Industrial Training Presentation
Industrial Training Presentation
University Supervisor -Mr Ir. Azman Bin SeninIndustrial Training Supervisor -Mr Chuah Wei Kit-
Auto Parts Manufacturers Company Sdn. Bhd. Main Products: Seats Trim, Seats Frame, and Seats
Mechanism Department: Production Engineering (Section Seat Assembly, Seat Frame, Seat Mechanism) Customers: Perodua-79% , Proton-3%, Others-18%
previous study and training. To learn lean manufacturing system from the Majaico model company.
Gantt chart
Job: Develop a new checking jig design to fulfill customer requirement (quality)
Part offset
Pin - Pin use to avoid part offset - To check part from slanting
Job: Develop a new welding jig for reduce sub process and increase productivity
Production low
To increase production Save cost & space Increase product quality Reduce cycle time
+
Jig 1
Handling time (10s)
=
Jig 2 New Jig
Job: Record a video, take picture, listing the detail operation sequence and time(s).Balancing time for each worker.
To increase productivity.
To reduce cost. Ensure the cycle time < takt time (Customer
Requirement).
Takt time Customer requirement time for 1 product Cycle time < takt time
Takt time = per day working hour 8.5 hr per day required order
The bar chart that show the total cycle time for each operator .
helped to reduce the production lead time, improve quality, increase productivity, hence helped student gain confidence and knowledge in jig & fixture design. The industrial training helped student involve in real working environment, also gain useful knowledge for future.