TRACK REHABILITATION & TRACK DOUBLING PROJECTS

Rail System Development Seminar


French Embassy, NSTA, TFTA
Siam City Hotel, 28 February 2011

Dr. Krit Anurakamonkul


STATE RAILWAY OF THAILAND

MYANMAR LAOS VIETNA M

Chiang Mai

Nong Khai

THAILAND
Ubon Ratchathani Nakhon Ratchasima

Existing SRT nationwide Rail Network


Total Route Length = 4,305 km

Aranyaprathet Bangkok

Sattah ip

CAMBODIA

GULF OF THAILAND

Planning & Implementation Horizon :

40% of which : Track Rehab scheme


ANDAMAN SEA

20% of which : Track Doubling scheme


Padang Besar

STATE RAILWAY OF Sungai Kolok THAILAND MALAYSIA

MYANMAR LAOS VIETNA M

Chiang Mai

Track Rehabilitation
Track Rehabilitation Projects Phase Phase Phase Phase Total 1 2 3 4* = (289 km) (258 km) (244 km) (227 km) 1,018 km

Nong Khai

THAILAND
Ubon Ratchathani Nakhon Ratchasima

Aranyaprathet Bangkok

Sattah ip

CAMBODIA

GULF OF THAILAND

Complete d
ANDAMAN SEA

Padang Besar

STATE RAILWAY OF Sungai Kolok THAILAND MALAYSIA

MYANMAR LAOS VIETNA M

Chiang Mai

Track Rehabilitation
Track Rehabilitation Projects Phase 5 (308 km) Phase 6 (278 km) total = 586 km

Nong Khai

THAILAND
Ubon Ratchathani Nakhon Ratchasima

Aranyaprathet Bangkok

Sattah ip

CAMBODIA

Budgeting Framework
GULF OF THAILAND

Phase 5 : 8,508 million baht Phase 6 : 6,779 million baht


4

ANDAMAN SEA

STATE RAILWAY OF Sungai Kolok THAILAND MALAYSIA

Padang Besar

Total Baht

= 15,287 mil.

Track Rehab Phase 5 :


k

Khaengkoi Khaengsueten (37 km) Suranarai Buayai (192 km) Jira Junc Buayai (79 km) total length = 308 km
5 6

Track Rehab Phase 6 :


Buayai Nongkhai length = 278 km

Deformed track from recent 7.1 Richter quake in New Zealand on Sept 4, 2010

/ (1)

( 3,926 28 ..51) ( 106 . 7,648 )
Klong Sip Kao Chachoengsao

Kaeng Khoi

82 24 69
Si Racha

Laem Chabang Symbol

Existing track Double track project: Chachoengsao Sriracha Laem Chabang Double track project: 6 2555 Chachoengsao Klong Sibkao Kaeng Khoi

10

MYANMAR LAOS VIETNA M

Chiang Mai

Track Doubling Projects


Long loop Track Doubling Project (832 kms.)
Northern Line 418 Kms. Northeastern Line 78 Kms. Southern Line 336 Kms. Total 832 Kms.

Nong Khai

THAILAND
Ubon Ratchathani Nakhon Ratchasima

Aranyaprathet Bangkok

Sattah ip

CAMBODIA

GULF OF THAILAND

ANDAMAN SEA

STATE RAILWAY OF Sungai Kolok THAILAND MALAYSIA

Padang Besar

Construction Cost 11 75,000 M Baht

(Eastern Seaboard Railway Line)

Existing Putthachaai Railway Tunnel

15 . H= 7.0 . W= 6.5 .

15 . H=7
.0 .

W=6.5

unnel Portal: northbound Tunnel Portal : southboun

Twin-Tunnels Alignment

Existing tunnel

Proposed tunnel

14

Project Cost Estimates :

100+500

Deformed track from recent 7.1 Richter quake in New Zealand on Sept 4, 2010

End of Presentation

Dr. Krit Anurakamonkul


STATE RAILWAY OF THAILAND

Email : kritkrit@yahoo.com Mobile: +66 814493970 Phone: +66 22204282