You are on page 1of 34

Welcome to Presentation on

Multi-modal International
Hub Airport at Nagpur
(MIHAN)
Why Nagpur As A Hub Airport??

 Nagpur – Centre of India.


 Well connected – East– West & North–South by 5
National Highways and 2 Rail routes. (N-S corridor
passes through Nagpur).
 Existing International Airport
 Govt. of India declared it as an International Passenger
& Cargo Hub.
 Most conducive weather dynamics for air
transportation.
 Wide catchment area spreading almost 500 kms.
radius.
 Plenty of land suitable for unrestricted development
available
Existing Transportation Network - Nagpur

Kolkata Kolkata

Road Rail
Domestic Hubbing Potential
International Hub Airport at Nagpur

Moscow
Frankfurt
London
(6843.66Kms)
(7404.87Kms) Beijing (4120.40Kms)

Seoul Tokyo (6058.74Kms)


Cairo
(4882.05Kms)
(4843.47Kms)

Colombo Singapore (3480.17Kms)


(1548.33Kms)
Surabaya

Johannesburg
(7582.18Kms) Canberra
(9678.53Kms)
India Definitely Needs A Hub Airport

5 hours
Flying zone
City-wise Comparative Chart

Hyderabad

Bangalore

Chennai
Mumbai

Nagpur
Delhi
Pune
Parameters

Area (Sq. Kms) 1,864 430 484 438 1486 172 218

Population (in Lakhs) 55 27 57 163 128 64 27

Road length/vehicle
0.11 N.A. 0.13 0.13 0.68 0.29 4.76
(in metres)
Power Tariff (Industrial)
4.30 3.90 4.15 3.90 4.25 4.15 2.70*
(Rs. per unit)
Comm. Real Estate Rates
7000 3350 4000 10000 7712 2500 2000
(Rs./Sq.ft.)
Consumer Price Index 441 442 476 420 427 506 410
Location Of MIHAN & Nagpur City

MADC
MIHAN Project
MIHAN Project

 Development of existing airport as an multi-modal


International passenger and cargo hub of India
 Development of adjacent SEZ over an area of 1475
Hectares
 IT centre
 Health City
 Captive Power Plant
 Value added industries
 Manufacturing industries
 100% Export oriented units
 Support Services in MIHAN Project
 Road terminal with warehouses and other facilities
 Rail Terminal with container depot
MIHAN Project

 Total Project Area 4025 ha.


 Airport 1200 ha.
 Road & Rail Terminal 200 ha.
 SEZ 1475 ha.
 Captive Power House 52 ha.
 IT Parks 400 ha.
 Health City 60 ha.
 Other Manufacturing &Value Added Units 963 ha.
 International School 10 ha.
 Residential, Open Spaces, Hotels, Roads,
Interchange & RoB, Water Supply, Storm Water
Drainage, Sewage System, Entertainment, Utility 1140 ha
& Land for IAF (exchange)
Special Economic Zone (SEZ)

 Govt. of India has in principle approved SEZ at


Nagpur.
 A Captive Power Plant to provide uninterrupted
quality power
 A Health City with  a chain of Super Specialty
Hospitals
 I.T. zone.
 Value Added commercial complex
 World class facilities & Efficient service at
competitive price.
 Infrastructure estimates - Rs. 849 Crores.
Neighbours in MIHAN

 Dr. D. Y. Patil Deemed University.


 Satyam Computer Services Ltd.
 Shapoorji Pallonji & Co. Ltd.
 Reatox Builders & Developers
 L&T Infocity Ltd.
 Haldirams Manufacturing Co. Ltd*
 Max Aerospace & Aviation Ltd*
 Patni Computer Services Ltd.*
 Others – M.R.O.
MoU with Satyam
Major Bank’s Financing MIHAN Project

 Vijaya Bank.
 Jammu & Kashmir Bank Ltd.
 Dena Bank Ltd.
 Bank Of Maharashtra Ltd.
 Punjab National Bank Ltd.
 Bank Of Baroda Ltd.
 Oriental Bank of Commerce
Major Airlines Operating from Nagpur

 Air-India
 Indian Airlines
 Jet Airways
 Air Deccan
 Al-Arabia
 Alliance Air
 Qatar Airways
Role of MADC

 Facilitator and Coordinator


 To implement the project on PPP basis
 Equity participation by MADC – 26% to 49%
 MADC to approve the plans and buildings
 Government permissions and clearance, if required.
 Required Real Estate.
 Development of regional airports – Shirdi & others
 Suggestions invited to develop these airports as
also real estate development on PPP basis.
Investment Opportunities in MIHAN

 PPP system for projects “or” Contracting “or” Real


Estate Development.
 Advertisement in national newspapers & on Website
“www.madcindia.org”
 Two Envelope System for selection
 Technical & Experience Clearance.
 Financial Offer.
 MADC allots land, approves Plan, provides Power,
Water, Roads, Telecom, Sewage Systems.
 Provide Infrastructure within legal timeframe.
 System of Bonus/Penalty for early completion/Delays.
Special Economic Zone

