History & Current State of Affairs The Future for Zambia Railways Limited (ZR) 2013-2017 & Beyond Rehabilitation & Reconstruction of Existing Network Process Network Development Programme of the future Zambian Designed Motive Power & Rolling Stock Business Model For Sustainable Profitability & Growth Partnerships Floatation of Minority Stake to finance modernisation of the network Conclusions
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Zambia Railways Limited operated and still operates a network of 1062 km of 1067mm gauge, single track of which 848km is the mainline and 214 km is on branch lines or spurs
In 2001, two years before the concession ZRL moved 1.98 million tonnes of traffic. Today that is 667,000 tonnes ZRL had and has a total of 37 locomotives (12 GT ,17 U20C and 8 U15C) and has a total of 2201 wagons of various types.
HISTORY
ZRL own passenger coaches have become dilapidated and out of service during the concession. Therefore using 28 passenger coaches belonging to Railway Systems of Zambia (RSZ).
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
Mainline Track The mainline extends from Victoria Falls Bridge in the South to Nkana Kitwe
The weight of rails on the mainline is 91lb per yard (606km) 90lb per yard (101km) 80lb per yard (141km), these need replacing with 91lb/yard
530 km of the mainline is on concrete sleepers & 318 km on wooden sleepers The depth of ballast on mainline varies between 50mm and 160mm instead of the required depth of 250mm to 300mm.
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
Track Condition
Missing rail fastenings on consecutive sleepers on the mainline near Kabwe and Monze railway stations, making the railway line unsafe.
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
The railway line is overgrown with weeds in many sections, thus even maintenance of the line difficult to carry out.
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
If repairs were made, the plan was to interlace 1 concrete sleeper in 4 wooden sleepers and claim to have upgraded the railway line
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
Mainline Track The mainline extends from Victoria Falls Bridge in the South to Nkana Kitwe
The weight of rails on the mainline is 91lb per yard (606km) 90lb per yard (101km) 80lb per yard (141km), these need replacing with 91lb/yard
530 km of the mainline is on concrete sleepers & 318 km on wooden sleepers The depth of ballast on mainline varies between 50mm and 160mm instead of the required depth of 250mm to 300mm.
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Track Condition
Branch Lines The following are the branch lines on Zambia Railways Limited:S/N Section Length Type of Rail Type of Sleeper
i ii iii iv v
Kitwe Chingola Ndola Sakania Chambeshi Mufulira Luano Chililabombwe Choma Masuku Total
Track Condition
Branch Lines The following are the branch lines on Zambia Railways Limited:S/N Section Length Type of Rail Type of Sleeper
i ii iii iv v
Kitwe Chingola Ndola Sakania Chambeshi Mufulira Luano Chililabombwe Choma Masuku Total
Linear Rail
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Station Condition
More than 90% of stations along the main line and branch lines are dilapidated beyond repair due to lack of maintenance. Kitwe Total demolition Ndola Major repairs (Cheaper new build) Kapiri-Mposhi Total Demolition Kabwe Major repairs (Cheaper new build) Lusaka Substantial repairs Kafue Total demolition Mazabuka Total repairs Choma - Major repairs (Cheaper new build) Livingstone Substantial repairs All intermediate stations need total rehabilitation
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Station Condition
More than 90% of stations along the main line and branch lines are dilapidated beyond repair due to lack of maintenance. Kitwe Total demolition Ndola Major repairs (Cheaper new build) Kapiri-Mposhi Total Demolition Kabwe Major repairs (Cheaper new build) Lusaka Substantial repairs Kafue Total demolition Mazabuka Total repairs Choma - Major repairs (Cheaper new build) Livingstone Substantial repairs All intermediate stations need total rehabilitation
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
The Vision
To have an effective and efficient railways network that is extremely profitable as a core business and that is the envy of the world, strategically connecting Zambia, its natural border countries and overseas.
