MEMBINA DAN MENYIAPKAN GELANGGANG SKUASY SERTA KERJA-KERJA

BERKAITAN DI SEKOLAH MENENGAH KEBANGSAAN TG, PANGLIMA PERANG TG,


MUHAMMMAD, KUANTAN, PAHANG D.M.

1.0 PRELIMINARIES

1.1

Sample dan ujian

1.2

Obligasi statutory

1.3

Pancang tanda

1.4

Pemeriksaan tapak

1.5

Fomen dan pembantu,Laluan sementara,Saliran tapak bina,Kerosakan jalan


sediada,Kebersihan,Air dan kuasa elektrik,Pengawasan,Jagaan dan
perlindungan,Gambar foto kemajuan

1.6

Insuran kemalangan/kerosakan

1.7

PERKESO

1.8

Insuran kerja

1.9

Kecacatan selepas siap

1.10 Sample barang dan ketukangan


1.11 Tempat simpanan barang
1.11.1 Pasang
1.11.2 Buka
1.12 Peti pertolongan cemas
1.13 Site office
1.13.1 Pasang
1.13.1 Buka
1.14 S.O equipment:topi,boot,jaket,telefon,komputer camera.
1.15 Alat kerja ukur
1.16 Dinding adang

1.16.1 Pasang
1.16.2 Buka
1.17 Program kerja
1.18 Papan Tanda
1.18.1 Pasang
1.18.2 Buka
1.19 Pemasangan sambungan kekal bekalan air dan elektrik
1.20 Penyediaan dokumen kontrak
1.21 Mengemas/membersih selepas siap
1.22 Ujian proba
1.23

NIOSH

1.24

Lantikan jurukur Berlesen - sebelum mula kerja

1.25

Lantikan jurukur Berlesen - ukur tapak selepas siap

1.26

M & E Coordinator

1.27

4 set as built drawing

2.0 BANGUNAN

2.1 Work Below Lowest Floor Finishes


2.1.1

Site Clearing

2.1.2

Pad Footing
2.1.2.1 Excavate for pad footing
2.1.2.2 Formwork
2.1.2.3 Lean Concrete
2.1.2.4 16mm High tensil bar
2.1.2.5 12mm High tensil bar
2.1.2.6 Concrete grade 35

2.1.3

Stump
2.1.3.1 20mm High tensil bar

2.1.3.2 16mm High tensil bar


2.1.3.3 10mm ms link
2.1.3.4 Formwork
2.1.3.5 Concrete grade 35
2.1.3.6 Anti Termite

2.1.4

Ground Beam
2.1.4.1 Excavate for ground beam
2.1.4.2 Formwork
2.1.4.3 Lean Concrete
2.1.4.4 25mm High tensil bar
2.1.4.5 20mm High tensil bar
2.1.4.6 16mm High tensil bar
2.1.4.7 12mm High tensil bar
2.1.4.8 10mm ms stirrup
2.1.4.9 Concrete grade 35
2.1.4.10

Anti Termite

2.1.5 Ground Slab


2.1.5.1 Crusher run bedding
2.1.5.2 Anti termite
2.1.5.3 Damp proof membrane
2.1.5.4 Formwork
2.1.5.5 10mm ms bar
2.1.5.6 150mm thk. Concrete grade 35

2.1.6 R.C Seating


2.1.6.1Formwork
2.1.6.2 10mm dia. Ms bar
2.1.6.3 Concrete grade 35
2.1.7

Apron & Perimeter drain


2.1.7.1 Excavation for apron
2.1.7.2 Crusher run bedding
2.1.7.3 Anti termite
2.1.7.4 Extra excavation
2.1.7.5 Concrete grade 20
2.1.7.6 Perimeter drain
2.1.7.7 Ms grating
2.1.7.8 Ramp
2.1.7.9 Sump

2.2 FRAME
2.2.1 Column
2.2.1.1 16mm High steel bar
2.2.1.1 10mm links
2.2.1.2 Formwork
2.2.1.3 Concrete

2.2.2

Roof Beam
2.2.2.1 Formwork
2.2.1.2 25mm high steel bar
2.2.1.3 20mm high steel bar

2.2.1.4 16mm high steel bar


2.2.1.5 12mm high steel bar
2.2.1.6 10mm ms stirrup
2.2.1.7 Concrete

2.2.3

Upper Roof Beam


2.2.3.1 Formwork
2.2.3.2 Rebar
2.2.3.3 Concrete

2.3 UPPER FLOOR CONSRUCTIONS


2.3.1

Upper Floor Slab


2.3.1.1 Formwork
2.3.1.2 10mm dia. High tensil bar
2.3.1.3 Concrete grade 35

2.4 ROOF
2.4.1

Roof Structure
2.4.1.1 Kerangka T1
2.4.1.2 Kerangka T2
2.4.1.3 Bracing and plates