 Project - Setting of Export Units


 Approval - In principle by Govt. of India
 Consultants - Scott Wilson Kirkpatrick India Pvt.
Ltd.
 Area - 1475 Ha.
 Land Price - 200 Ha of land @ Rs. 75lakhs/Ha
 Allotment of land - First-come-First basis
 Basic Infrastructure - Provided by MADC
 State SEZ Act - Approved by Cabinet
Captive Power Plant in SEZ

 Project - 2 x 50 MW with backup


 Cost estimates - Rs. 349 Crores
 Consultants - Ernst & Young Pvt Ltd.
 Return on Equity - 18%
 Expression of Interest by - March 2006.
 Environmental Clearance - Obtained
 Fuel - Coal / Gas (operator to
choose)
 Land (52 Ha.) - Virtually in possession
 Method - BOT/BOOT basis.
 Period of Lease - 33 years

Transmission & Distribution for Electricity

 Project - Electric supply network in


project
 Cost estimates - Rs. 80 Crores
 Consultants - Premier Mott-MacDonald
 Tenders by - March 2006.
 Environmental Clearance - Being Obtained
 Method - Competitive bidding
 Stage - Design & Specifications
finalised.
Road Terminal

 Project - 1,000 Truck parking,


Warehousing, ColdStorages, Open stockyards,
Central Facility building, Dormitories, etc.
 Cost estimates - Rs. 72 Crores
 Consultants - Prasad Associates, Hyderabad.
(Designing) - Darashaw & Co. Pvt Ltd.
(Financial)
 Project IRR - 21%
 Expression of Interest - to be submitted by 10th
March 2006
 Land (60 Ha.) - Mostly in possession, acquisition
on
 Method - BOT/BOOT basis.
Rail Terminal

 Project - Rail Container Terminal, Container


stockyard, Etc.
 Cost estimates - Rs. 58 Crores
 Consultants - CRISIL.
 Project IRR - 23%
 Expression of Interest - to be submitted by 13th
March 2006
 Land (24/32 Ha.) - Mostly in possession, acquisition
on
 Method - BOT/BOOT basis.
 Period - 66 years
Telecommunication Network

 Project - Ducting, Optical Fibre Cable laying,


Building, Towers, etc.
 Cost estimates - Rs. 70 Crores
 Consultants - In-house with Tata Teleservices
(M) Ltd.
 Tenders by - April 2006.
 Method - Competitive bidding.
Health City in SEZ

 Project - Setting of Super-specialty


Hospitals (Neurology, Orthopedics, Cardiology,
Pediatrics, Ophthalmology, Organ transplantation,
Senior citizen home, etc.)
 Cost estimates - Rs. 300 Crores
 Consultants - Ernst & Young Pvt Ltd.
 Expression of Interest by - April 2006.
 Land (50 Ha.) - Mostly in possession, acquisition
on
 Method - By PPP through Special Purpose
Vehicle & Private Investors
Water supply, Sewage Disposal System

 Project - Water supply, Sewage Disposal


system
 Cost estimates - Rs. 250 Crores
 Consultants - Kirloskar Consultants Ltd
 Tenders by - End of March 2006.
 Method - Open & Competitive bidding
 Tendering Details
 Head Works & Raw Water Transmission.
 Water Supply Scheme
- Water Treatment Plant, Ground Services Reservoir, Elevated
Service Reservoir, Pumping Station
- Feeder Mains & Distribution Network
 Sewage Disposal Sector/ Storm Water drainage system
- Sewage Treatment plant, Tersely treatment Plant, Sewage
collection Network, Nalla diversion & related works
 Electrical & Mechanical Works
Construction of Roads in MIHAN

 Project - Construction of Roads.


 Cost estimates - Approximately Rs. 150 Crores
 Consultants - Span Consultants Pvt Ltd
 Tenders - To be submitted by 16th March 2006
 Method - Competitive bidding
Flyover & Interchange on NH-7

 Project - Flyover & Interchange on NH-7 &


Railway over Bridge
 Cost estimates - Rs. 65 Crores
 Consultants - Consulting Engineering Services (India)
Pvt Ltd
 Tenders by - Mid March 2006.
 Method - Competitive bidding
Central Facility Building in SEZ

 To accommodate various offices and service


providers
 Total built up area of about 2 Lakhs Sq.Ft.
 Estimated cost of the project Rs.20 Crores
 Design and Consultancy services by the
Engineering, Design & Research Centre (EDRC) of L
& T Ltd
 Tenders to be invited by middle of May 2006
Status of the Project

 MIHAN project approved by the Government of


Maharashtra.
 Nagpur airport declared as International Hub Airport
for Passenger & Cargo operation by Government of
India.
 Techno Economic Feasibility Study done by a
consortium of Internationally reputed consultant lead
by L&T Ramboll consulting Engineers Limited
 MIHAN SEZ Business Plan, approved in principle by
GoI
 Land acquisition in progress, 1475 Ha in possession.
 International School to be functional by 2007.
 Developer for Modern Township in MIHAN appointed.
Letter of Intent for International School
Real Estate Development

 Huge scope for real estate development in MIHAN


Project Area
 Major real estate development for providing housing
required for SEZ workers
 Other commercial real estate development
 Tenders will be invited over a period of time
Implementation Plan

MADC to implement the project


components by Open and
Transparent Tender System
In pursuit of this objective we invite
you to participate to make this
Project efficient, user friendly & a
landmark to the nation.

You might also like