Nature and Purpose of PPA
Background
•Electricity cannot be stored
•Need for massive capital investment in an energy project
•Need to leverage that investment with debt so as to allow
a reasonable return to equity investors and a low power
cost for consumers
•Need to create of a long term stable cashflow to service
the debt
The Classic Thermal PPA
• IPP agrees to construct and operate a power station and
sell all electricity generated to the utility
• Term: Construction plus 20 – 25 years
• Payment: IPP cannot take “market risk” so is paid (usually)
through a two part tariff
– First part: capacity payment covering fixed costs (debt,
equity, fixed O&M costs). Paid on basis of power
station’s availability to generate
– Second part: energy payment covering variable costs
(fuel and parts). Paid on basis of electricity delivered
Variants for renewable energy
• Greater interplay between statute and contract – many
developed jurisdictions have specific statutory regime for
renewable energy so very short form PPAs. Indonesia not
such a jurisdiction
• Renewable energy either has zero or next to zero variable
cost and/or benefits from statutory or regulatory obligations
on the utility to purchase this power
• So simpler payment tariff – an all energy payment backed
by an obligation to take (or take or pay for) all electricity
generated
Geothermal Projects
• Geothermal is “different” because there are two distinct
projects:
– the geothermal field; and
– the power plant,
and the skills for developing constructing and operating
these projects may be different
• So there are a variety of structures used for exploiting
geothermal energy
Geothermal Structures
Field Owner IPP Developer
Field/IPP Developer
Geothermal Power PPA Utility
Field Plant
Advantages
• Simplicity
Disadvantages
• Skills of developing geothermal field and power plant
not necessarily the same
Geothermal Structures
Advantages
• Separates risks and allocates them to parties best able
to bear them
Disadvantages
• IPP Developer is in the middle taking risks on both
sides (geothermal plus utility)
Geothermal Structures
• Introductions
• Development Phase
• Construction Phase
• Operation Phase
• Tariff and Payment
• Force Majeure and Termination
INTRODUCTION
Logically:
• no developer will commit to the cost of a drilling programme
without having a PPA in place first
• but the utility cannot commit to an uncertain level of power at
whatever price the developer eventually incurs
So this arrangement is probably inevitable but:
• the “hard” 50MW obligation makes the exploration of any
small project particularly risky
THE DEVELOPMENT PERIOD
Timing
• Minimum Exploration Spend Deadline – 2 years from Signing
by which time Project Company must have spent USD20
million on exploration
• 4 year deadline to satisfy (normal conditions precedent,
complete “ Exploration Activities and issue:
– Notice of Resource Confirmation (“NORC”) confirming
capacity
– Notice of Investment Decision (“NOID”) confirming the
decision to proceed (in practice likely to be linked to
financial close).
THE DEVELOPMENT PERIOD
Mitigation
• Risk sharing with partners and exploration contractor
• Careful technical monitoring – important to cut losses early if
50 MW will not be achieved
THE CONSTRUCTION PERIOD
• 30 months from Effective Date but protection for Project
Company to specify a different period in the NOID
• If cannot achieve Commercial Operation Date by Required
Commercial Operation Date (unless excused) then –
– PLN can draw pre agreed amounts from Performance
Security Stage 2 at 90,120 and 180 days delay
– PLN can terminate the PPA if the construction is 90 days
after the Required Commercial Operation Date
– PLN can terminate the PPA if construction does not start
within 90 days of the Effective Date
• A termination right at 90 days is onerous and risks and is
not consistent with timings for drawdown on the bond
THE CONSTRUCTION PERIOD
Compared to “usual” PPAs
•treatment is “better” in that there is no sanction for first 90 days
of delay
•However treatment is “worse” in that a termination right applies
after 90 days
A “usual” PPA would provide for
•liquidated damages for each day of delay
•once liquidated damages exhausted (6-12 months?) only then
does a right to terminate apply
THE CONSTRUCTION PERIOD
For a full list of our locations around the globe please visit our websites:
www.pinsentmasonsmpillay.com www.Out-Law.com