Tests On Concrete
Tests On Concrete
SAMP LING The first step is to take a test sample from the large batch of concrete. This should be done as soon as discharge of the concrete commences. The sample should be representative of the concrete supplied. The sample is taken in one of two ways: For purposes of accepting or rejecting the load: Sampling after 0.2 m3 of the load has been poured. For routine quality checks: Sampling from three places in the load.
2. 3.
4. 5.
cone (100 mm top diameter x 200 mm bottom diameter x 300 mm high) Small scoop Bullet-nosed rod (600 mm long x 16 mm diameter) Rule Slump plate (500 mm x 500 mm)
4. Steel plate