You are on page 1of 659

Arch.

Sherif El-wishahy, PMP

Course Objectives
After completing this course, you should be able to: Help you to prepare for the PMP Certification Exam Make the most of limited study time for taking the PMP exam Become familiar with the exam format and question types Develop a personal study plan

Identify personal areas of competency and weakness


Reinforce knowledge of the ten Project Management Knowledge Areas, and the five Project Management Process Groups.
Arch. Sherif Elwishahy, PMP

Project Management Institute


The Project Management Institute (PMI) was founded in 1969 and started offering the PMP certification exam in 1984. The PMI certification program has attained the (ISO) 9001. PMI provides certification such as:
Project Management Professional (PMP) Certified Associate Project Manager (CAPM) Program Management Professional (PgMP) PMI Scheduling Professional (PMI SP) PMI Risk Management Professional (PMI RMP)
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

It demonstrates proof of professional achievement. It increases your marketability. It provides greater opportunity for advancement in your field. It raises customer confidence in you and in your companys services.

Arch. Sherif Elwishahy, PMP

About the Exam


4 hours to write the exam Multiple Choice format Provides option to mark answers for later review 175 / 200 questions are actually marked 25 are dummy questions You will not know which 25 are not marked therefore answer all carefully 108/175 correct to pass at 61% You will be notified if you pass or fail immediately after completing the exam You will not be given your actual mark 3 attempts per year but you will pass this !!
Arch. Sherif Elwishahy, PMP

Project Management Introduction

Project Definition A project is : A temporary endeavor undertaken to create a unique product, service, or result

Arch. Sherif Elwishahy, PMP

Project Definition
Temporary: Projects have a definite beginning and end. Projects are unique: first time not repetitive. Progressively: proceeding in steps Elaborated: worked with care and detail

Arch. Sherif Elwishahy, PMP

Project Definition
Projects end when their objectives have been reached or the project has been terminated. Scope of project should remain constant even as characteristics are progressively elaborated.

Arch. Sherif Elwishahy, PMP

Examples of projects
Developing a new product, service, or result. Effecting a change in the structure, processes, staffing, or style of an organization. Developing or acquiring a new or modified information system (hardware or software). Conducting a research effort Constructing a building, or infrastructure. Implementing, improving, or enhancing existing business processes and procedures.
Arch. Sherif Elwishahy, PMP

Project Management
The application of knowledge, skills, tools and techniques to project activities in order to meet the project requirements, through the appropriate application and integration of the 47 logically grouped project management processes, which are categorized into five Process Groups. Initiating, Planning, Executing, Monitoring and Controlling, and Closing.
Arch. Sherif Elwishahy, PMP

The Project Manager

Is the person assigned by the performing organization to achieve the project objectives. Characteristics of the Project Manager: knowledge: what the P.M. knows about project management. Performance: what is the P.M. able to do. Personal: how the P.M. behaves.

Arch. Sherif Elwishahy, PMP

Project Managers Areas of Expertise

Arch. Sherif Elwishahy, PMP

Project Constraints
Quality / Scope Defines the specifications of the work of the project. Cost / Resources Requires constant monitoring, immediate corrective action Schedule / Time Most likely to change

Arch. Sherif Elwishahy, PMP

Program Management

Program management A group of related projects managed in a coordinated way to obtain benefits and control not available from managing them individually.
Ex. a new communications satellite system.

Arch. Sherif Elwishahy, PMP

Portfolio Management

Portfolio management A collection of projects or programs and other work that are grouped together to facilitate effective management of that work to meet strategic business objectives. Ex. an infrastructure firm makes a portfolio that
Includes a mix of projects in oil and gas, power.

Arch. Sherif Elwishahy, PMP

Projects and Strategic Planning


Projects are authorized as a result of: A market demand A business need A customer request A technological advance A legal requirement
Arch. Sherif Elwishahy, PMP

Project management office (PMO)


Is an organizational body or entity assigned various responsibilities related to the centralized and coordinated management of those projects under its domain. The primary function of a PMO: Managing shared resources across all projects. Coaching, mentoring, and training for PM. Monitoring compliance with project management standards. Developing and managing project standards. Coordinating communication across projects.
Arch. Sherif Elwishahy, PMP

Projects and Operational Work Operational Work Planned, executed & Controlled series of tasks and activities Constrained by limited resources to produce an output/product.
operation Projects

Ongoing and repetitive


Similar outputs Permanent resources

Temporary
Unique output

Resources temporary upon-need basis


Arch. Sherif Elwishahy, PMP

Organizational Influences & Project Life Cycle

Organizational Influences on Project Management


Organizational Cultures and Styles Cultures and styles are group phenomena known as cultural norms, which develop over time. Organizational culture is shaped by the common experiences of members of the organization. Organizations develop unique cultures over time by practice and common usage. The organizations culture is an enterprise environmental factor.

Arch. Sherif Elwishahy, PMP

Organizational Influences on Project Management


Organizational Communications Project management success is highly dependent on an effective organizational communication style. Project managers in distant locations are able to communicate with all relevant stakeholders to facilitate decision making.

Arch. Sherif Elwishahy, PMP

Organizational Influences on Project Management Organizational Structure PMI Defines 5 types of Organizational Structure: Functional Organizations. Projectized Organizations. Weak Matrix Organizations. Balanced Matrix Organizations. Strong Matrix Organizations.
Arch. Sherif Elwishahy, PMP

Functional Organization
C.E.O
Project coordination

Functional Manager

Functional Manager

Functional Manager

Functional Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Arch. Sherif Elwishahy, PMP

Projectized Organization
Project coordination

C.E.O

Project Manager

Project Manager

Project Manager

Project Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Arch. Sherif Elwishahy, PMP

Weak Matrix Organization


C.E.O

Functional Manager

Functional Manager

Functional Manager

Functional Manager

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Staff

Project coordination

Arch. Sherif Elwishahy, PMP

Balanced Matrix Organization


C.E.O

Functional Manager

Functional Manager

Functional Manager

Functional Manager

Staff

Staff

Staff

Staff

Project manager

Staff

Staff

Staff

Project coordination

Arch. Sherif Elwishahy, PMP

Strong Matrix Organization


C.E.O

Functional Manager

Functional Manager

Functional Manager

Manager of Project Managers

Staff

Staff

Staff

Project manager

Staff

Staff

Staff

Project manager

Project coordination

Arch. Sherif Elwishahy, PMP

Organizational Structure
Organization Structure

Project Characteristics

Functional
Little or None

Weak Matrix
Weak Few Available

Balanced Matrix
Balanced w/ Funct. Some Available

Strong Matrix
Strong Mostly Available PM

Projectized
Complete Available PM Dedicated

PM Authority

Resource None / few Availability Available Budget Control Project Team PMs Title

Functional Functional Balanced Mgr. Mgr. Not Dedicated Project Lead /


Coordinator

Mostly Dedicated Not Dedicated Dedicated


Lead /
Coordinator /

Expeditor

Project Project or Program Manager Program or Project Manager Manager


Arch. Sherif Elwishahy, PMP

Organizational Process Assets


Include any or all process related assets, from any or all of the organizations involved in the project. Components may include: 1.Processes and Procedures Organizational standard processes Templates Organization communication requirements Project closure guidelines Financial Control procedures Change Control procedures
Arch. Sherif Elwishahy, PMP

Organizational Process Assets

2.Corporate Knowledge Base Projects files. Historical Information. Issues & defect management databases. Financial databases

Arch. Sherif Elwishahy, PMP

Enterprise Environmental Factors


Refer to both internal and external environmental factors that surround and influence a projects success. Organizational culture, structure, and processes. Government or industry standards. Infrastructure. Existing human resources. Company work authorization systems. Marketplace conditions. Political climate. Organizations established communications channels. Project management information systems (PMIS)
Arch. Sherif Elwishahy, PMP

Project stakeholders
A stakeholder is someone whose interests may be positively or negatively impacted by the project.

Arch. Sherif Elwishahy, PMP

Project Governance
Project governance is an oversight function that is aligned with the organizations governance model and that encompasses the project life cycle. Project governance involves stakeholders as well as documented policies, procedures, and standards; responsibilities; and authorities.

Arch. Sherif Elwishahy, PMP

Project Governance
Elements of project governance framework : Project success and deliverable acceptance criteria. Process to identify, escalate, and resolve issues. Relationship among the project team, and external stakeholders. Project organization chart that define project roles. Processes and procedures for communication. Project decision-making processes.

Arch. Sherif Elwishahy, PMP

Project Team
Project management staff. Project staff. Supporting experts. User or Customer Representatives. Business partner. Business partners members.

Arch. Sherif Elwishahy, PMP

Project Team
Composition of Project Teams

It varies based on factors such as organizational culture, scope, and location. The relationship between the project manager and the team varies depending on the authority of the project manager.

Arch. Sherif Elwishahy, PMP

Project Team
Examples of basic project team compositions: Dedicated: all or a majority of the project team members are assigned to work fulltime on the project. Part-Time: Some projects are established as temporary additional work, with part-time team members may also be assigned to more than one project at a time

Arch. Sherif Elwishahy, PMP

Project Life Cycle


A project life cycle is the series of phases that a project passes through from its initiation to its closure, the phases are generally sequential and sometimes overlapping.
Initiating Planning Executing Monitoring and controlling Closing Initiating Planning Executing Monitoring and controlling Closing Initiating Planning Executing Monitoring and controlling Closing

Phase 1

Phase 2

Phase 3

Arch. Sherif Elwishahy, PMP

Characteristics of the Project Life Cycle

Arch. Sherif Elwishahy, PMP

Characteristics of the Project Life Cycle

Arch. Sherif Elwishahy, PMP

Project Phases
A project phase is a collection of logically related project activities that lead to the completion of one or more deliverables. A project may be divided into any number of phases. All phases have similar characteristics: The work has a distinct focus that differs from any other phase. Achieving the objective of the phase requires controls or processes unique to the phase or its activities. The closure of a phase ends with the transfer or handoff of the work produced as the phase deliverable.
Arch. Sherif Elwishahy, PMP

Project Phases
Phase-to-Phase Relationships

Arch. Sherif Elwishahy, PMP

Predictive Life Cycles


Also known as Fully Plan-Driven: are ones in which the project scope, and the time and cost required to deliver that scope, are determined as early in the project life cycle as practically possible.

Arch. Sherif Elwishahy, PMP

Iterative and Incremental Life Cycles


Are ones in which project phases (also called iterations) intentionally repeat one or more project activities as the project teams understanding of the product increases. Iterations develop the product through a series of repeated cycles, while increments successively add to the functionality of the product. These life cycles develop the product both iteratively and incrementally.

Arch. Sherif Elwishahy, PMP

Adaptive Life Cycles


Also known as change-driven or agile methods: are intended to respond to high levels of change and ongoing stakeholder involvement. Difference between Adaptive methods and iterative: Iterations are very rapid usually with a duration of 2 to 4 weeks. Fixed in time and cost.

Arch. Sherif Elwishahy, PMP

Project Management Processes

Project Management Process Groups

Arch. Sherif Elwishahy, PMP

Project Management

Time Management
Integration Management Scope Management

Human Resource Management

Cost Management

Quality Management

Procurement Management

Communications Management

Risk Management

Stakeholder Management
Arch. Sherif Elwishahy, PMP

Project Management Process Groups

Start Project

End Project

Arch. Sherif Elwishahy, PMP

Process Groups Interaction

Arch. Sherif Elwishahy, PMP

Project Management Process Groups Initiating process group performed to define a new project or a new phase of an existing project. Planning process group performed to establish the total scope of the effort, define and refine the objectives, and develop the course of action required to attain those objectives.

