Professional Documents
Culture Documents
On
Construction Contract
Administration and Claims
(Adama)
Types of Delays
•Excusable and Compensable Delay: A delay for which the Client is entirely
responsible; like possession of site.
•Excusable but Non-Compensable Delay: A delay beyond the control of
both parties; like Adverse Weather, Earthquake. It is also termed as Delay
due to Neutral Event
Delay…..Cont’d
• Inexcusable/Culpable Delay: A delay for which the Contractor
is entirely responsible; like delay due to poor progress
• Concurrent Delay: at-least two events occurring at the same
time of which one of them is Employer related delay while the
other is Contractor’s own delay;
• Parallel Delay: at-least two events occurring at the same time
but unlike Concurrent Delay, here the responsible party for the
events are either the Employer or the Contractor; not both
1.3.2 Progress of Works…..Cont’d
Suspension
Is a stoppage of work on any or all activities in all or part of the
works for a certain duration.
Major Causes of Suspension
– Delay in Payment;
– Design Revision;
– Availability of Obstructions.
Effects of Suspension
– Reduction of Rate of Progress
– Stoppage of work
– Termination of Contract
1.3.2 Progress of Works…..Cont’d
Termination
Termination of a contract is defined as bringing the contract to an end
regardless of the status of the project.
Defaults by Contractor
•persistently and flagrantly neglecting to carry out his obligations under
the contract
•becomes insolvent, involuntary bankruptcy, liquidation or dissolution
•notwithstanding that the other party has committed no fault, when the
contract has become useless to the public service or unsuitable for its
requirements - Ethiopian Civil Code Article 3180
Termination…..Cont’d
Defaults by the Employer
• failing to pay the contractor entitle him to suspend and later
terminate the contract.
• outright refusal to give possession in the first place
• Delay in giving possession of site and omission of the work
together may entitle the contractor to terminate
• wrongful ejection of the contractor from the site
• where an intervention by the employer has its effect to upset the
general economy of the contract - Ethiopian Civil Code Article
3182 –
1. Contract Admin…..Cont’d
1.3.3 Completion of Works
Taking Over
Substantial Completion/ Provisional Taking Over
Final Taking Over
Obligation of Contractor after completion
Defect Liability Period
• Patent and Latent Defects
• Commencement of the DLP
• Contractor’s payment during the DLP
• Failure by the contractor to remedy any defects
• Termination during DLP
1. Contract Admin…..Cont’d
1.4 Payment
• Advance/ Interim/Final Payments
• Variation/ Valuation
• Fluctuation
• Retention Money
• Provisional Sum and Prime Cost Item
• Liquidated Damages and Penalty
1.4 Payment…..Cont’d
1.4.1- The main and critical obligation of the Employer is paying the
Contractor what is to be due.
Advance Payment: What makes it different from Down Payment?
Is it Interest Free for the Employer; in case of delay?
Interim Payment Certificates: Could be termed as temporary
certification that could be corrected/modified. It is a sum of monthly
statements if the amount of the previous month is less than the
minimum.
Statement at Completion: payment for the whole outstanding
payments of works after substantial completion. Half of the
retention money would also be released.
Final Payment: Covers all eligible payments until the completion of
the DLP. Any claim/dispute should be settled before the final
payment. Letter of Discharge.
1.4 Payment…..Cont’d
1.4.2 Variation
Any changes to contracts from what has been anticipated at the
making of the contracts could be regarded as variation.
Causes of Variations: Variations could arise either from the
insufficiency of the original design, change in mind by the
client, as a result of mitigation measures, etc.
Which Variations do require Order? Except for quantity decrease or
increase of certain items of the work
Absence of Variation Clause: contractors would be entitled to
negotiate a new rate for that piece of work of variation
Scope of Variations : Within the general scope of the contract and
that does not go to the root of contract.
1.4 Payment…..Cont’d
Valuations of Variations
– Similar to Contract: for varied work similar to an item in the contract. In
this case the Bill rate will be used.
– Substituted Work: for varied work similar to an item in the contract but
with different characteristics; like sub-base placing at Junctions.
– Change of Circumstances: for varied work due to change in circumstances;
like working seasons (from Summer to Winter), working in difficult social
and environmental situation than anticipated.
– Major Change in Quantity: Occurrence of appreciable quantity variations
(increase or decrease) that affect the OH element of the bill rate.
– Entirely new type of work: This is a varied work with a completely new
items. In this case as far as practicable the tender rate will be used as a
base for building a new rate.
1.4 Payment…..Cont’d
1.4.3 Fluctuations
• Fluctuation is the rise or fall of the prices of construction inputs;
like material, labour and/or equipment during the course of
construction.
• In longer time contracts, the risk is allocated mostly to Clients
using a prescribed formula. Base/Current indices or prices.
• Any change in legislation after the contract could be considered to
adjust the price of the contract by reimbursing the contractor
with an equal amount
• What if the price of an input that has not been identified as
adjustable material increases substantially?
1.4 Payment…..Cont’d
1.4.4 Retention Money
The main purpose of retaining a certain percentage of the
certified sum from each IPC is for the employer to guarantee for
the rectification by the contractor of any defects observed during
the performance of the contract but completed and certified
section and during the defect liability period.
Could be replaced by an Unconditional Bank Guarantee.
Performance Bond could not be used alternately for rectification
of defects.
1.4 Payment…..Cont’d
1.4.5 Provisional Sum and Prime Cost Sum
i. Provisional Sum
are used for work that has not been finalized or for costs unknown at the
time the contract is prepared.
Does not necessarily imply any obligation on the part of the employer to
spend them.
The contract administrator must issue instructions to spend these sums.
ii. Prime Cost Sum
For works by specialized firms like, nominated sub-contractors that usually
have been selected prior to the main contractor.
the contractor has no control over the pricing of this work,
Prime cost is taken to mean that the contractor will be fully reimbursed for
any valid expenditure.
1.4 Payment…..Cont’d
1.4.5 Liquidated Damages and Penalty
Liquidated Damages – a genuine covenanted pre-estimate of loss.
Claimed without proof of loss
There is no bar to limit a genuine pre-estimate loss in non-commercial
projects.
When to challenge the Employer on the excessive amount of LD?
How it is calculated? – usually the maximum to be recovered between
one third and two-third of the Contract Period
Penalties– to force the contractor to complete in terrorem.
It is intended to penalize the defaulted party
Can excessive liquidated damage amount be considered as penalty?
Does the court interfere in the commercial bargains struck by the
parties?
1. Contract Admin…..Cont’d
1.5 Risk Management
Risk is an uncertain event or condition that, if it occurs, has an effect
on at least one project objective
Stages of Risks
•Plan Risk Management
•Risk Identification
•Risk Analysis (Qualitative and Quantitatively)
•Risk Response (Retention, Avoiding, Transfer and Mitigation)
•Monitor and Control Risks
1.5 Risk Management...Cont’d
2.8.6 Litigation
• Settling disputes in Court
• Takes longer time and higher cost than any other dispute resolution
mechanism
• Parties have automatic rights to refers their case to Litigation whether
its is mentioned in the contract or not.
Thank you!!!