NETTWORK PLANNING

PEMBANGUNAN GEDUNG KANTOR KEJAKSAAN NEGERI PANDEGLANG

PEKERJAAN ELEKTRIKAL MEKANIKAL START


Milestone Date: Mon 08/07/13 ID: 1 Start: 27/09/13 Finish: 16/10/13 Comp: 0% ID: 12 Dur: 14 days

PEKERJAAN RANGKA ATAP DAN PLAFOND


Start: 09/09/13 Finish: 26/09/13 Res: ID: 7 Dur: 14 days

XI.A PEKERJAAN ELEKTRIKAL


Start: 27/09/13 Finish: 07/10/13 Res: ID: 13 Dur: 7 days

XI.B PEKERJAAN MEKANIKAL


Start: 08/10/13 Finish: 16/10/13 Res: ID: 14 Dur: 7 days

PEKERJAAN PERSIAPAN
Start: 08/07/13 Finish: 16/07/13 Res: ID: 2 Dur: 7 days

PEKERJAAN TANAH, PONDASI DAN SUB STRUKTUR PEKERJAAN TANGGA


Start: 17/07/13 Finish: 01/08/13 Res: ID: 3 Dur: 12 days Start: 02/08/13 Finish: 12/08/13 Res: ID: 5 Dur: 7 days

PEKERJAAN KUSEN, PINTU, JENDELA DAN VENTILASI PEKERJAAN PENGECATAN DAN WATERPROOFING
Start: 27/09/13 Finish: 16/10/13 Res: ID: 8 Dur: 14 days Start: 17/10/13 Finish: 14/11/13 Res: ID: 10 Dur: 21 days

PEKERJAAN STRUKTUR UTAMA


Start: 02/08/13 Finish: 22/08/13 Res: ID: 4 Dur: 15 days

PEKERJAAN PENUTUP LANTAI


Start: 09/09/13 Finish: 20/09/13 Res: ID: 9 Dur: 10 days

PEKERJAAN LAIN-LAIN
Start: 15/11/13 Finish: 03/12/13 Res: ID: 15 Dur: 13 days

PEKERJAAN PASANGAN BATA & PLESTERAN


Start: 23/08/13 Finish: 06/09/13 Res: ID: 6 Dur: 11 days

PEKERJAAN SANITASI DAN PERALATAN SANITER


Start: 09/09/13 Finish: 26/09/13 Res: ID: 11 Dur: 14 days

FINISH
Milestone Date: Wed 04/12/13 ID: 16

Critical

Milestone Critical Summary Summary

Critical Inserted Inserted Critical Marked

Marked Critical External External

Project Summary Highlighted Critical Highlighted Noncritical

TTD DAN CAP

Noncritical Critical Milestone

WAKTU PELAKSANAAN PEKERJAAN 150 HK TANGGAL PELAKSANAAN AKAN DISESUAIKAN DENGAN KONTRAK