Arch. Sherif Elwishahy, PMP

Project Management Process Groups Executing process group performed to complete the work defined in the project management plan to satisfy the project specifications. Monitoring and Controlling process group the processes required to track, review, and regulate the progress and performance of the project. Closing process group performed to formally complete the project, phase, or contractual obligations. Arch. Sherif Elwishahy, PMP

Initiation Process Group


As you engage potential team members and stakeholders, project initiation activities establish the scope, goals and preliminary plan. Key Activities Scope Definition Confirm sponsorship and funding Confirm initial clarification of requirements Determine Project Stakeholders and their roles Draft high level plan for inputs and resources
Arch. Sherif Elwishahy, PMP

Initiation Process Group


Sponsor /customer Needs
Project Statement of Work Company culture and existing systems Processes, procedures, and historical information Project manager assists the sponsor with the charter if necessary

Sponsor issues the charter

Project manager develops the preliminary project scope statement and the project management plan

The Project management plan is bought into, approved, realistic, and formal
Arch. Sherif Elwishahy, PMP

Initiation Process Group

Arch. Sherif Elwishahy, PMP

The planning processes develop the project management plan and project documents. As more information is known about the project additional planning may be required. The progressive detailing of the project management plan is called ( rolling wave planning) The project management plan defines how the project is executed, monitored, controlled, and closed.
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Project plan execution involves managing and performing the work described in the project plan. The majority of time and money is usually spent on execution. The application area of the project directly affects project execution. The outcomes of the project are realized during and after the execution stage.

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Track and review actual project accomplishments and results to project plans. Help team and management take corrective action early when project performance varies significantly from original plans. Tracks all major project variables Cost Time Scope Quality of Deliverables
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Administrative Closure : generating necessary information to formally recognize Phase or project completion. Contract Close-out : completion and delivery of project deliverables and resolving open issues such as: Procurement Audits Product Verification Formal Acceptance Lessons Learned Update Records Archive Records Release Team
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Project Information
Work performance data: The raw observations and measurements identified during activities performed Work performance information: The performance data collected from various controlling processes, Work performance reports: The physical or electronic representation of work performance information
Arch. Sherif Elwishahy, PMP

Project Information

Arch. Sherif Elwishahy, PMP

Question No : 1
Which of the following is NOT a characteristic of a project? A. Constrained by limited resources B. Planned, executed, and controlled C. Creates a unique product or service D. Ongoing and repetitive

Question No : 2
In your organization, all big technical projects go through Initiate, Analyze, Design, Implement, Test, and Closeout. In this context, a project life cycle: A. Defines the product life cycle B. Defines the project phases C. Contains several product life cycles D. Has deliverables that must be completed before work starts on the next phase

Question No : 3
You have been managing a project to construct a flyover on Interstate 10. You have divided the project into phases to provide better management control. Which of the following is a characteristic of a project phase? A. Formal phase completion necessarily includes authorization for the subsequent phase. B. A project phase can be closed with a decision not to initiate the subsequent phase. C. A project phase should not be divided into sub-phases even in complex projects, because it will be difficult to manage. D. All deliverables in the project phase should correspond to the project management process.

Question No : 4
Which of the following is not a Project Management Knowledge Area? A. Project Integration Management B. Project Procurement Management C. Project Configuration Management D. Project Communications Management

Question No : 5
You are responsible for managing a project in your company but you have least authority and have to constantly report to a functional manager. To which organizational structure does your company belong? A. Matrix B. Functional C. Projectized D. Balanced

Question No : 6
Which of the following processes occurs in the Planning Process Group? A. Identify Risks B. Manage Stakeholders Expectations C. Acquire Project Team D. Identify Stakeholders

Question No : 7
In which Process Group will work defined be completed and all the specifications of your project be satisfied? A. Planning Process Group B. Executing Process Group C. Monitoring and Controlling Process Group D. Closing Process Group

Question No : 8
The project charter is created in which Process Group ? A. Executing B. Planning C. Closing D. Initiating

Question No : 9
The person who should be in control of the project during the planning is the : A. Project manager B. Team member C. Functional manager D. Sponsor

Question No : 10
Which of the following is a characteristic of project management processes ? A. Iterative B. Unique C. Unnecessary D. Standardized

Project Integration Management

Integration is What?
Its best described as putting all other management processes of the project into a cohesive whole.

Arch. Sherif Elwishahy, PMP

Project Integration Management


Includes the processes and activities needed to combine, unify, and coordinate the various processes and project management activities. Choosing where to concentrate resources and effort at any given moment. The integration effort also involves making tradeoffs among competing objectives and alternatives. Is the glue that connects all the knowledge areas.

Arch. Sherif Elwishahy, PMP

4. Integration Management
Initiating
4.1

Planning
Executing

4.2

4.3

4.4

Monitoring
4.5

Closing

4.6 Arch. Sherif Elwishahy, PMP

4.1 Develop Project Charter

Arch. Sherif Elwishahy, PMP

4.1 Develop Project Charter


Developing a document that formally authorizes a project or a phase. Documenting initial requirements that satisfy the stakeholders needs and expectations. Is recommended that the project manager participate in the development of the project charter It provides the project manager with the authority to apply resources to project activities..
Arch. Sherif Elwishahy, PMP

4.1 Develop Project Charter

Arch. Sherif Elwishahy, PMP

4.1.1 Develop Project Charter: Inputs


1. Project Statement of work Is a narrative description of products or services to be delivered by the project. The SOW references: Business need Product scope description Strategic plan 2 .Business Case Provides the necessary information from a business standpoint to determine whether or not the project is worth the required investment. Market demand, Organizational need, Customer request, Technological advance, Legal requirement.
Arch. Sherif Elwishahy, PMP

Economic Project Selection Techniques

Arch. Sherif Elwishahy, PMP

4.1.1 Develop Project Charter: Inputs


3. Agreement Is an input if the project is being done for an external customer. 4. Enterprise environmental Factors Governmental or industry standards Organization infrastructure Marketplace conditions 5. Organizational Process assets Organizational standard processes, policies. Templates (e.g., project charter template). Historical information and lessons learned database.

Arch. Sherif Elwishahy, PMP

4.1.2 Develop Project Charter: tools and techniques


1. Expert judgment Expertise is provided by any group or individual with specialized knowledge or training.

2. Facilitation Techniques Brainstorming, conflict resolution, problem solving, and meeting management are examples of key techniques used by facilitators to help teams and individuals accomplish project activities.

Arch. Sherif Elwishahy, PMP

4.1.3 Develop Project Charter: outputs


1. Project Charter Documents the business needs, current understanding of the customers needs, and the new product, or service: Project purpose or justification Measurable project objectives. High-level requirements, and project description. High-level risks. Summary milestone, schedule, and budget. Project approval requirements Assigned project manager, responsibility, and authority, Name and authority of the sponsor or other person(s) authorizing the project charter.
Arch. Sherif Elwishahy, PMP

4.2 Develop Project Management Plan


Arch. Sherif Elwishahy, PMP

Develop Project Management Plan is the process of documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans.

Arch. Sherif Elwishahy, PMP

4.2.1 Develop Project management Plan: Inputs


1. Project Charter

2. Outputs from Planning Processes Outputs of the planning processes described in Chapters 5 through 12 are integrated to create the project management plan. Any baselines and subsidiary management plans that are an output from other planning processes are inputs to this process. Updates to these documents can necessitate updates to the project management plan.
Arch. Sherif Elwishahy, PMP

1. Expert Judgment Expert judgment is utilized to: Tailor the process to meet the project needs, Develop technical and management details. Determine resources and skill levels needed to perform project work. Determine which project documents will be subject to the formal change control process.

2. Facilitation Techniques

Arch. Sherif Elwishahy, PMP

1. Project management Plan Integrates all of the subsidiary management plans and baselines. Schedule baseline. Cost performance baseline. Scope baseline. The life cycle selected for the project and the processes that will be applied to each phase. How work will be executed to accomplish the project objectives. A change management plan that documents how changes will be monitored and controlled.
Arch. Sherif Elwishahy, PMP

4.3 Direct and manage Project Work

Arch. Sherif Elwishahy, PMP

Direct and Manage Project Execution is the process of performing the work defined in the project management plan to achieve the projects objectives.

Arch. Sherif Elwishahy, PMP

4.3.1 Direct and manage Project Execution: Inputs


1. Project management Plan 2. approved Change Requests Approved change requests are the documented, authorized changes to expand or reduce: project scope. The project management plan Procedures Costs Budgets Schedules. Implementation of preventive or corrective actions.
Arch. Sherif Elwishahy, PMP

1. Expert Judgment: 2. Project Management Information System [PMIS]: Is used for communication and information distribution on the project. Not necessary a high tech system 3. Meetings

Arch. Sherif Elwishahy, PMP

1. Deliverables An approved deliverable is any unique and verifiable product, result, or capability to perform a service that must be produced to complete a process, phase, or project. 2. work Performance Data: Information from project activities is routinely collected as the project progresses. Include but not limited to: Deliverable status. Schedule progress. Costs incurred.
Arch. Sherif Elwishahy, PMP

3. Change Requests Can be direct or indirect, externally or internally initiated, and can be optional or mandated. and can include: Corrective action. Preventive action. Defect repair. updates. 4. Project management Plan updates 5. Project Document updates
Arch. Sherif Elwishahy, PMP

4.4 Monitor and Control Project Work


Arch. Sherif Elwishahy, PMP

4.4 monitor and Control Project work

Is the process of: Tracking, reviewing, and regulating the progress to meet the performance objectives defined in the project management plan. It can include: Collecting performance information Measuring performance information Interpreting performance information
Arch. Sherif Elwishahy, PMP

4.4 monitor and Control Project work

Arch. Sherif Elwishahy, PMP

1. Change Requests Corrective action. Preventive action. Defect repair. 2. Work Performance Reports

3. Project management Plan updates


4. Project Document updates
Arch. Sherif Elwishahy, PMP

Configuration management system

Configuration: Functional and physical characteristics of a deliverable (product) as defined in technical documents and achieved in the product. Configuration item: A part that has a set of function and is designated for configuration management. Configuration management system: Provides a standardized way to centrally manage approved changes and baselines within a project.
Arch. Sherif Elwishahy, PMP

Configuration management system Configuration identification: Breaking down the project into configuration items, and creating a unique numbering system for each item, and establishing configuration baselines. Configuration status accounting: Provides a complete record of what happened to the configuration to date. Configuration verification and audit: Ensures that projects configuration items is correct and that corresponding changes are registered, assessed, approved, tracked, and correctly implemented.
Arch. Sherif Elwishahy, PMP

4.5 Perform Integrated Change Control

Arch. Sherif Elwishahy, PMP

4.5 Perform Integrated Change Control

Is the process of: Reviewing all change requests. Approving changes. Managing changes to the deliverables, project documents, and the project management plan. The Change Control Board [CCB] can evaluate changes as part of the change control procedures.
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

1. Expert Judgment.

2. Meetings
3. Change Control Tools:

Manual or automated tools may be used. Based on the needs of the project stakeholders. Used to manage the change requests and the resulting decisions.
Arch. Sherif Elwishahy, PMP

1. Approved Change Requests .

2. Change Log.
3. Project management Plan updates 4. Project Document updates

Arch. Sherif Elwishahy, PMP

4.6 Close Project or Phase


Arch. Sherif Elwishahy, PMP

4.6 Close Project or Phase


Is the process of: Performing the work defined in the project management plan to achieve the projects objectives. It is important to remember that when a project stops (regardless or reason), the project must be closed.

Arch. Sherif Elwishahy, PMP

4.6 Close Project or Phase

Arch. Sherif Elwishahy, PMP

1. Expert judgment These experts ensure the project or phase closure is performed to the appropriate standards.

Arch. Sherif Elwishahy, PMP

1. Final Product, Service, or Result transition This output refers to the transition of the final product, service, or result that the project was authorized to produce.