2.4.2

Roof Finishes
2.4.2.1 Roof decking
2.4.2.2 fibre glass wool, chicken wiremesh etc.
2.4.2.3 aluminium foil

2.4.2.4 Galvanised iron flashing

2.5 STAIRCASE
2.5.1

Formwork

2.5.2

Rebar

2.5.3

Concrete

2.6 EXTERNAL WALL


2.6.1

Brickworks

2.6.2

Damp proof course

2.6.3

6mm dia. Ms bonding ties

2.7 WINDOWS AND DOORS


2.7.1

Windows
2.7.1.1 Lintol
2.7.1.2 Naco Frame
2.7.1.3 5mm thick glass panel nako

2.7.2

External Door
2.7.2.1 Lintol
2.7.2.2 Metal Frame
2.7.2.3 Timber Door
2.7.2.4 Ironmongery

2.7.3

INTERNAL WALLS
2.7.3.1 Brickworks
2.7.3.2 Damp proof course

2.7.3.3 6mm dia. Ms bonding ties


2.7.3.4 S/S handrail
2.7.3.5 Glass Backwall
2.7.3.6 Playboard

2.7.4

INTERNAL WALL FINISHES


2.7.4.1 Plastering
2.7.4.2 Squash court wall finishes - front and side walls
2.7.4.3 300 x300mm homogeneous wall tile
2.7.4.4 Painting - Plastered surface
2.7.4.5 Painting - Squash court wall

2.7.5

INTERNAL FLOOR FINISHES


2.7.5.1 Tiling 300mm x 300mm
2.7.5.2 tiling 600mm x 600mm
2.7.5.3 300 x 75 nosing tiles
2.7.5.4 Tiling 300mm x 300mm - seating area
2.7.5.5 tiling 600mm x 600mm - seating area
2.7.5.6 100mm skirting
2.7.5.7 Parquet to court
2.7.5.8 Timber floor finish
2.7.5.9 WPB 12mm plywood
2.7.5.10Rubber pads
2.7.5.11Vapour proof barrier membrane
2.7.5.12Epoxy
2.7.5.13Cement render

2.7.6

INTERNAL CEILING FINISHES


2.7.6.1 Ceiling suspended/board
2.7.6.2 Ceiling Joist
2.7.6.3 Plasterer
2.7.6.4 Painting

2.7.7

EXTERNAL FINISHES
2.7.7.1 Plaster to wall, column and beams
2.7.7.2 Painting to wall, column and beams
2.7.7.3 Cement render to apron

2.7.8

SANITARY APPLIANCES
2.7.8.1 Sanitary Fitting
2.7.8.2 Accessories
2.7.8.3 OKU toilet
2.7.8.4 Accessories

2.7.9

PLUMBING INSTALLATION
2.7.9.1 Cool water installation
2.7.9.2 2 no 500 gallon water tank
2.7.9.3 Waste water , soil and vent pipe
2.7.9.4 Gully trap
2.7.9.5 Manhole
2.7.9.6 Testing

2.7.10

SUNDRIES
2.7.10.1

Squash court line

2.7.10.2

table top

2.7.10.3

Builders work in connection

2.7.10.4

counter top

2.7.10.5

Squash equipment

3.0 WANG KOS PRIMA

3.1

KERJA-KERJA ELEKTRIKAL
3.1.1 Pemasangan elektrik
3.1.2 Keuntungan
3.1.3 Layanan

3.2

3.3

PENGUDARAAN
3.2.1

Pengudaraan

3.2.2

Keuntungan

3.2.3

Layanan

PENCEGAH KEBAKARAN
3.3.1

Pencegah kebakaran

3.3.2

Keuntungan

3.3.3

Layanan

4.0 WANG PERUNTUKAN SEMENTARA

4.1

Pembelian Tangki Najis

4.2

Pembayaran Bil Elektrik dan Air

5.0 KERJA-KERJA SEKITAR BANGUNAN

5.1

Penyediaan Tapak dan Kerja Tanah

5.2

Saliran Kotoran Dan Sistem Pembentungan Najis

5.3

5.4

5.2.1

Saliran, manhole

5.2.2

Pemasangan tangki najis

5.2.3

Pagar dan pintu pagar

Sistem Retikulasi Air Luar Dan Kerja Berkaitan


5.3.1

150mm dia GI pipe

5.3.2

50mm dia. GI pipe

5.3.3

100mm dia. MS Pipe

5.3.4

110mm dia. HDPE pipe

5.3.5

Hydrant

5.3.6

Paip marker

Ujian Proba Pengesahan


5.4.1

5.5

Menjalankan ujian proba pengesahan

Saliran Permukaan
5.5.1

Longkang & Ms grating

5.5.2

Sump & ms grating

5.6 Kerja Menanam Rumput

5.7

6.0

5.6.1

Close turfing

5.6.2

Plat No. Bangunan

Pagar
5.7.1

Pagar dawai berangkai dengan bendul termasuk pintu pagar

5.7.2

Testing & Commenssioning

PENYERAHAN