PEKERJAAN PERSIAPAN
Start: 08/07/13 Finish: 16/07/13 Res: ID: 2 Dur: 7 days
PEKERJAAN KUSEN, PINTU, JENDELA DAN VENTILASI PEKERJAAN PENGECATAN DAN WATERPROOFING
Start: 27/09/13 Finish: 16/10/13 Res: ID: 8 Dur: 14 days Start: 17/10/13 Finish: 14/11/13 Res: ID: 10 Dur: 21 days
PEKERJAAN LAIN-LAIN
Start: 15/11/13 Finish: 03/12/13 Res: ID: 15 Dur: 13 days
FINISH
Milestone Date: Wed 04/12/13 ID: 16
Critical
WAKTU PELAKSANAAN PEKERJAAN 150 HK TANGGAL PELAKSANAAN AKAN DISESUAIKAN DENGAN KONTRAK