2. organizational Process assets updates Project files. Project or phase closure documents Historical information.
Arch. Sherif Elwishahy, PMP

Question No : 1
In a recent job interview, you are asked to define the most important characteristic of a project manager. Which of the following will be the best answer? A. Subject matter expert B. Integrator C. Creative person D. Risk minimizer

Question No : 2
Your project is nearing completion, when the customer requests you to include an additional feature in the project`s final product. The BEST course of action is to: A. Include the feature, as it will improve customer satisfaction B. Include the feature -- otherwise the product will not be accepted by the customer C. Talk with the customer and explain that the new feature does not make business sense D. Take the requirement through the change control process

Question No : 3
In your project, you are in the process of performing the work as defined in the project management plan to achieve the project`s objectives. This is done during: A. Direct and Manage Project Execution B. Develop Project Management Plan C. Monitor and Control Project Work D. Create Deliverables

Question No : 4
Project integration management includes the processes and activities needed to identify, define, combine, unify, and coordinate the various processes and project management activities. For successful project integration management, you definitely need(select the best answer): A. A strong matrix organizational structure in your company B. A good communication management plan C. Good project selection techniques D. Positive stakeholders who support the project

Question No : 5
A change in your project schedule has resulted in increased cost and risk. It has also impacted your resource plan. To coordinate changes across the entire project, you will need to rely on which of the following: A. Change control system B. Perform Integrated Change Control C. Change requests D. Changes to project plan baselines

Project Scope

Management

Define Scope

What is the meaning of the word

Scope
? An area in which something acts or operates or has power or control.

Arch. Sherif Elwishahy, PMP

Project Scope Management


Includes the processes required to ensure that the project includes all the work required, and only the work required, to complete the project successfully. Managing the project scope is primarily concerned with defining and controlling what is and is not included in the project preventing extra work or gold plating. You should give the customer what exactly they asked for, no more and no less. Giving any extras is a waste of time and adds no benefit to the project.
Arch. Sherif Elwishahy, PMP

Project Scope Management


The term Scope can be applied to: Product scope: Features and functions that characterize a product, service or result. Project scope: Work that must be performed to deliver a product, service, or result with the Specified features and functions. Completion of project scope is measured against the project management plan, the project scope statement, and the associated WBS. Completion of the product scope is measured against the product requirements
Arch. Sherif Elwishahy, PMP

5.1 Plan Scope Management

Arch. Sherif Elwishahy, PMP

5.1 Plan Scope Management Is the process of: Plan Scope Management is the process of creating a scope management plan that documents how the project scope will be defined, validated, and controlled.

Arch. Sherif Elwishahy, PMP

5.1 Plan Scope Management

Arch. Sherif Elwishahy, PMP

5.1.1 Plan Scope Management: Inputs


1. Project Management Plan

2. Project Charter It provides the high-level project description, and characteristics from the project statement of work.

Arch. Sherif Elwishahy, PMP

5.1.1 Plan Scope Management: Inputs


3.Enterprise Environmental Factors include, but are not limited to: Organizations culture, Infrastructure, Personnel administration, and Marketplace conditions. 4.Organizational Process Assets include, but are not limited to: Policies and procedures, and Historical information.

Arch. Sherif Elwishahy, PMP

5.1.2 Plan Scope Management: Tools & Techniques


1.Expert Judgment Refers to input received from knowledgeable and experienced parties. Expertise may be provided by any group or person with specialized education, knowledge, skill, experience, or training in developing scope management plans. 2.Meetings Project teams may attend project meetings to develop the scope management plan.

Arch. Sherif Elwishahy, PMP

5.1.3 Plan Scope Management: Outputs


1. Scope Management Plan
Describes how the scope will be defined, developed, monitored, controlled, and verified. The components of a scope management plan include: Process for preparing a project scope statement. Process that enables the creation of the WBS. Process that establishes how the WBS will be maintained and approved. Process that specifies how formal acceptance of the completed project deliverables will be obtained. Process to control how requests for changes to the detailed project scope statement will be processed.
Arch. Sherif Elwishahy, PMP

5.1.3 Plan Scope Management: Outputs


2. Requirements Management Plan
Describes how requirements will be analyzed, documented, and managed. Components of the requirements management include: How requirements activities will be planned, and reported. How changes to the product will be initiated. How impacts will be analyzed, traced, and reported. Requirements prioritization process. Product metrics that will be used and the rationale. Traceability structure to reflect which requirement attributes will be captured on the traceability matrix.
Arch. Sherif Elwishahy, PMP

5.2 Collect Requirements

Arch. Sherif Elwishahy, PMP

5.2 Collect Requirements


Is the process of:

Defining and documenting, and managing stakeholders needs, and requirements to meet the project objectives. Requirements include: Quantified and documented needs. Expectations of the sponsor. Expectations of the customer. Expectations of other stakeholders. Product Requirements: The Features and functions that characterize a product, service or result. Project Requirements: The work that needs be accomplished to deliver a product, service or result.

Arch. Sherif Elwishahy, PMP

5.2 Collect Requirements

Arch. Sherif Elwishahy, PMP

1. Scope Management Plan 2. Requirements Management Plan 3.Stakeholder Management Plan


Is used to understand stakeholder the level of stakeholder engagement in order to assess and adapt to the level of participation in requirements activities.

4. Project Charter
Is used to provide the high-level description of the product, service, or result of the project.

5.Stakeholder Register
Is used to identify stakeholders who can provide information on the requirements. Arch. Sherif Elwishahy, PMP

1. Interviews: Is a formal or informal approach to discover information from stakeholders by talking to them directly. Interviewing experienced project participants, stakeholders, and subject matter experts can aid in identifying and defining the features and functions of the desired project deliverables.

Arch. Sherif Elwishahy, PMP

2. Focus Groups: Bring together prequalified stakeholders and subject matter experts to learn about their expectations and attitudes about the proposed product, service or result.

Arch. Sherif Elwishahy, PMP

3. Facilitated Workshops: Are focused sessions that bring key cross-functional stakeholders together to define product requirements. For example: In S/W development Industry, (JAD) Joint Application Development or Design. In Manufacturing Industry, (QFD) Quality Function Development. Sometimes Known as (VOC) Voice Of the Customer.

Arch. Sherif Elwishahy, PMP

4. group Creativity Techniques Brainstorming. Nominal group technique. Idea/mind mapping. Affinity diagram. Multi-criteria decision analysis.

Arch. Sherif Elwishahy, PMP

5. Group Decision Making Techniques: Is an assessment process of multiple alternatives with an expected outcome in the form of future actions resolution. For example: Unanimity. Majority. Plurality. Dictatorship.

Arch. Sherif Elwishahy, PMP

6. Questionnaires and Surveys: Written sets of questions designed to quickly accumulate information from wide number of respondents. Requires Statistical analysis.

Arch. Sherif Elwishahy, PMP

7. Observation: Provide a direct way of viewing individuals in their environment and how they perform their jobs or tasks and carry out processes. Sometimes called Job Shadowing. Used to uncover hidden requirements.

8. Prototypes: Obtaining early feedback on requirements by providing a work model of the expected product before actually building it.
Arch. Sherif Elwishahy, PMP

9.Benchmarking Involves comparing actual or planned practices, to those of comparable organizations to provide a basis for measuring performance. The organizations compared during benchmarking can be internal or external.

Arch. Sherif Elwishahy, PMP

10. Context Diagrams Is an example of a scope model which visually depict the product scope. It shows inputs to the business system, the actor(s) providing the input, the outputs from the business system, and the actor(s) receiving the output.

Arch. Sherif Elwishahy, PMP

11. Document Analysis Is used to find requirements by analyzing existing documentation and identifying information relevant to the requirements. Examples of documents that may be analyzed: Business plans, Requests for proposal, Current process flows Requirements documentation, Problem/issue logs, Policies, procedures, and regulatory documentation such as laws.
Arch. Sherif Elwishahy, PMP

1. Requirements Documentation: Describes how individual requirements meet the business need for the project. Components may include: Business need or opportunity to be seized. Functional requirements. Quality requirements. Requirements assumptions and constraints Acceptance criteria. Support and training required.

Arch. Sherif Elwishahy, PMP

2. Requirements Traceability Matrix: Is a table that links requirements to their origin and traces them throughout the project life cycle. Processes may include: Requirements to business needs. Requirements to project objectives. Requirements to project scope. Requirements to product design.

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

5.3 Define Scope

Arch. Sherif Elwishahy, PMP

5.3 Define Scope


Is the process of: Developing a detailed description of the project and product. We need to define the following: What the project consists of? What is involved to create the project? What it is expected to do when complete. It emphasis is on creating a written Scope Statement to be used in future project decision making.

Arch. Sherif Elwishahy, PMP

5.3 Define Scope

Arch. Sherif Elwishahy, PMP

5.3.1 Define Scope : Inputs 1. Scope Management Plan 2.Project Charter 3 . Requirements Documentation 4 . Organizational Process Assets

Arch. Sherif Elwishahy, PMP

5.3.2 Define Scope : Tools & Techniques


1. Expert Judgment:

2. Product Analysis: Involves translating the project goals into realistic deliverables. Techniques to develop a better understanding of the product.

Arch. Sherif Elwishahy, PMP

5.3.2 Define Scope : Tools & Techniques


3. Alternative Generation: Involves looking at different techniques to achieve the goals of the project. This can include brainstorming, pair wise comparisons, and lateral thinking. 4. Facilitated Workshops.

Arch. Sherif Elwishahy, PMP

5.3.3 Define Scope : Outputs


1. Project Scope Statement Detailed description of the project deliverables, and the work required to create those deliverables. May include: Project Deliverables. Project assumptions. Project Constraints. Project Exclusions. Product acceptance criteria. Product Scope Description. 2.Project Document Updates.
Arch. Sherif Elwishahy, PMP

5.4 Create WBS

Arch. Sherif Elwishahy, PMP

5.4 Create WBS


Is the process of: Subdividing project deliverables and project work into smaller, more manageable components. The pieces are ultimately rolled into the Work Breakdown Structure (WBS). The lowest level of the WBS is the work package.

Arch. Sherif Elwishahy, PMP

Work Package
Is a deliverable or project work component at the lowest level of each branch of the work breakdown structure . Level at which the cost and schedule for the work can be reliably estimated, monitored, and controlled. Approximated time expected for work package is 80 hours.

Arch. Sherif Elwishahy, PMP

5.4 Create WBS

Arch. Sherif Elwishahy, PMP

5.4 Create WBS

Arch. Sherif Elwishahy, PMP

Benefits of using WBS


Provides a structure for planning the project Provides a basis for assigning work to groups and individuals Provides a basis for preparing estimates, calculating costs, and measuring the progress of work Clarifies roles and responsibilities of personnel Defines the project scope and thus provides a mechanism for assessing the impact of proposed changes Provides data for projecting costs and activities needed on future, similar projects
Arch. Sherif Elwishahy, PMP

5.4 Create WBS


1.0 Concept 1.1 Evaluate current systems 1.2 Define Requirements 1.2.1 Define user requirements 1.2.2 Define content requirements 1.2.3 Define system requirements requirements 1.2.4 Define server owner

1.3 Define specific functionality


1.4 Define risks and risk management approach 1.5 Develop project plan 1.6 Brief web development team

2.0 Web Site Design


3.0 Web Site Development 4.0 Roll Out 5.0 Support
Arch. Sherif Elwishahy, PMP

5.4 Create WBS

Arch. Sherif Elwishahy, PMP

5.4.1 Create WBS: Inputs


1. Scope Management Plan

2 . Project scope statement


3 . Requirements documentation 4.Enterprise Environmental Factors 5 . Organizational process assets
Arch. Sherif Elwishahy, PMP

5.4.2 Create WBS: Tools & Techniques


1. Decomposition: Subdividing of project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level. Generally involves five steps: 1.Identify the deliverables and related work. 2.Structure and organize the WBS. 3.Decompose the upper WBS levels into lower detailed components. 4.Develop and assign identification codes to the WBS. 5.Verify that the degree of decomposition is necessary and sufficient.

