You are on page 1of 61

Project Time Management

Based on PMBOK 5th Edition

Waleed El-Naggar, MBA, PMP

https://www.facebook.com/waleed.naggar

Agenda

6.1 Plan Schedule Management


6.2 Define Activities

6.3 Sequence Activities


6.4 Estimate Activity Resources

6.5 Estimate Activity Durations


6.6 Develop Schedule

6.7 Control Schedule


https://www.facebook.com/waleed.naggar 2

PMP - Project Time Management

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

Project Time Management


Includes the processes required to
accomplish timely completion of the project; involved 7 processes used to in developing time schedule The schedule can have any format.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

6.1 Plan Schedule Management


Establishing the policies, procedures, and

documentation for planning, developing,


managing, executing, and controlling the project

schedule.
The key benefit is to provide guidance and

direction on how the project schedule will be


managed.
PMP - Project Time Management https://www.facebook.com/waleed.naggar 5

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

Plan Schedule Management: Inputs


1. Project Management Plan
Scope baselines

Other Information
2. Project Charter

3. Enterprise Environmental Factors


4. Organization Process Assets
PMP - Project Time Management https://www.facebook.com/waleed.naggar 7

Plan Schedule Management: T & T


1. Expert Judgment
2. Analytical Techniques 3. Meetings

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

Plan Schedule Management: Output


1. Schedule Management Plan, includes but
not limited to:

Project Schedule Model Development


Level of accuracy

Rules of Performance Management


Reporting Formats

Process Description
PMP - Project Time Management https://www.facebook.com/waleed.naggar 9

6.2 Define Activities


Identify the specific actions to be performed to produce the project deliverables Activities provide a basis for estimating,

scheduling, executing and monitoring and


controlling the project work.
PMP - Project Time Management https://www.facebook.com/waleed.naggar 10

Define Activities
Data Flow

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

11

Define Activities: Inputs


1. Schedule Management Plan

2. Scope baselines
3. Enterprise Environmental Factors 4. Organizational Process Assets

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

12

Define Activities: T & T


1. Decomposition

2. Rolling Wave Planning


3. Expert Judgment

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

13

Define Activities: Outputs


1. Activity List: A list of all the activities that will be performed on the project and a

description of each activity


2. Activity Attributes

3. Milestone List: A milestone is a significant


point or event in project.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

14

6.3 Sequence Activities


The process of identifying and documenting
relationships among the project activities.

Lead/Lag time between activities should be


considered to support a realistic schedule.

Can be performed by a software or


manually.
PMP - Project Time Management https://www.facebook.com/waleed.naggar 15

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

16

Sequence Activities: Inputs


1. Schedule Management Plan 2. Activity List

3. Activity Attributes
4. Milestone List

5. Project Scope Statement


6. Enterprise Environmental Factors

7. Organizational Process Assets


PMP - Project Time Management https://www.facebook.com/waleed.naggar 17

Sequence Activities: T & T


1. Precedence Diagramming
The most common method of arranging the project activities visually. Activities are put in boxes, called nodes, and connected with arrows (Activity on Node).
PMP - Project Time Management https://www.facebook.com/waleed.naggar 18

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

19

Sequence Activities: T & T


2. Dependency Determination Mandatory Dependency Discretionary dependency: preferred logic, preferential logic, or soft logic. External dependencies

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

20

Sequence Activities: T & T


3. Applying Leads an Lags

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

21

Sequence Activities: Outputs


1. Project Schedule Network Diagrams
2. Project Document Updates

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

22

Exercise
Activity A B C D E F G Predecessor A B, F C E F

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

23

6.4 Estimate Activity Resources


Estimate the type and quantities of
material, human resources, equipment, or

supplied required to perform each activity.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

24

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

25

Estimate Activity Resources: Inputs


1. Schedule Management Plan

2. Activity List
3. Activity Attributes

4. Resource Calendars
5. Risk Register 6. Activity Cost Estimates 7. Enterprise Environmental Factors 8. Organizational Process Assets
PMP - Project Time Management https://www.facebook.com/waleed.naggar 26

Estimate Activity Resources: T & T


1. Expert Judgment 2. Alternatives Analysis 3. Published Estimating Data

4. Bottom-up Estimation
5. Project Management Software
PMP - Project Time Management https://www.facebook.com/waleed.naggar 27

Estimate Activity Resources: Outputs


1. Activity Resource Requirements

2. Resource Breakdown Structure


3. Project Document Updates

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

28

Quiz
Determining the physical resources, quantities

of each and when they would be used is called


A. Resources Selection. B. Resource leveling. C. Resource Breakdown Structure (RBS). D. Estimate Activity Resources.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

29

6.4 Estimate Activity Duration


The process of approximating the number of work periods needed to complete individual activities with estimated resources.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

30

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

31

Estimate Activity Duration: Inputs (1)


1. Schedule Management Plan 2. Activity List. 3. Activity Attributes 4. Activity Resource Requirements 5. Resource Calendar
PMP - Project Time Management https://www.facebook.com/waleed.naggar 32

Estimate Activity Duration: Inputs (2)


6. Scope Statement 7. Risk Register 8. Resource Breakdown Structure

9. Enterprise Environmental Factors


10.Organization Process Assets
PMP - Project Time Management https://www.facebook.com/waleed.naggar 33

Estimate Activity Duration: T & T (1)


