Professional Documents
Culture Documents
Planning Witoon Permpongsacharoen Director Mekong Energy and Ecology Network (MEE Net)/ Towards Ecologic Recovery and Regional Alliance (TERRA) Foundation for Ecological Recovery (FER) Thailand witoon@terraper.org
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
(MW)
Demand Forecast
(MW)
Difference of Forecast and Actual
(%)
Difference of Forecast and Actual
Jun-93 Dec-94 Oct-95 Oct 96 (Base) Jun 97 (Low) Sep-97 Sep 98 (MER) Feb 01 (Base) Aug-02 Jan 04 (MEG) Apr 06 (Base) Aug-06 Jan-07 Mar 07 (Low) Dec-08 Feb-10
31,749 31,749 32,756 39,247 37,075 34,883 28,912 28,912 27,711 29,808 27,761 27,711 26,635 25,956 23,936 23,249
7,739.10 7,739.10 8,746.10 15,237.10 13,065.10 10,873.10 4,902.10 4,902.10 3,701.10 5,798.10 3,751.10 3,701.10 2,625.10 1,946.10 - 73.90 - 760.90
32.23 % 32.23 % 36.4 % 63.46 % 54.42 % 45.29 % 20.42 % 20.42 % 15.41 % 24.15 % 15.62 % 15.41 % 10.93 % 8.11 % -0.31 % -3.17 %
24,000 MW
Yearly peak demand growth since 1986 to 2011 (actual) and future demand forecast from 2012 to 2030 in PDP 2010
1,000
1,500
2,000
-500 500 0
Actual Forecast
1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030
Actual Demand 2010 31,516.61 Actual Demand 2011 Forecasted Demand 2011 Installed Capacity Reserve Margin 15%
32,000.00
28,000.00
26,000.00
24,100.00
24,000.00
22,000.00
20,000.00
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Cost-plus tariff structure that enables utilities to pass on unnecessary costs to consumers
Recommendations
The tariff should not allow the over investment costs of generation capacities to be passed on to consumers. In the Thai case, the system security policy is based on the peak demand plus a reserve margin of 15%. The cost of the reserve margin over 15% should not be passed on to consumers. Requests for large additional demand (e.g. 10MW) should come under the Contracted Demand System. Integrated Resources Planning (IRP) should be introduced into the PDP. EE should be prioritized and included in the PDP in the same way as other generation investment projects, and EE projects should be indicated clearly with a capacity (MW) and a time frame. In this way, the implementers would gain a profit from EE.
Recommendations
To avoid conflicts of interest, EE programs should not be monopolized by EGAT, but should be open to more competition as well as be transparent. The utilities should be evaluated by their overall performance and not on the basis of the assets they own or profits (performance-based regulation). Good EE studies and planning are needed. Public education is needed as well. All stakeholders should be given correct information and high-quality messages on EE. The regulator should function better and promote peoples participation in the PDP process and in all aspects of power sector development.
Thank you
Email: witoon@terraper.org