2. Expert Judgment
Arch. Sherif Elwishahy, PMP

5.4.3 Create WBS: Outputs


1. Scope Baseline: - Project scope statement - WBS - WBS Dictionary A document that describes each component in the WBS For each WBS component, the WBS dictionary includes a: Code of account identifier

Statement of work
Responsible organization

List of schedule milestones


2. Project Document Updates
Arch. Sherif Elwishahy, PMP

5.5 Validate Scope

Arch. Sherif Elwishahy, PMP

5.5 Validate Scope


Is the process of: Formalizing acceptance of the completed project deliverables. Reviewing deliverables with the customer or sponsor. The main goal of Scope Verification is to secure signoff of the project scope and obtain Formal Acceptance. If the project is terminated early, the scope verification process should establish and document the level and extent of completion.
Arch. Sherif Elwishahy, PMP

5.5 Validate Scope

Arch. Sherif Elwishahy, PMP

5.5.1 Validate Scope: Inputs


1. Project Management Plan

2. Requirements Documentation
3.Requirements Traceability Matrix

4. Verified Deliverables
Validated deliverables have been completed and checked for correctness by the Perform Quality Control process. 5. Work Performance Data

Arch. Sherif Elwishahy, PMP

5.5.2 Validate Scope : Tools & Techniques


1. Inspection:

Is used to validate that the correct work has been done.


Includes activities, such as measuring, examining, and testing, undertaken to determine whether results conform to requirements. Purpose is to specifically identify deficiencies, gaps and errors against the project documentation.

2. Group Decision Making Techniques

5.5.3 Validate Scope : Outputs


1. Accepted Deliverables

Deliverables that meet the acceptance criteria are formally signed off and approved by the customer or sponsor.

2 .Change Requests

3. Work Performance Information


4. Project Document Updates
Arch. Sherif Elwishahy, PMP

5.6 Control Scope

Arch. Sherif Elwishahy, PMP

5.6 Control Scope


Is the process of: Monitoring the status of the project and product scope. Managing changes to the Scope Baseline. Assure that all requested changes and recommended corrective actions are processed through the Integrated Change Control process. Manage the actual changes when they occur. Uncontrolled changes are referred to as project Scope Creep. Change Control Board (CCB) is responsible for approving or rejecting change request.
Arch. Sherif Elwishahy, PMP

5.6 Control Scope

Arch. Sherif Elwishahy, PMP

5.6.1 Control Scope: Inputs


1.Project Management Plan. 2. Requirements Documentation 3. Requirements Traceability Matrix

4. Work Performance Data: Information about progress such as which deliverables have started, their progress and which deliverables have finished.
5. Organizational Process Assets

Arch. Sherif Elwishahy, PMP

5.6.2 Control Scope: Tools & Techniques


1. Variance Analysis: Determining the cause of variance relative to the scope baseline and deciding whether corrective action is required. Method for resolving the total variance in the set of scope, cost, and schedule variables.

Arch. Sherif Elwishahy, PMP

5.6.3 Control Scope: Outputs


1. Work Performance Information Measurements can include planned vs. actual technical performance or other scope performance measurements. This information is documented and communicated to stakeholders. 2. Change Requests Change requests can include preventive or corrective actions or defect repairs.

Arch. Sherif Elwishahy, PMP

5.6.3 Control Scope: Outputs


3. Project Management Plan Updates Scope Baseline Updates. Other Baseline Updates. 4. Project Document Updates

5. Organizational Process Assets Updates Causes of variances, Corrective action chosen and the reasons.

Arch. Sherif Elwishahy, PMP

Question No : 1
You are probably going to be the project manager for the HGD Project and will need as many inputs to the initiation phase as possible. Of the following, which is the best source of information for your project? A. Business plans B. Historical information C. WBS D. The project charter

Question No : 2
You are the project manager for the NBG Project. This project must be completed within six months. This is an example of which of the following? A. Schedule B. Assumption C. Constraint D. Planning process

Question No : 3
Of the following, which does the scope statement not provide? A. Project justification B. Project product C. Project manager authority D. Project objective

Question No : 4
You are a project manager for a large manufacturer. Your current project is to create a new manufacturing assembly line that will allow your organization to create its products with less downtime and faster turnaround time for its clients. Which of the following is an example of value-added change in this project? A. Adding more team members to the project to get the project work done faster. B. Outsourcing portions of the project execution to transfer risk. C. Adding a recently created computer program to control and monitor the manufacturing assembly. D. Documenting the project and how the manufacturing assembly should work.

Question No : 5
You are the project manager of the WIFI Project. You would like to meet with a stakeholder for scope verification. Which of the following is typical of scope verification? A. Reviewing changes to the project scope with the stakeholders B. Reviewing the performance of the project deliverables C. Reviewing the performance of the project team to date D. Reviewing the EVM results of the project to date

Project Time Management

6. Time Management
Project Time Management includes the processes required to manage timely completion of the project.

The Project time management processes and their associated tools and techniques are documented in the schedule management plan.

Arch. Sherif Elwishahy, PMP

6. Time Management
Planning
6.1 Plan Schedule Management 6.2 Define Activities 6.3 Sequence Activities 6.4 Estimate Activity Resources Controlling

6.5 Estimate Activity Duration

6.6 Develop Schedule

6.7 Control Schedule

Arch. Sherif Elwishahy, PMP

6.1 Plan Schedule Management


Arch. Sherif Elwishahy, PMP

6.1 Plan Schedule Management


Is the process of Establishing the policies, procedures, and documentation for planning, developing, managing, executing, and controlling the project schedule. The key benefit of this process is that it provides guidance and direction on how the project schedule will be managed throughout the project.

Arch. Sherif Elwishahy, PMP

6.1 Plan Schedule Management

Arch. Sherif Elwishahy, PMP

5.1.1 Plan Scope Management: Inputs


1. Project Management Plan 2. Project Charter 3.Enterprise Environmental Factors

4.Organizational Process Assets

Arch. Sherif Elwishahy, PMP

6.1.2 Plan Schedule Management: Tools & Techniques


1. Expert Judgment

2. Analytical Techniques The process may involve choosing strategic options to estimate and schedule the project such as: Scheduling methodology, Scheduling tools and techniques, Estimating approaches, Formats, and project management software.

Arch. Sherif Elwishahy, PMP

6.1.2 Plan Schedule Management: Tools & Techniques


3. Meetings Project teams may hold planning meetings to develop the schedule management plan.

Arch. Sherif Elwishahy, PMP

5.1.3 Plan Scope Management: Outputs


1. Schedule Management Plan A component of the project management plan. Level of accuracy Units of measure Project schedule model maintenance Control thresholds Reporting formats Process descriptions

Arch. Sherif Elwishahy, PMP

6.2 Define Activities

Arch. Sherif Elwishahy, PMP

6.2 Define Activities


Is the process of Identifying the specific actions to be performed to produce the project deliverables and objectives. Identifying and documenting the work that is planned to be performed. The Activity Definition process will identify the deliverables at the lowest level (Work Package). Work packages are decomposed into smaller components called Schedule Activities

Arch. Sherif Elwishahy, PMP

6.1 Define Activities

Arch. Sherif Elwishahy, PMP

6.2.1 Define Activities: Inputs


1. Schedule Management Plan 2. Scope Baseline

3. Enterprise Environmental Factors


4. Organization Process Assets

Arch. Sherif Elwishahy, PMP

6.2.2 Define Activities: Tools & Techniques


1. Decomposition: Subdividing the project work packages into smaller, more manageable components called schedule activities. The activity list, WBS, and WBS dictionary can be developed either sequentially or concurrently, Is often performed by the project team members responsible for the work package.

Arch. Sherif Elwishahy, PMP

6.2.2 Define Activities: Tools & Techniques


2. Rolling Wave Planning: Is a form of progressive elaboration planning. The work to be accomplished in the near term is planned in detail at a low level of the WBS. Work far in the future is planned for WBS components that are at a relatively high level. Schedule activities can exist at various levels of detail in the projects life cycle. 3. Expert Judgment: Project team members or other experts can provide expertise in defining activities.
Arch. Sherif Elwishahy, PMP

6.2.3 Define Activities: Outputs


1. Activity List The activity list is a comprehensive list including all schedule activities required on the project. Includes the activity identifier Scope of work description for each activity in sufficient detail to ensure that project team members understand what work is required to be completed.

Arch. Sherif Elwishahy, PMP

6.2.3 Define Activities: Outputs


2. Activity Attributes: Extend the description by identifying multiple components associated with each activity. May include most of the following: WBS ID. Activity Name. Activity Code. Activity Description. Predecessor, and Successor Activities. Logical Relationship. Constraints.

Arch. Sherif Elwishahy, PMP

6.2.3 Define Activities: Outputs


3. Milestone List A milestone is a significant point or event in the project. A milestone list identifies all milestones Indicates whether the milestone is mandatory, such as those required by contract, or optional, such as those based upon historical information.

Arch. Sherif Elwishahy, PMP

6.3 Sequence Activities

Arch. Sherif Elwishahy, PMP

6.3 Sequence Activities


Is the process of: Identifying and documenting relationships among the project activities. Logically sequenced with proper precedence relationships. Involves leads and lags to support later development of a realistic and achievable project schedule. Sequencing can be performed by using project management software or by using manual techniques.

Arch. Sherif Elwishahy, PMP

6.3 Sequence Activities

Arch. Sherif Elwishahy, PMP

6.3.1 Sequence Activities: Inputs 1. 2. 3. 4. 5. 6. 7. Schedule Management Plan Activity List. Activity Attributes. Milestone List. Project Scope Statement. Enterprise Environmental Factors Organization Process Assets.

Arch. Sherif Elwishahy, PMP

6.3.2 Sequence Activities: Tools & Techniques


1. Precedence Diagramming method (PDM)

Arch. Sherif Elwishahy, PMP

6.3.2 Sequence Activities: Tools & Techniques


PDM includes four types of dependencies or logical relationships:

Arch. Sherif Elwishahy, PMP

6.3.2 Sequence Activities: Tools & Techniques 2. Dependency Determination: Mandatory dependencies: Inherent in the nature of the work; (Hard logic). Discretionary dependencies: Defined by the project team (Soft logic). External dependencies: Involve relationships between project and non-project activities. Internal dependencies. A precedence relationship between project activities and are generally inside the project teams control.

Arch. Sherif Elwishahy, PMP

6.3.2 Sequence Activities: Tools & Techniques


3.Applying Leads and Lags: Lead: Is an accelerant of an activity. Lag: Is a delay between activities.

Arch. Sherif Elwishahy, PMP

6.3.3 Sequence Activities: Outputs


1. Project Schedule network Diagrams
B A C Start FS +15 F SS +10 K G End SS D E

J
FF

2. Project Document Updates.


Arch. Sherif Elwishahy, PMP

6.4 Estimate Activity Resources


Arch. Sherif Elwishahy, PMP

6.4 Estimate Activity Resources


Is the process of: Estimating the type and quantities of material, people, equipment, or support required to perform each activity.

Arch. Sherif Elwishahy, PMP

6.4 Estimate Activity Resources

Arch. Sherif Elwishahy, PMP

6.4.1 Estimate Activity Resources: Inputs


1. Schedule Management Plan 2. Activity List. 3. Activity Attributes. 4. Resource Calendars. 5. Risk Register 6. Enterprise Environmental Factors 7. Organization Process Asset

Arch. Sherif Elwishahy, PMP

6.4.2 Estimate Activity Resources: Tools & Techniques


1. Expert Judgment 2. Alternative Analysis: They include using various levels of resource capability or skills. Different size or type of machines. Different tools (hand versus automated). Make-or-buy decisions.

Arch. Sherif Elwishahy, PMP

6.4.2 Estimate Activity Resources: Tools & Techniques


3.Published Estimating Data: Several companies routinely publish updated production rates and unit costs. Very common practice in Construction field (Materials & Labor).