7 5 6 5 4
PHASE 2
-TAZARA & CHIPATA-MCHINJI LINES TO CONNECT -MULOBEZI-SHANGOMBO TO BOTSWANA
9 1
10
9
PHASE 3
6
Further railway tracks to service our mining & Agro Co. industries plus passenger transport -LUSAKA-MONGU -CHINGOLA-MWINILUNGA -KAFUE-HARARE -MPIKA-MANSA-KAPUTAMPULUNGU/MBALA-CHOZI
Livingstone Mulobezi lines Livingstone Chingola Lines Inter-mines & Ndola Sakania then Kolwezi (Congo) TAZARA connect to Chipata-Mchinji & to Mpulungu Chipata-Mchinji line (to Malawi/Mozambique) Lusaka Mongu Chingola Mwinilunga (On the way to Angola) Mpika Mansa Kaputa Mpulungu/Mbala Chozi Mulobezi-Shangombo (On the way to Bostwana) Kafue to Harare (On the way to Zimbabwe)
7 8
10 8
Figure 1: The future Zambia Railways Network (This network is indicative of partial selected routes and not exhaustive as further lines can be added or removed)
FREIGHT DIVISION
PASSENGER DIVISION
INTER-MINE DIVISION
BRANDING
BRANDING
Creating; Identity, focus, values, pride. Denoting; Political, societal and commercial change. Presenting; A reality for the future a vibrant and successful Zambian Railway
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
BRANDING
BRANDING
Rail Freight Creating the brand; customer focused divisions within he main brand, Mining, Inter Mine, International, Coal, Gold etc.
OFFER: Up to 3 million tonnes per year in delivering: Ore, Anodes, Concentrates, Lime and other products for production.
The Project
INFRASTRUCTURE: RAILWAY NETWORK
COMMERCIAL: STATIONS
Project Workpackages
INFRASTRUCTURE Existing Line Rehabilitation Second line construction Bridge & Culvert construction Tunnel & Flyover Construction Electrification COMMERCIAL Station Mall Bar, Pub, Restaurant, shop Hotel Business Offices THINK TANK ENGINEERING Research & Development Engineering Design Manufacture of Railway Vehicles Manufacture of Auxiliary Equipment Training
Contribution Package
INFRASTRUCTURE
RAIL
SLIPPERS
FIXTURES
Contribution Package
INFRASTRUCTURE
RAIL
SLIPPERS
FIXTURES
Contribution Package
INFRASTRUCTURE
MODULAR DESIGN CONSTRUCTION MODULE 1: VICTORIA FALLS MAYOBA (105 KM) MODULE 2: MAYOBA CHOMA (112 KM) MODULE 3: CHOMA MONZE (101 KM) SECOND LINE CONSTRUCTION
MODULE 4: MONZE NALUAMA (101 KM) MODULE 5: NALUAMA CHISAMBA (109 KM) MODULE 6: CHISAMBA LUANSHIMBA (103 KM)
MODULE 7: LUANSHIMBA KAFULAFUTA (104 KM) MODULE 8: KAFULAFUTA MABOTE (94 KM) MODULE 9: MABOTE CHINGOLA (92 KM)
Contribution Package
INFRASTRUCTURE RAIL TRACK
MODULAR DESIGN CONSTRUCTION MODULE 1: VICTORIA FALLS MAYOBA (105 KM) MODULE 2: MAYOBA CHOMA (112 KM) MODULE 3: CHOMA MONZE (101 KM) MODULE 4: MONZE NALUAMA (101 KM) MODULE 5: NALUAMA CHISAMBA (109 KM) MODULE 6: CHISAMBA LUANSHIMBA (103 KM) 50KG (91LB) RBS RAIL = 916,00 TONS BALLAST = 916,000 M CONCRETE SLEEPERS = 1,282,400 5 MM THICH HDPE RAIL PAD = 2,564,800 E1820 TYPE PANDROL CLIP/BOLTS = 5,129,600 INSULATOR (BLUE/BLAC LINER) = 5,129,600 BAR FISHPLATE (PAIR) = 150,164 FISHBOLT & WASHER = 600,656
MODULE 7: LUANSHIMBA KAFULAFUTA (104 KM) MODULE 8: KAFULAFUTA MABOTE (94 KM) MODULE 9: MABOTE CHINGOLA (92 KM)
