Name

Duration

Start

Finish

Predecessors

Start

0 days 11/25/13 8:00 AM

11/25/13 8:00 AM

Stablish the database Baseline

5 days 11/25/13 8:00 AM

11/29/13 5:00 PM

Clustering Strategy

2 days 12/2/13 8:00 AM

12/3/13 5:00 PM

Quotation of Connecting the Blade to the 3par

7 days 11/25/13 8:00 AM

12/3/13 5:00 PM

Blade to 3Par connection

5 days 12/4/13 8:00 AM

12/10/13 5:00 PM

Freeing 2 blades 2 CPU's 64 bit for clustering

5 days 12/2/13 8:00 AM

12/6/13 5:00 PM

Installing Windows 2008 R2 on Blades

2 days 12/9/13 8:00 AM

12/10/13 5:00 PM

Configuring the Securepath to 3par

1 day 12/11/13 8:00 AM

12/11/13 5:00 PM

Zoning the 3par

1 day 12/12/13 8:00 AM

12/12/13 5:00 PM

10

Preparing 1st Cluster

11

Cluster configuration

12

Preparing GSSCREPL Migration

13
14
15
16

18 days 11/25/13 8:00 ... 12/18/13 5:00 ...


1 day 11/25/13 8:00 AM

11/25/13 5:00 PM

2 days 12/13/13 8:00 AM

12/16/13 5:00 PM

GSSCREPL Migration

1 day 12/17/13 8:00 AM

12/17/13 5:00 PM

12

Clustering Testing

1 day 12/18/13 8:00 AM

12/18/13 5:00 PM

13

Migration Strategy

2 days 11/25/13 8:00 AM

11/26/13 5:00 PM

Preparing 2nd Cluster

17

Preparing the .33 server for migration

18

26 days 11/25/13 8:00 ... 12/30/13 5:00 ...


5 days 12/19/13 8:00 AM

12/25/13 5:00 PM

14

Backing up the .33 server

1 day 12/26/13 8:00 AM

12/26/13 5:00 PM

17

19

OS reinstallation .33

1 day 12/27/13 8:00 AM

12/27/13 5:00 PM

18

20

Cluster Setup

1 day 12/30/13 8:00 AM

12/30/13 5:00 PM

19

21

Migration

1 day 11/25/13 8:00 AM

11/25/13 5:00 PM

GSSC Clustering - page1

Resource Names

24 Nov 13
F S S M T W T
11/25

24 Nov 13
1 Dec 13
8 Dec 13
15 Dec 13
22 Dec 13
29 Dec 13
5 Jan 14
12 Jan 14
19 Jan 14
26 Jan 14
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W
11/25

GSSC Clustering - page2