4. Bottom-Up Estimating: When a schedule activity cannot be estimated with a reasonable degree of confidence, the work within the schedule activity is decomposed into more detail. The team and project manager create an estimate from the activity level and roll the estimates up to create a total project estimate. 5. Project Management Software:
Arch. Sherif Elwishahy, PMP

6.4.3 Estimate Activity Resources: Outputs


1. Activity Resource Requirements The process identifies the types and quantities of resources required for each activity in a work package. The amount of detail and the level of specificity can vary by application area. Can include the basis of estimate, and the assumptions that were made in determining resources.
2.Resource Breakdown Structure

3. Project Document Updates


Arch. Sherif Elwishahy, PMP

6.5 Estimate Activity Duration


Arch. Sherif Elwishahy, PMP

6.5 Estimate Activity Duration


Is the process of: Approximating the number of work periods needed to complete individual activities with estimated resources. The key is to estimate the number of work days (or hours) to complete each activity. Estimation then rolls up to create summary (high level) estimates.

Arch. Sherif Elwishahy, PMP

6.5 Estimate Activity Duration

Arch. Sherif Elwishahy, PMP

6.5.1 Estimate Activity Duration: Inputs


1. Schedule Management Plan. 2. Activity List. 3. Activity Attributes. 4. Activity Resource Requirements. 5. Resource Calendars. 6. Project Scope Statement 7. Risk Register 8.Resource Breakdown Structure 9. Enterprise Environmental Factors 10. Organization Process Asset
Arch. Sherif Elwishahy, PMP

6.5.2 Estimate Activity Duration: Tools & Techniques


1. Expert Judgment: 2. Analogous Estimating Uses parameters such as duration, budget, size, weight, and complexity, from a previous, similar project, as the basis for estimating for a future project. Used when there is limited amount of detailed information Analogous estimating uses historical information and expert judgment. Is generally less costly and time consuming than other techniques.
Arch. Sherif Elwishahy, PMP

6.5.2 Estimate Activity Duration: Tools & Techniques


3. Parametric Estimating Parametric estimating uses a statistical relationship between historical data and other variables. to calculate an estimate for activity parameters, such as cost, budget, and duration. (square footage in construction)

Arch. Sherif Elwishahy, PMP

6.5.2 Estimate Activity Duration: Tools & Techniques


4. Three-point Estimates (Program Evaluation and Review Technique) PERT Uses three estimates to define an approximate range for an activitys duration. Most likely: the duration of the activity, given the resources likely to be assigned, their productivity. Optimistic: the activity duration is based on analysis of the bestcase scenario for the activity. Pessimistic: the activity duration is based on analysis of the worst-case scenario for the activity. T = O +4M+P 6 Standard Deviation () = P O Variance (V) = 2 6 Arch. Sherif Elwishahy, PMP

Example

Activity

Optimistic

Most likely

Pessimistic

Expected duration (O+ 4*M +P) 6


4 5 7 5

Standard Deviation (P O) 6

Variance V = 2

A B C D

2 3 4 4

4 5 7 5

6 7 10 6

0.67 0.67 1 0.33

0.44 0.44 1 0.11

Arch. Sherif Elwishahy, PMP

6.5.2 Estimate Activity Duration: Tools & Techniques


5. Group decision-making Techniques. 6. Reserve Analysis: Is used when a team wants to plan for known unknowns. Sometimes called Contingency reserves. The analysis adds extra time to the estimates from a work units or percentage estimates.

Arch. Sherif Elwishahy, PMP

6.5.2 Estimate Activity Duration: Outputs


1. Activity Duration Estimates Activity duration estimates are quantitative assessments of the likely number of work periods that will be required to complete an activity. Duration estimates do not include any lags as described in 6.2.2.3. Activity duration estimates may include some indication of the range of possible results. For example: 2 weeks 2 days to indicate that the activity will take at least eight days and no more than twelve (assuming a five-day workweek). 15% probability of exceeding three weeks to indicate a high probability 85% percentthat the activity will take three weeks or less. 2. Project Document Updates.

Arch. Sherif Elwishahy, PMP

6.6 Develop Schedule

Arch. Sherif Elwishahy, PMP

6.6 Develop Schedule


Is the process of: Analyzing activity sequences, Durations, resource requirements, and schedule constraints to create the project schedule. At this point, the following come together and the schedule is born: WHAT; activity list and WBS. WHEN; start and finish dates. WHO; resources. WHAT ORDER; activity sequencing.

Arch. Sherif Elwishahy, PMP

6.6 Develop Schedule

Arch. Sherif Elwishahy, PMP

6.6.1 Develop Schedule: Inputs


1. Schedule Management Plan. 2. Activity List. 3. Activity Attributes. 4. Project Schedule network Diagrams 5. Activity Resource Requirements. 6. Resource Calendars. 7. Activity Duration Estimates 8. Project Scope Statement 9. Risk Register 10. Project staff assignments 11. Resource Breakdown Structure 12. Enterprise Environmental Factors 13. Organization Process Asset

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


1. Schedule Network Analysis It is a technique that generates the schedule. It employs several techniques such as: Critical path analysis. Critical chain analysis. What If analysis. Resource leveling.

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


2. Critical Path Method (CPM): It calculates the early start and finish dates. It calculates the late start and finish dates. It doesn't take account of any resource limitations. Generates the CPM by performing a forward and backward pass analysis through the schedule network.

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


A network diagrams is a schematic display of projects activities and dependencies.
2 Days

12 Days B

5 Days

Start

Finish
6 Days 7 Days

3 Days F

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


The Forward Pass
Early Start Box
0

2 Days
2

Early Finish Box

0 Start Start

A A 6 Days
0 D D 6

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Early Start = Highest of predecessors Early Finish Times

2 A 2 Days

14

14

19

0 Start

B 12 Days

C 5 Days

19 Finish

19

13

13

16

D 6 Days

E 7 Days

F 3 Days

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


The Backward Pass
5 Days 14 C C 14 3 Days 19 19 19 Finish Finish 19 19

19

13
F F 16

16
19

Late Start Box

Late Finish Box


Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Late Finish = Lowest of successors Late Start Times 12 Days 2 A A 0 2

2 Days 0

5 Days

2
B B 2

14
14 C C 14 19 19 19

Start Start
0 0

Finish Finish
6 Days 0 D D 3 9 9 6 6 E 7 Days 13 3 Days 19 19

E
16 16

F F 19

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Late Finish = Lowest of successors Late Start Times 12 Days 2 2 2

2 Days 0 0 0

5 Days

A A

2 2
2

B B

14 14
14

14 14

C C

19 19 19 19 19 19 19

Start Start
0 0

Finish Finish
6 Days 0 0 D D 3 9 9 6 6 7 Days 6 6 E 13 13 3 Days 13 F F 16 16 19 16 19

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


2.Critical Path Method (CPM): If one or more activities on the critical path takes longer than planned, the whole project schedule will slip unless corrective action is taken Misconceptions: The critical path is not the one with all the critical activities; it only accounts for time. There can be more than one critical path. The critical path can change as the project progresses.

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Late Finish = Lowest of successors Late Start Times 12 Days 2 2 2

2 Days 0 0 0

5 Days

A A

2 2
2

B B

14 14
14

14 14

C C

19 19 19 19 19 19 19

Start Start
0 0

Finish Finish
6 Days 0 0 D D 3 9 9 6 6 7 Days 6 6 E 13 13 3 Days 13 F F 16 16 19 16 19

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Late Finish = Lowest of successors Late Start Times 12 Days 2 2 2

2 Days 0 0 0

5 Days

A A

2 2
2

B B

14 14
14

14 14

C C

19 19 19 19 19 19 19

Start Start
0 0

Finish Finish
6 Days 0 0 D D 3 9 9 6 6 7 Days 6 6 E 13 13 3 Days 13 F F 16 16 19 16 19

Path A Path B Path C

19 Days 11 Days 16 Days

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Free float ( slack ) The amount of time an activity can delay without delaying the early start of its successor . Total float ( slack ) The amount of time an activity can delay without delaying the project completion date .

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Late Finish = Lowest of successors Late Start Times 12 Days 2 2 2

2 Days 0 0 0

5 Days

A A

2 2
2

B B

14 14
14

14 14

C C

19 19 19 19 19 19 19

Start Start
0 0

Finish Finish
6 Days 0 0 D D 3 9 9 6 6 7 Days 6 6 E 13 13 3 Days 13 F F 16 16 19 16 19

Free float ( slack )= 3 Days


Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


3. Critical Chain Method Accounts for limited resources. There is a focus on starting activities as late as possible. Project Buffer:
placed after last task in project to protect schedule .

Feeding Buffers:
placed between a noncritical task and a critical task when the noncritical task is an immediate predecessor of the critical task.

Resource Buffers:
placed just before a critical task that uses a new resource type .

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


3. Critical Chain Method

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


4. Resource Optimization Techniques: Leveling is the process of adjusting resource peeks and valleys to create a level usage of the resources. Typically, leveling sacrifice the overall finish date, and it is not uncommon to see the schedule stretch out a little.

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


5. Modeling Techniques: It is an analysis of the question What happens if the situation represented by scenario X happens? Delaying a major component delivery. Extending specific engineering duration. Introducing an external factor. Simulation calculating multiple project durations with different sets of activity assumptions. The most common simulation technique is Monte Carlo analysis. Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


6. Applying Leads and Lags: Are done to fine tune the schedule. Adds delays (Lags) or accelerators (Lead) that sometimes come between activities.

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques 7. Schedule Compression: After the initial schedule has been put together. To achieve a more aggressive time goal. To compensate for a delay in an activity on the critical path. If the initial schedule does not meet the required end Due date of the project. Can be achieved mainly by two techniques: Crashing. Fast Tracking.
Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques


Crashing: Involves putting more people on the critical path activity. Excludes re-sequencing activities. Requires extra cost affects budget. Fast Tracking: Refers to making activities parallel. Use the network diagram to re-plan the sequence of activities to make more activities parallel. Includes Risk exposure associated with resequencing, and parallel activities.
Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques

Arch. Sherif Elwishahy, PMP

6.6.2 Develop Schedule: Tools & Techniques 8.Scheduling Tool: Automated scheduling tools expedite the scheduling process by generating start and finish dates based on the input of: Activities. Network diagrams. Resources. Activity durations. Can be used in conjunction with other project management software. Very sensitive to input data.
Arch. Sherif Elwishahy, PMP

6.6.3 Develop Schedule: Outputs 1. Project schedule

Arch. Sherif Elwishahy, PMP

6.6.3 Develop Schedule: Outputs

Arch. Sherif Elwishahy, PMP

6.6.3 Develop Schedule: Outputs


2. Schedule baseline Is the accepted and approved version of the project schedule. 3. Schedule data Includes the schedule milestones, schedule activities, activity attributes, and documentation of all identified assumptions and constraints.

4. Project Calendars 5. Project Management Plan Update 6. Project document updates.


Arch. Sherif Elwishahy, PMP

6.7 Control Schedule

Arch. Sherif Elwishahy, PMP

6.7 Control Schedule


Is the process of: Monitoring the status of the project. Updating project progress. Managing changes to the schedule baseline. Schedule control is concerned with: Determining the current status of the project schedule. Influencing the factors that create schedule changes. Determine that the project schedule has changed. Managing the actual changes as they occur.

Arch. Sherif Elwishahy, PMP

6.7 Control Schedule

Arch. Sherif Elwishahy, PMP

1. Project Management Plan. 2. Project schedule 3. Work Performance Data. 4. Project Calendars. 5. Schedule Data. 6. Organization Process Asset.