THE AKAPELWA LECTURE
Contribution Package
INFRASTRUCTURE - BRIDGES
MODULAR DESIGN CONSTRUCTION MODULE 1: VICTORIA FALLS MAYOBA (105 KM) MODULE 2: MAYOBA CHOMA (112 KM) MODULE 3: CHOMA MONZE (101 KM) MODULE 4: MONZE NALUAMA (101 KM) MODULE 5: NALUAMA CHISAMBA (109 KM) MODULE 6: CHISAMBA LUANSHIMBA (103 KM) ROAD UNDER BRIDGES = 5 FOOT BRIDGES = 5 CULVERTS = 868 RIVER BRIDGES = 22
MODULE 7: LUANSHIMBA KAFULAFUTA (104 KM) MODULE 8: KAFULAFUTA MABOTE (94 KM) MODULE 9: MABOTE CHINGOLA (92 KM)
THE AKAPELWA LECTURE
Contribution Package
INFRASTRUCTURE - ELECTRIFICATION
MODULAR DESIGN CONSTRUCTION MODULE 1: VICTORIA FALLS MAYOBA (105 KM) MODULE 2: MAYOBA CHOMA (112 KM) MODULE 3: CHOMA MONZE (101 KM) MODULE 4: MONZE NALUAMA (101 KM) MODULE 5: NALUAMA CHISAMBA (109 KM) MODULE 6: CHISAMBA LUANSHIMBA (103 KM) 921 KM CATENARY SYSTEM 921 KM DISTRIBUTION FACILITY 921 X 2 FANCING ALONG LINE 14 SUB-STATIONS
367,000 POLES
MODULE 7: LUANSHIMBA KAFULAFUTA (104 KM) MODULE 8: KAFULAFUTA MABOTE (94 KM) MODULE 9: MABOTE CHINGOLA (92 KM)
THE AKAPELWA LECTURE
Contribution Package
FIXED ASSETS - STATIONS
MODULAR DESIGN CONSTRUCTION MODULE 1: VICTORIA FALLS MAYOBA (105 KM) MODULE 2: MAYOBA CHOMA (112 KM) MODULE 3: CHOMA MONZE (101 KM) MODULE 4: MONZE NALUAMA (101 KM) MODULE 5: NALUAMA CHISAMBA (109 KM) REHABILITATION OF ALL SMALL STATIONS BY BUILDING PLATFORMS AND WAITING ROOMS > 150 REBUILDING OF KITWE, NDOLA, KAPIRI, KABWE, KAFUE, MAZABUKA, CHOMA, LIVINGSTONE TOTAL SINKING OF LUSAKA FOR LAND DEVELOPMENT
Contribution Package
FIXED ASSETS - STATION MODERNISATION
Contribution Package
FIXED ASSETS - STATION MODERNISATION
Contribution Package
FIXED ASSETS - STATION MODERNISATION
Contribution Package
FIXED ASSETS - LUSAKA STATION UNDERGROUND
Contribution Package
ENGINEERING DESIGN THINK TANK
RESEARCH & DEVELOPMENT INSTITUTE OF RAILWAY STUDY AT THE COPPERBELT UNIVERSTY
MANUFACTURING OF ALL ENGINEERING DESIGNED PRODUCTS MARKET: ZR; ALL HEAVY & LIGHT INDUSTRIES; MINES; AGRICULTURE; TRANSPORT
THE AKAPELWA LECTURE
31st January 2013, Government Complex Conference Centre, Lusaka, Zambia
Contribution Package
ENGINEERING DESIGN - FUTURE ROLLING STOCK
Contribution Package
ENGINEERING DESIGN - FUTURE ROLLING STOCK
Contribution Package
ENGINEERING DESIGN - FURTURE ROLLING STOCK
Contribution Package
ENGINEERING DESIGN - CURRENT FREIGHT ROLLING STOCK
Contribution Package
ENGINEERING DESIGN - ROLLING STOCK
OUR GOAL
Delivery Milestones
DELIVERY TIMELINE
TASKS QUARTER PREAMBLE ERA RP FEIDD PHASE 1 LINE 1 LINE 2 LINE 3 PHASE 2 LINE 4 LINE 5 LINE 9 PHASE 3 LINE 6 LINE 7 LINE 8 LINE 10 TRAINING YEAR 1 2 3 YEAR 2 2 3 YEAR 3 2 3 YEAR 4 2 3 YEAR 5 2 3 1 4 1 4 1 4 1 4 1 4
Delivery Milestones
DELIVERY TIMELINE
TASKS QUARTER PREAMBLE ERA RP FEIDD PHASE 1 LINE 1 LINE 2 LINE 3 PHASE 2 LINE 4 LINE 5 LINE 9 PHASE 3 LINE 6 LINE 7 LINE 8 LINE 10 TRAINING YEAR 1 2 3 YEAR 2 2 3 YEAR 3 2 3 YEAR 4 2 3 YEAR 5 2 3 1 4 1 4 1 4 1 4 1 4
ZR
IT Hardware & Software Production Think-Tank & Research
Stone/Wood/ Cement/etc..