Professional Documents
Culture Documents
The table below shows the tasks involved in a project, with their durations and immediate predecessors.
Task A Duration (days) 2 Immediate predecessors -
B
C D E F G
3
5 6 8 2 4
A, B C C D, E
Draw an activity network and use it to find the critical activities and the minimum duration of the project.
A(2)
1
B(3)
C(5)
Activities A, B and C have no preceding activities, so can all begin at the start node.
A(2)
1 3 D(6)
B(3)
C(5)
Activity D depends on both A and B. Since A and B must not start and finish at the same node, a dummy activity is needed to ensure unique numbering.
The dummy activity has zero duration. Now activity D can be drawn in, following on from both A and B.
A(2)
1 3 D(6)
B(3)
C(5) E(8) 4
F(2)
A(2)
1 3 D(6) 5 G(4)
B(3)
C(5)
E(8) E(8) 4
Since G depends on both D and E, these two activities must both lead into the same node.
F(2)
A(2)
1 3 D(6) 5 G(4) 6
B(3)
C(5)
E(8) F(2) 4
F(2)
A(2)
1 3 D(6) 5 G(4) 6
B(3)
C(5)
E(8) F(2) 4
A(2)
1 0 C(5) E(8) F(2) 4 3 D(6) 5 G(4) 6
B(3)
Event 1 occurs at time zero. The earliest that event 2 can occur is after A has finished, at time 2.
A(2)
1 0 C(5) 3 3 E(8) F(2) 4 D(6) 5 G(4) 6
B(3)
Event 3 cannot occur until both A and B have finished, so the earliest time at which event 3 can occur is 3.
A(2)
1 0 C(5) 3 3 E(8) F(2) 4 D(6) 5 G(4) 6
B(3)
Event 4 cannot occur until C has finished, so the earliest time at which event 5 can occur is 5.
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6) 5 G(4) 6
The earliest that D can finish is at time 9, and the earliest that E can finish is at time 13, so the earliest that event 5 can occur is time 13.
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6) 5 G(4) 6 17
The earliest that F can finish is at time 7, and the earliest that G can finish is at time 17, so the earliest that event 5 can occur is time 17.
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6) 5 G(4) 6 17
The next step is to find the latest event times (LETs), starting from the finish node and working backwards.
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6) 5 G(4) 6 17 17
Event 6 must not occur later than time 17, or the project will be delayed .
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6)
13
5 G(4) 6 17 17
The latest G can start is at time 13, so the latest time for event 5 is 13.
A(2) 13
1 0 C(5) B(3) 3 E(8) F(2) 4 3 D(6)
13
5 G(4) 6 17 17
The latest that E can start is at time 5, and the latest that F can start is at time 15, so the latest possible time for event 4 is 5.
A(2) 13
1 0 C(5) B(3) 3 3 7 E(8) F(2) 4 D(6)
13
5 G(4) 6 17 17
The latest that D can start is at time 7, so the latest possible time for event 3 is 7.
A(2) 13
1 0 C(5) B(3) 3 3 7 E(8) F(2) 4 D(6)
13
5 G(4) 6 17 17
The latest that the dummy activity (with zero duration) can start is at time 7, so the latest possible time for event 2 is 7.
A(2) 13
1 0 0 C(5) B(3) 3 3 7 E(8) F(2) 4 D(6)
13
5 G(4) 6 17 17
A(2) 13
1 0 0 C(5) B(3) 3 3 7 E(8) F(2) 4 D(6)
13
5 G(4) 6 17 17
The critical activities are 5 activities for which the float is zero: i.e. the latest event time for activity j the earliest event time for activity i is equal to the activity duration.
A(2) 13
1 0 0 C(5) B(3) 3 3 7 E(8) F(2) 4 D(6)
13
5 G(4) 6 17 17
For analysis of the float in this example, see Example 2 in the Notes and Examples.