Arch. Sherif Elwishahy, PMP

1. Performance reviews Performance reviews measure, compare, and analyze schedule performance such as actual start and finish dates, percent complete, and remaining duration for work in progress. Trend analysis Critical path method Critical chain method Earned value management

Arch. Sherif Elwishahy, PMP

2. Project management software 3. Resource Optimization Techniques 5. Modeling Techniques 6. Leads and lags 7. Schedule compression 8. Scheduling tool

Arch. Sherif Elwishahy, PMP

1. Work Performance Information. 2. Schedule Forecasts.

3. Change Requests.
4. Project Management Plan Updates.

5. Project Documents Updates.


6. Organization Process Asset Updates.

Arch. Sherif Elwishahy, PMP

Question No 1
You are the project manager of the JHG Project. This project has 32 stakeholders and will require implementation activities in North and South America. You have been requested to provide a duration estimate for the project. Of the following, which will offer the best level of detail in your estimate? A. WBS B. Order of magnitude C. Requirements document D. Stakeholder analysis

Question No 2
You are the project manager for the LLL Project. Steven, a project team member, is confused about network diagrams. Specifically, he wants to know what the critical path is in a network diagram. Your answer is which one of the following? A. The critical path is the network that hosts the activities most critical to the project success. B. The critical path is the path with the longest duration. C. The critical path is always one path that cannot be delayed or the entire project will be delayed. D. The critical path is the path from start to completion with no deviation from the project plan.

Question No 3
You are the project manager for the POL Project. This project will use PERT to calculate the estimates for activity duration. For activity D, you have the following information: P=9, O=4, M=5. What is the result of PERT? A. 18 weeks B. 5.5 weeks C. 33.33 days D. 3 weeks

Question No 4
You are the project manager for a project with the following network diagram. Studying the diagram, which path is the critical path? A. ABCD B. EBCD C. EFH D. EGH

Question No 5
Bertha is the project manager for the HAR Project. The project is behind schedule and Bertha has elected, with managements approval, to crash the critical path. This process adds more what?

A. Cost
B. Time

C. Risk
D. Documentation

Project Cost
Management

7. Cost Management
Includes the processes involved in estimating, budgeting, and controlling costs so that the project can be completed within the approved budget. Estimate costs Determine budget Control costs

Arch. Sherif Elwishahy, PMP

Cost Management Plan


Should include most of the following: Level of Accuracy. Units to Measure.

Organizational procedures links (Control


account).

Control Thresholds: an agreed-upon amount of variation allowed before action needs to be taken. Rules of Performance Measurement. Reporting Format. Process Description.
Arch. Sherif Elwishahy, PMP

Level of accuracy
Estimate Name Process Group Tolerance Range Example (Actual Cost) Generally Accepted Estimate Tolerance

Order of Magnitude Budget

Initiation

-25% to +75%

1000 EGP

7501750 EGP

Planning (Early)

-10% : + 25%

1000 EGP

900 1250 EGP

Definitive

Planning (Late)

-5% : + 10%

1000 EGP

950 1100 EGP

Arch. Sherif Elwishahy, PMP

LIFE CYCLE COSTING


Means that the cost of operation and maintenance is to be considered and managed with the project Cost.
PROJECT OPERATIONS AND MAINTENANCE PHASE

costs

costs

Arch. Sherif Elwishahy, PMP

Sunk Cost
Are costs that have already been spent on a project. DO NOT consider these costs when making future project decisions.

Example: When terminating a project dont consider all previous payments in your decision.

Arch. Sherif Elwishahy, PMP

7. Cost Management
Planning Controlling

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

7.4 Control Costs

Arch. Sherif Elwishahy, PMP

7.1 Plan Cost Management

Arch. Sherif Elwishahy, PMP

7.1 Plan Cost Management

Arch. Sherif Elwishahy, PMP

7.1.1 Plan Cost Management: Inputs

1. Project management plan

2. Project charter
3. Enterprise environmental factors 4. Organizational process assets

Arch. Sherif Elwishahy, PMP

7.1.2 Plan Cost Management: Tools & Techniques

1. Expert judgment 2. Analytical techniques

3. Meetings

Arch. Sherif Elwishahy, PMP

7.1.3 Plan Cost Management: Outputs

1. Cost management plan A component of the project management plan. Level of accuracy Units of measure Project schedule model maintenance Control thresholds Reporting formats Process descriptions
Arch. Sherif Elwishahy, PMP

7.2 Estimate Costs

Arch. Sherif Elwishahy, PMP

7.1 Estimate Costs


Is the process of: Developing an approximation of the monetary resources needed to complete project activities. The estimator considers the possible causes of variation of the cost estimates, including risks. It is a key element because good estimates can determine project success or failure.

Arch. Sherif Elwishahy, PMP

7.2 Estimate Costs

Arch. Sherif Elwishahy, PMP

7.2.1 Estimate Costs: Inputs


1. Cost Management Plan. 2. Human Resource Plan. 3. Scope Baseline. 4. Project Schedule. 5. Risk Register. 6. Enterprise Environmental Factors. 7. Organizational Process Assets.

Arch. Sherif Elwishahy, PMP

7.2.2 Estimate Costs: Tools & Techniques


1. Expert Judgment: 2. Analogous Estimating:( ) It is a high level estimate not a detailed one. Is done by reviewing similar projects, and benchmarking with them.

Arch. Sherif Elwishahy, PMP

Example of Analogous Estimating


The Carlton Park Project was to pave a sidewalk around a pond in the community park. The sidewalk of Carlton Park was 1048 feet by 6 feet, used a textured surface, had some curves around trees, and cost $25,287 to complete or $4.021 / foot . The current project, King Park, will have a similar surface and will cover 4,500 feet by 6 feet. The analogous estimate for this project, based on the work in Carlton Park, is 108,500 $. This is based on the price per foot of material at $4.021.
Arch. Sherif Elwishahy, PMP

7.2.2 Estimate Costs: Tools & Techniques


3. Parametric Estimating:( ( Uses a mathematical model based on known parameters to predict the cost of a project. Example: Consultant Hour Rate = 200 EGPS. He is expected to work on the project for = 25 Hours. C=W*R Total Cost= 200 * 25 = 5000 EGP.

Arch. Sherif Elwishahy, PMP

7.2.2 Estimate Costs: Tools & Techniques


4. Bottom-Up Estimating: The team builds the total detailed estimate from the bottom up. 5. Three Point Estimating: Mathematical function. D = (O + ( 4 * M ) + P) 6 6. Reserve Analysis: Sometimes called Contingency reserves. May be a percentage of the estimated cost, a fixed number.
Arch. Sherif Elwishahy, PMP

7.2.2 Estimate Costs: Tools & Techniques


7. Cost Of Quality [COQ]: (8.1 Plan Quality) Assumptions about COQ is factored in to create the project cost estimate.

Arch. Sherif Elwishahy, PMP

7.2.2 Estimate Costs: Tools & Techniques


8. Project Management Estimating Software:
Has the capability to help plan, organize, and manage resource pools. Computerized Spreadsheets. Simulations. Statistical Tools. Can facilitate cost estimate alternatives.

9.Vendor Bid Analysis: (Procurement Management Module) 10. Group Decision Making Techniques.
Arch. Sherif Elwishahy, PMP

7.2.3 Estimate Costs: Outputs


1. Activity Cost Estimates 2. Basis of Estimates: The amount and type of additional details supporting the cost estimates. Should include most of the following: The basis of estimate All assumptions made. Known constraints. Range of possible estimates (10000 EGP 10%) Indication of the confidence level of the final estimate. 3. Project Document Updates.
Arch. Sherif Elwishahy, PMP

7.3 Determine Budget

Arch. Sherif Elwishahy, PMP

7.3 Determine Budget


Is the process of:

Aggregating the estimated costs of individual


activities or work packages to establish an authorized cost baseline.

The budgeting should include a timebased


approach to help determine project costs needs as time passes.

It establishes the basis for measurement,


monitoring, and controlling of the project costs.

Arch. Sherif Elwishahy, PMP

7.3 Determine Budget

Arch. Sherif Elwishahy, PMP

7.3.1 Determine Budget: Inputs


1. Cost management plan.
2. Scope Baseline. 3. Activity Cost Estimates. 4.Basis of Estimates. 5.Project Schedule.

6.Resource Calendars.
7. Risk register

8. Agreements.
9.Organizational Process Assets.
Arch. Sherif Elwishahy, PMP

7.3.2 Determine Budget: Tools & Techniques


1. Cost Aggregation: Schedule activity cost estimates are aggregated by work packages in accordance with the WBS. The work package cost estimates are then aggregated for the higher component levels of the WBS, such as control accounts, and ultimately for the entire project. Is done to roll-up the project costs starting with the activity level task.

Arch. Sherif Elwishahy, PMP

7.3.2 Determine Budget: Tools & Techniques


8. Cost Budget
7.Management Reserves $ 1423 $ 68

6. Cost Baseline
5. Contingency Reserves 4. Project Estimates 3. Control Account Estimate 2. Work Package Estimate

$ 1355
$ 105 $ 1250 CA 1 $ 850 WP 1 $ 100
A1 $ 25 A2 $ 25 A3 $ 25

Cost Aggregation

CA 2 $ 400 WP 2 $ 250 WP 3 $ 500

1. Activity Estimates

A4 $ 25 Arch. Sherif Elwishahy, PMP

7.3.2 Determine Budget: Tools & Techniques


2. Reserve Analysis:

Is used when a team wants to plan for known


unknowns.

Contingency Reserve / Management Reserve. Reserves are NOT part of the project cost baseline. Reserves MAY be included in the total budget. Reserves are NOT included in EVM.()
3. Expert Judgment.
Arch. Sherif Elwishahy, PMP

7.3.2 Determine Budget: Tools & Techniques


4. Historical Relationships:

Any historical relationships that result in


parametric estimates or analogous estimates.
Example:

residential home construction is based on


X cost / m2 of space.

Arch. Sherif Elwishahy, PMP

7.3.2 Determine Budget: Tools & Techniques


5. Funding Limit Reconciliation:

Large variations in the periodic expenditure of


funds are usually undesirable for organizational operations.

The expenditure of funds is reconciled with the


funding limits set by the customer or performing organization.

Arch. Sherif Elwishahy, PMP

7.3.3 Determine Budget: Outputs


1.
Cost Baseline: An authorized time-phased budget at completion (BAC) used to measure, and control overall cost performance of the project.

Arch. Sherif Elwishahy, PMP

7.3.3 Determine Budget: Outputs


2. Project Funding Requirements:

3. Project Document Updates.


Arch. Sherif Elwishahy, PMP

7.4 Control Costs

Arch. Sherif Elwishahy, PMP

7.4 Control Costs


Is the process of:

Monitoring the status of the project. Updating the project budget. Managing changes to the baseline.
Can Involve:

Managing cost Levels compared to the Baseline. Analyzing and managing cost variance. Documenting cost records. Communicating with stakeholders about cost issues.

Arch. Sherif Elwishahy, PMP

7.4 Control Costs

Arch. Sherif Elwishahy, PMP

7.4.1 Control Costs: Inputs


1.Project Management Plan. 2.Project Funding Requirements. 3.Work Performance Data.

4.Organizational Process Assets.

Arch. Sherif Elwishahy, PMP

1.Earned Value Management:

Is a method of measuring project performance by comparing the amount of work planned with that actually accomplished, in order to determine if cost and schedule performance are as planned.

Arch. Sherif Elwishahy, PMP

BAC

The total amount originally expected to be spent on the project. The authorized budget assigned to the work to be accomplished )% * PV( The value of work performed

Budget At Completion Planned Value

Key Dimension

PV EV

Earned Value

AC CPI
Performance Index SPI CV

The total cost actually incurred EV/AC

Actual Cost Cost Performance Index


Schedule Performance Index Cost Variance Schedule Variance

EV/PV EV AC. EV PV

Variance

SV

VAC

BAC - EAC

Variance At Completion
Arch. Sherif Elwishahy, PMP

Earned Value Management

Arch. Sherif Elwishahy, PMP

2. Forecasting

If the BAC is no longer viable, the project manager


should develop a Forecasted EAC.

Forecasts are generated based on work performance


information provided as the project is executed.

The work performance information covers the


projects past performance and any information that could impact the project in the future.

Arch. Sherif Elwishahy, PMP

It is used when the original estimate was fundamentally flawed. It is used when no variances from the BAC have occurred or will continue at the same rate of spending.

