You are on page 1of 4

Management Accounting By Paresh Shah Oxford University Press Chapter No.

9 Chapter Name Contract Costing

Dear Student / Reader, To have on-hand experience, do exercises, by using following templates. Please fill the data in ORANGE colour cell, for following Illustrations. Illustration No. 8

The Answer will appear in BLUE colour. If your answer is right, a message will appear as "Answer is Right". Till you get the message on screen, go on exercising it, to achieve the required level of skill and competency.

For any Query, contact at profpareshshah@yahoo.co.in profpareshshah@fenilinstitute.org

quired level of skill and competency.

Statement Showing the Estimated Profit to Date and on Completion of Contract No -----Cost Elements Fabrication Costs: Direct Materials Direct labour Overheads Fabrication Cost Erection Costs Total Estimated Profit % Completion 1 1 1 1 1 -1 Cost to date 1 % Balance 99 99 99 99 Further Cost 99 0 0 99 0 99 -99

Contract Price Total Cost 100 0 0 100 0 100 -100