1. Expert Judgment 2. Analogous Estimating (Top-down) - Use actual values of a similar project 3. Parametric Estimating 4. Group Decision making techniques 5. Reserve Analysis

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

34

Estimate Activity Duration: T & T (2)


6. Three-point Estimate

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

35

Program Evaluation & Review Technique (PERT)


Uses a weighted average duration estimate to calculate activity durations.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

36

Gantt Chart
Bar charts are relatively easy to read, and are

frequently used in management presentations.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

37

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

38

Estimate Activity Duration: Outputs


1. Activity Duration Estimates: Quantitative estimates of the likely duration of each activity as well as the range of possible

results ( 10 2 day )
2. Project Document Updates
PMP - Project Time Management https://www.facebook.com/waleed.naggar 39

Quiz
The optimistic estimate is 1, the pessimistic

estimate is 9 & the most likely estimate is 8.


What is the PERT estimate? A. 9 B. 7 C. 8 D. 6
PMP - Project Time Management https://www.facebook.com/waleed.naggar 40

6.6 Develop Schedule


The process of analyzing activity sequence, durations, resource

requirements, & schedule constraints to


create a project schedule.

Developing an acceptable schedule is


often an iterative process.

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

41

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

42

Develop Schedule: Inputs (1)


1. Schedule Management Plan 2. Activity List 3. Activity Attributes 4. Project Schedule Network Diagrams

5. Activity Resource Requirements


6. Resource Calendars

7. Activity Duration Estimates


PMP - Project Time Management https://www.facebook.com/waleed.naggar 43

Develop Schedule: Inputs (2)


8. Project Scope Statement 9. Risk Register 10.Project Staff Assignment 11.Resource Breakdown Structure

12.Enterprise Environmental Factors


13.Organizational Process Assets

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

44

Develop Schedule: T & T


1. Schedule Network Analysis 2. Critical Path Method 3. Critical Chain Method 4. Resource Optimization Techniques

A. Resource Leveling
B. Resource Smoothing

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

45

Develop Schedule: T & T


5. Modeling Techniques What-if scenario analysis Simulation 6. Leads and Lags 7. Schedule Compression

Crashing
Fast tracking

8. Scheduling Tools
PMP - Project Time Management https://www.facebook.com/waleed.naggar 46

Critical Path
The longest duration path through a network diagram which represents the shortest time to complete the project
A:2 End Start D:2 E:2 H:2

B:3

C:4

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

47

Critical Chain

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

48

Resource Leveling & Smoothing

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

49

Duration Compression
Duration compression is a special case of mathematical analysis to shorten the project schedule

without changing the project scope


Crashing : cost & schedule tradeoffs are analyzed to determine how to obtain the greatest amount of compression for the least incremental cost. Fast-tracking: doing activities in parallel that would

normally be done in sequence. Fast tracking often


results in rework and usually increases risk.
PMP - Project Time Management https://www.facebook.com/waleed.naggar 50

Develop Schedule: Outputs


1. Schedule Baseline 2. Project Schedule Milestone Charts Bar Charts Schedule Network Diagrams 3. Schedule Data 4. Project Calendar 5. Project Management Plan Updates 6. Project Document Updates
PMP - Project Time Management https://www.facebook.com/waleed.naggar 51

Float
Total float (Slack): the amount of time an activity
can be delayed without delaying the project end date or/and intermediary milestone.

Free Float (Slack): the amount of time an activity


can be delayed without delaying the start of its

successor.

Project Float: the amount of time a project can be


delayed without delaying the externally imposed project completion date.
PMP - Project Time Management https://www.facebook.com/waleed.naggar 52

Quiz
Which of the following is the BEST project management tool to use to determine the longest time the project will take?

A. WBS
B. Network Diagram C. Bar chart D. Project Charter

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

53

Quiz
Which of the following is correct? A. A schedule can have several critical paths B. There must be only one critical path C. The network diagram will change every time the end date changes D. A project can never have negative float

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

54

6.6 Control Schedule


The process of monitoring the status of the project to update project progress and manage changes to schedule baseline. Concerned with:

Determine current status


Influence the factors that cause changes

Manage actual changes as they occur


PMP - Project Time Management https://www.facebook.com/waleed.naggar 55

Control Schedule: Inputs


1. Project Management Plan 2. Project Schedule 3. Work Performance Data 4. Project Calendars 5. Schedule Data 6. Organizational Process Assets

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

56

Control Schedule: T & T (1)


1. Performance Reviews Trend Analysis Critical Path Method Critical Chain Method

Earned Value Management


2. Project Management Software

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

57

Control Schedule: T & T (2)


3. Resource Optimization Techniques 4. Modeling Techniques 5. Leads and Lags

6. Schedule compression
7. Scheduling Tool
PMP - Project Time Management https://www.facebook.com/waleed.naggar 58

Control Schedule: Outputs


1. 2. 3. 4. Work Performance Information Schedule Forecasts Change Requests Project Management Plan Update 1. Schedule baseline 2. Schedule Management Plan 3. Cost baseline 5. Project Document Updates 6. Organizational Process Assets Updates
PMP - Project Time Management https://www.facebook.com/waleed.naggar 59

Quiz
All of the following relate to controlling the

schedule EXCEPT:
A. Value analysis. B. Crashing. C. Float. D. Mandatory dependencies

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

60

PMP - Project Time Management

https://www.facebook.com/waleed.naggar

61

You might also like