AC + Bottom up ETC

BAC Cumulative CPI

EAC Estimate At Completion

It calculates actual to date plus the remaining value of work to perform is used if variances are atypical.

AC + (BAC EV )

It calculates actual to date plus the remaining budget modified by performance. ETC The amount needed to finish the work based on the current spending

(BAC EV)
AC + CPI + SPI

EACAC
Arch. Sherif Elwishahy, PMP

3. To-Complete Performance Index (TCPI)

Is the calculated projection of cost performance that must be achieved on the remaining work to meet a specified management goal, such as the BAC or the EAC. budget what rate must we meet for the remaining work?
(BAC EV) (BAC AC) If BAC is still valid

It answers the question of In order to stay within

TCPI (BAC EV) (EAC AC) If BAC is flawed

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

4. Performance Reviews: (11.5 Plan Risk Responses) Compare cost performance over time, schedule activities or work packages overrunning and under running the budget.

If EVM is being used, the following information is determined:


Variance Analysis.

Trend Analysis.
Earned Value Performance.
Arch. Sherif Elwishahy, PMP

5. Project Management Software: Often used to monitor the three EVM dimensions (PV, EV, and AC). Used to: Display graphical trends. Forecast a range of possible final project results. 6. Reserve Analysis: Cost performance measurements (CV, CPI) are used to assess the magnitude of variation to the original cost baseline.

Arch. Sherif Elwishahy, PMP

1.Work Performance Information. 2.Cost Forecasts. 3.Change Requests. 4.Project Management Plan (UPDATE). 5.Project Document (UPDATE).

6.Organizational Process Assets (UPDATE).


Arch. Sherif Elwishahy, PMP

Case Study
You are a project Manager responsible for delivering a new manufacturing facility. Consider the following table which represents a project list of activities. Prepare a detailed Status Report of this project on day. Is this project OK ???

Arch. Sherif Elwishahy, PMP

Case Study
Activity PV $ 300 DAY 1 DAY 2 DAY 3 DAY 4 $ 150 $ 100 AC $ 300 $ 200 $ 150 % Complete 100% 100% 100% EV $ 300 $ 150 $ 100

$ 200
$ 100 $ 250 $ 200 $ 400 $ 300 $ 200

$ 225
$ 100 $ 300 $ 140 $ 100 $0 $0

100%
100% 60% 65% 20% 0% 0%

$ 200
$ 100 $ 150 $ 130 $ 80 $0 $0

DAY 5

Arch. Sherif Elwishahy, PMP

Case Study
1.Calculate BAC: Budget At Completion for the Project BAC= PV for all Activities BAC= 300+150+100+200+100+250+200+400+300+200 BAC= 2200 2.Calculate PV: Planned Value for the Scheduled Project PV = PV for activities till day 3 PV = 300+150+100+200+100+250 = 1100 3.Calculate AC: Actual Costs for the Project AC = AC for all activities AC = 300+200+150+225+100+300+140+250+0+0 AC = 1515 Arch. Sherif Elwishahy, PMP

Case Study
4.Calculate EV: for the Project EV= EV for all activities EV= 300+150+100+200+100+150+130+80+0+0 EV= 1210
5.Calculate CPI: Cost Performance Index CPI = EV / AC CPI = 1210 / 1515 = 0.799 6.Calculate SPI: Schedule Performance Index SPI= EV / PV SPI= 1210 / 1100 = 1.1
Arch. Sherif Elwishahy, PMP

Case Study
7.Calculate CV: Cost Variance CV = EVAC = 1210 1515 = -305 8.Calculate SV: Schedule Variance SV= EVPV = 1210 1100 = 110

9.Calculate EAC: Estimate At Completion (No corrective action + same performance expected) EAC= BAC / CPI EAC= 2200 / 0.799 = 2753 (Case I)
(Corrective action + one time error only) EAC= BAC+ (AC EV) EAC= BACCV = 2200 (-305) = 2505 (Case II) Arch. Sherif Elwishahy, PMP

Case Study
10.Calculate ETC: Estimate To Completion ETC = EAC-AC ETC = 2753 1515 = 1238 (Case I) ETC = 2505 1515 = 990 (Case II) 11.Calculate VAC: Variance At Completion VAC= BAC-EAC VAC= 2200 2753 = -553 (Case I) VAC= 2200 2505 = -305(Case II)

12.Calculate TCPI: To-Completion Performance Index TCPI= (BAC-EV) / (BAC-AC) TCPI= (2200 1210) / (2200 1515) TCPI= 990 / 685 = 1.445 Arch. Sherif Elwishahy, PMP

Question No : 1
You are the project manager for the JKH Project. You have elected to use parametric modeling in your cost estimating for the project. Which one of the following is an example of parametric modeling? A. $750 per ton B. Historical information from a similar project C. Estimates built from bottom-up based on the WBS D. Estimates based on top-down budgeting

Question No : 2
You are the project manager for a technical implementation project. The customer has requested that you factor in the after-the-project costs, such as maintenance and service. This is an example of which one of the following? A. Life cycle costs B. Scope creep C. Project spin off D. Operations

Question No : 3
You have just completed the initiating processes of a small project and are moving into the planning processes when a project stakeholder asks you for the projects budget and cost baseline. What should you tell her? A. The project budget can be found in the projects charter which has just been completed. B. The project budget and baseline will not be finalized and accepted until the planning processes are completed. C. The project management plan will not contain the projects budget and baseline, this is a small project. D. It is impossible to complete an estimate before the project management plan is created.

Question No : 4
Your project has a CV of -200. This means: A. Your project is under budget B. Your SPI is also negative C. Your project is above budget D. CV cannot be negative and there must be an error in the calculation.

Question No : 5
You are the project manager of the Carpet Installation Project for a new building. Your BAC is $600,000. You are now 40 percent done with the project, though your plan called for you to be 45 percent done with the work at this time. What is your earned value? A. $240,000 B. $270,000 C. $30,000 D. $30,000

Important Quality Concepts

Quality & Grade


Quality Is the sum of the characteristics of a product that allow it to meet the demands or expectations of the project. Quality is all about fulfilling requirements Grade Is a category or rank given to entities having the same functional use but different technical characteristics For example: there are different grades of paint, different grades of metal, and even different grades of travel.
Arch. Sherif Elwishahy, PMP

Precision & Accuracy


Accuracy
Means that the measured value is very close to the true value. Example: if you are testing a process and the target is 300 ml. output, accuracy deals with how close the measurement is to the 300 ml. target. Precision Means the values of repeated measurements are clustered and have little scatter. Example: how many of the outputs are 300 ml.
Arch. Sherif Elwishahy, PMP

Prevention & Inspection


Prevention Deals with eliminating defects and potential defects from the process. It is a proactive approach to quality. Inspection Deals with fixing errors as they come up in the process of creating the product. It is a reactive approach to quality.
Arch. Sherif Elwishahy, PMP

Total Quality Management


Is a philosophy conceived by Dr. Deming. It focuses on proactive attitude toward quality with a statistical analysis to document improvement. Quality should be planned not inspected.

Arch. Sherif Elwishahy, PMP

Zero Defect
Is a concept created by Philip Crosby. Do something right initially, and you shouldnt have to repeat it. If the money is spent upfront, the effort will eliminate or minimize the need for rework if defects occur. Main points: Cost of quality is measured by cost of nonconformance. Conformance to requirements. Quality comes from Prevention.
Arch. Sherif Elwishahy, PMP

Fitness For Use


Is a concept created by Joseph Juran.
The needs of the customers and stakeholders are defined and then attempted to satisfy. The main goal is to satisfy the real need of the customers and stakeholders.

Arch. Sherif Elwishahy, PMP

Kaizen
Means Kai (alter) and Zen (make better or improve). Small improvements in products or processes to reduce costs and ensure consistency of performance of products or services. In the US and most of Western Europe improvements are thought of as BIG improvements. In Japan, improvements are thought of as small improvements.
Arch. Sherif Elwishahy, PMP

Standard Deviation ( Sigma )


The formula for standard deviation is (P O) / 6. Minimum defects % acceptable from a process is sigma levels: 1 Sigma = 68.26% Accepted Defects = 317300000 / Billion 2 Sigma = 95.46% Accepted Defects = 45400000 / Billion 3 Sigma = 99.73% Accepted Defects = 2700 / Billion 6 Sigma = 99.9997% Accepted Defects = 3.4 / Billion
Arch. Sherif Elwishahy, PMP

Standard Deviatio ( Sigma )

6 Sigma 99.9997% 99.9997%

68.26% 95.46% 99.73%


Arch. Sherif Elwishahy, PMP

Project Quality Management

8. Quality Management
Project Quality Management includes the processes and activities that determine quality policies, objectives, and responsibilities. The objective is to satisfy the needs for which the project was undertaken. It applies to all projects, regardless of the nature of their product.

Arch. Sherif Elwishahy, PMP

8. Quality Management
Planning

Executing
8.2

Controlling

8.1

8.3

Arch. Sherif Elwishahy, PMP

8.1 Plan Quality Management


Arch. Sherif Elwishahy, PMP

8.1 Plan Quality Management


Is the process of: Identifying quality requirements and/or standards for the project and product. Documenting how the project will demonstrate compliance. Think through the rules that will define quality and establish them to verify that the product will adhere to the quality needs of the project.

Arch. Sherif Elwishahy, PMP

8.1 Plan Quality Management

Arch. Sherif Elwishahy, PMP

8.1.1 Plan Quality Management : Inputs


1. Project management plan 2. Stakeholder register 3. Risk register 4. Requirements documentation 5. Enterprise environmental factors 6. Organizational process assets

Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


1. Cost-Benefit Analysis: Is a key tool that involves analysis of how to minimize rework and maximize satisfaction and productivity. Marginal Analysis: Optimal quality is reached at the point where the incremental -revenue from improvement equals the incremental cost to secure it.

Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


2. Cost Of Quality [COQ]: Is the cost associated with conformance to requirements and steps taken to eliminate non-conformance.

Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


2. Cost Of Quality [COQ]:

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


3. Seven basic quality tools: 1- Cause and Effect Diagrams Also called Ishikawa diagrams or fishbone diagrams. Illustrate how various factors might be linked to potential problems or effects. A possible root cause can be uncovered by continuing to ask why or how along one of the lines.

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


2- Control Charts: Help measure and track output. Shows output over time so monitoring for variance and trends can be completed. Contains two limitations: Upper and Lower Control Limits (UCL, LCL). Upper and Lower Specs. Limits (USL, LSL). Assignable Cause: Is a measurement on the control chart that must be researched before you can determine the reason of the failure.
Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques 2- Control Charts:

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


Special Causes: Sometimes are called unusual events. They deal with things that dont typically happen associated with a test process. Common Causes: Sometimes called normal process variation or random cause. They deal with the variation that typically happens within a process. It deals with random events that can occur.
Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


2- Control Charts:

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


3- Flowcharting:

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


4- Histogram

Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques 5- Pareto Chart:

6- Check Sheets
Arch. Sherif Elwishahy, PMP

8.1.2 Perform Quality Control: Tools & Techniques


7- Scatter Diagram

Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


4. Benchmarking: Is a key tool used to compare the product or service to other established standards. Comparing planned practices to other projects, in order to generate ideas for improvement and to provide a standard against which to measure performance.

Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


5. Design of Experiments: Analytical technique that helps identify which variables have the most influence on the overall outcome Helps determine an optimal solution from a relatively limited number of cases. 6. Statistical Sampling: Is used to test an appropriate amount of output to detect defects. The quantity tested is enough so that the cost would not out weight the benefit.
Arch. Sherif Elwishahy, PMP

8.1.2 Plan Quality Management : Tools & Techniques


7. Additional Quality Planning Tools: These include but not limited to: Brainstorming. Affinity Diagrams. Force Field Analysis. Nominal Group Technique. Matrix Diagrams. Prioritization Matrices.

