UNIVERSITI TEKNOLOGI MARA CENTRE OF CONSTRUCTION MANAGEMENT FACULTY OF ARCHITECTURE, PLANNING AND SURVEYING

BUILDERS QUANTITIES AND ESTIMATING III (BCM663)

TUTORIAL 2

MUHAMMAD ZABRI MASTAR 2011445284

18 JUN 2013

QUESTION Estimate the proposed construction and completion of earthwork for Primary School at Bandar Setia Alam, Shah Alam, Selangor. Refer to the information given below: Scope of works : Excavation in bulk for suitable material 500,000 m3 : Load, transport, deposit and compact within the site to form platforms to require levels. Duration Plant Utilization : 16 weeks : Hydraulic Excavator PC 300 - Output 1000m3 / day : Bulldozer - Output 2000m3 / day : Roller : Backpusher 600m3/day : Lorry 6m3/load (86sec/load) Rental : Hydraulic excavator RM700.00/day Bulldozer RM600.00/day Roller RM350.00/day Backpusher RM500.00/day Lorry RM20.00/hour