8. Meetings.
Arch. Sherif Elwishahy, PMP

8.1.3Plan Quality Management : Outputs


1. Quality management plan 2. Quality metrics Is an operational definition that describes, in very specific terms, a project or product attribute and how the quality control process will measure it.

Arch. Sherif Elwishahy, PMP

8.1.3Plan Quality Management : Outputs


3. Quality checklists Its usually a list of activities that workers will check off to ensure each task has been completed. Checklists can be quick instructions of what needs to be done to clean a piece of equipment, or questions that remind the employee to complete a task.

Arch. Sherif Elwishahy, PMP

8.1.3Plan Quality Management : Outputs


4. Process improvement Plan: Process boundaries: Describes the purpose of processes, their start and end, their inputs/ outputs, the data required, the owner, and the stakeholders. Process configuration: A graphic depiction of processes, with interfaces identified, used to facilitate analysis. Process metrics: Along with control limits, allows analysis of process efficiency. Targets for improved performance: Guides the process improvement activities.

5. Project Document updates.


Arch. Sherif Elwishahy, PMP

8.2 Perform Quality Assurance


Arch. Sherif Elwishahy, PMP

8.2 Perform Quality Assurance


Is the process of: Auditing the quality requirements and the results from quality control measurements to insure appropriate quality standards and operational definitions are used. We verify or validate that the quality standards defined for the project will indeed meet the standards. This validates the quality process not the product.

Arch. Sherif Elwishahy, PMP

8.2 Perform Quality Assurance

Arch. Sherif Elwishahy, PMP

8.2.1 Perform Quality Assurance: Inputs 1. Quality management plan 2. Process improvement plan 3. Quality metrics 4. Quality control measurements 5. Project documents

Arch. Sherif Elwishahy, PMP

8.2.2 Perform Quality Assurance: Tools & Techniques


1. Plan Quality and Control Quality Tools & Techniques.

Arch. Sherif Elwishahy, PMP

8.2.2 Perform Quality Assurance: Tools & Techniques


2. Quality Audits: Is a structured, independent review to determine whether project activities comply with organizational and project policies, processes, and procedures. The objectives of a quality audit are: Identify all the good/best practices being implemented, Identify all the gaps/shortcomings, Share the good practices. Proactively offer assistance in a positive manner. Highlight contributions of each audit in the lessons learned repository of the organization.

Arch. Sherif Elwishahy, PMP

8.2.2 Perform Quality Assurance: Tools & Techniques


3. Process Analysis: Utilize the process improvement plan to figure out ways to optimize the project execution. Root-Cause analysis is done to determine what is causing any problems and takes steps to eliminate similar problems in the future.

Arch. Sherif Elwishahy, PMP

8.2.3 Perform Quality Assurance: Outputs


1. Change requests

2. Project management plan updates


3. Project document updates 4. Organizational process assets updates

Arch. Sherif Elwishahy, PMP

8.3 Perform Quality Control


Arch. Sherif Elwishahy, PMP

8.3 Perform Quality Control


Is the process of: Monitoring and recording results of executing the quality activities to assess performance and recommend necessary changes. It is the process area in which the product or the output of the process is measured against the specifications. The items that roll off the line would be measured against the approved standard.

Arch. Sherif Elwishahy, PMP

8.3 Perform Quality Control

Arch. Sherif Elwishahy, PMP

8.3.1 Perform Quality Control: Inputs


1.Project Management Plan. 2.Quality Metrics. 3.Quality Checklists. 4.Work Performance Data. 5.Approved Change Requests. 6.Deliverables. 7. Project Documents 8.Organizational Process Assets.

Arch. Sherif Elwishahy, PMP

8.3.2 Plan Quality Management : Tools & Techniques


1. Seven Basic Quality Tools

Arch. Sherif Elwishahy, PMP

8.3.2 Perform Quality Control: Tools & Techniques


2. Statistical Sampling:

3. Inspection: Is the process of verifying that the work was built as intended includes measuring, examining, and testing. Performed at various points in the project Also referred to as reviews, peer reviews, audits, and walk-thorough.
4. Approved Change Requests Review:
Arch. Sherif Elwishahy, PMP

8.3.3Perform Quality Control: Outputs


1. Quality control measurements 2. Validated changes 3. Verified deliverables 4. Work Performance Information 5. Change requests 6. Project management plan updates 7. Project document updates 8. Organizational process assets updates
Arch. Sherif Elwishahy, PMP

Question No : 1
The customer was not satisfied with the finished product`s quality. The cost of poor quality can also be referred to as: A. Cost of conformance B. Failure cost C. Rework cost D.Opportunity cost .

Question No : 2
You are the project manager for the Floor Installation Project. Today, you plan to meet with your project team to ensure the project is completed with no deviations from the project requirements. This process is which of the following? A. Quality planning B. Quality management C. Quality control D. Quality assurance

Question No : 3
All the following statements about "Quality" and "Grade" are true EXCEPT: A. Grade is a rank given to entities having the same functional use but different technical characteristics. B. Low quality product may be of high grade. C. Low grade product may be of high quality. D. It is a problem if the product is of high quality and low grade.

Question No : 4
You are the project manager for the KOY Project. This project Requires Quality that maps to federal guidelines. To ensure that you can meet these standards, you have elected to send the project team through training specific to the federal guidelines your project must adhere to. The costs of these classes can be assigned to which of the following? A. Cost of doing business B. Cost of quality C. Cost of adherence D. Cost of nonconformance

Question No : 5
In the following graphic, what does the highlighted area represent? A. Out of control data points B. In control data points C. Rule of seven D. Standard deviation

Project Human Resource Management

9. Human Resource Management


Planning
9.1

Executing
9.2

9.3

9.4

Arch. Sherif Elwishahy, PMP

9. Human Resource Management


Project HR Management includes the processes that organize, manage, and lead the project team. PMIs perspective is that the Project Manager has human resource responsibilities and authority.

Arch. Sherif Elwishahy, PMP

9.1 Develop Human Resource Plan


Arch. Sherif Elwishahy, PMP

9.1 Develop Human Resource Plan

Is the process of: Identifying and documenting project roles, responsibilities and required skills. Reporting relationships Creating a staffing management plan. Individuals and groups may be part of the organization or external to it.

Arch. Sherif Elwishahy, PMP

9.1 Plan Human Resource Management

Arch. Sherif Elwishahy, PMP

9.1.1 Develop Human Resource Plan : Inputs


1. Project Management Plan

2.Activity Resource Requirements.


3.Enterprise Environmental Factors. 4.Organizational Process Assets.

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques


1. Organization Charts and Position Description: Also known as Organizational Breakdown Structure [OBS] or Resource Breakdown Structure [RBS]. It is a graphical display of reporting relationships on the project. Position Description help team members understand their project responsibilities. We can categorize into (3) types: Hierarchical-type chart (OBS, or RBS). Matrix-based chart (RAM). Text-oriented format.

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques


2. Networking: Is a good opportunity to ensure that an appropriate approach to staffing and the appropriate parties are involved. Is a formal and informal interaction with others in an organization, industry, or professional environment. Human Resource networking activities include: Proactive correspondence. Luncheon meetings. Informal conversations. Trade conferences.
Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques


3. Organizational Theory: Helps establish how the organization or project should be structured. Effective use of this information can: Shorten the amount of time, cost, and effort needed to create the human resource planning outputs. Improve the likelihood that the planning will be effective.

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Tools & Techniques


4. Expert Judgment

5. Meetings

Arch. Sherif Elwishahy, PMP

9.1.2 Develop Human Resource Plan : Outputs


1. Human Resource Plan: Is created to include roles and responsibilities, organizational charts, and a staffing management plan for the project. The plan should include at minimum: Documentation of roles and responsibilities. Project organization charts that define team members and their reporting hierarchy. Staffing Management Plan.

Arch. Sherif Elwishahy, PMP

Role &Responsibility
Role: The portion of a project for which a person is accountable. Authority: Right to apply project resources, expend funds, make decisions, or give approvals Responsibility: Work that a project team member is expected to perform. Competency: Skill and capacity required to complete project activities.

Arch. Sherif Elwishahy, PMP

Staffing Management Plan


Is part of the Human Resource Plan and helps Project Manager and team do the following: Acquire staff. Establish Resource Calendar. Create a staff release plan. Establish training requirements. Establish recognition and rewards. Ensure compliance. Ensure safety.
Arch. Sherif Elwishahy, PMP

9.2 Acquire Project Team

Arch. Sherif Elwishahy, PMP

9.2 Acquire Project Team


Is the process of: Confirming human resource availability. Obtaining the team necessary to complete project assignments. The project management team may or may not have direct control over team member selection because: Use of subcontractor personnel. Matrix project environment.

Arch. Sherif Elwishahy, PMP

9.2 Acquire Project Team

Arch. Sherif Elwishahy, PMP

9.2.1 Acquire Project Team: Inputs


1.Human Resource Management Plan.

2.Enterprise Environmental Factors.


3.Organizational Process Assets.

Arch. Sherif Elwishahy, PMP

9.2.2 Acquire Project Team: Tools & Techniques


1. Pre-Assignment: Pre-assignment occurs when it is known in advance that certain people will be on the project team. Some of the reasons could be: Some people being promised as part of a competitive proposal. The project depends upon the expertise of particular persons.

Some staff assignments are defined within the project charter.


Arch. Sherif Elwishahy, PMP

9.2.2 Acquire Project Team: Tools & Techniques


2. Negotiation:
Staff assignments are negotiated on many projects.

The project management team negotiates with:


Functional Managers.

Other Project Management teams.


External organizations (vendors, contractors).

Arch. Sherif Elwishahy, PMP

9.2.2 Acquire Project Team: Tools & Techniques


3. Acquisitions: Required services may be acquired from outside sources. Can involve hiring individual consultants or subcontracting work to another organization.

Arch. Sherif Elwishahy, PMP

9.2.2 Acquire Project Team: Tools & Techniques


4. Virtual Teams: Are comprised of people working in various locations. They can work together virtually via technology for activities such as communication and information sharing.

Benefits may be:


Form teams who live in widespread geographic areas. Incorporate employees who work from home offices.

Include people with mobility limitations or disabilities.


Launch projects that would have been ignored due to travel expenses.
Arch. Sherif Elwishahy, PMP

9.2.2 Acquire Project Team: Tools & Techniques


5. Multi-Criteria Decision Analysis Criteria is developed and used to rate potential team members. The criteria is weighted according to the relative importance. Some examples of selection criteria are as follows: Availability. Cost. Experience. Ability. Knowledge Skills. Attitude. International factors.
Arch. Sherif Elwishahy, PMP

9.2.3 Acquire Project Team: Outputs


1. Project Staff Assignments.

2. Resource Calendars: Document the time periods that each project team member can work on the project. This should include: Vacations. Commitment to other projects. Team member availability.
3. Project Management Plan Update.
Arch. Sherif Elwishahy, PMP

9.3 Develop Project Team

Arch. Sherif Elwishahy, PMP

9.3 Develop Project Team


Is the process of: Improve knowledge and skills of team members. Improve feelings of trust and agreement among team members to lower conflict, and increase team work. Create a team culture to allow cross-training and mentoring between team members to share knowledge and expertise.

Arch. Sherif Elwishahy, PMP

9.3 Develop Project Team

Arch. Sherif Elwishahy, PMP

9.3.1 Develop Project Team: Inputs


1.Project Human Resource Plan.

2.Project Staff Assignments..


3.Resource Calendars.

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques


1. Interpersonal Skills: Sometimes known as Soft Skills. Are vital to maximize the output of the team. This allows the project manager to work with the appropriate parties as needed to get the necessary outcome. Skills such as: Empathy. Influence. Creativity. Group Facilitation.
Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques


2. Training: Is a key to team development. Training focuses on developing the individual, which helps make the team stronger. There are a number of training formats: Online, and Computer-based. Classroom. On-the-job. Mentoring, and Coaching. Learning from other team members.

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques


3. Team-Building Activities: Help in team development. Activities could include group lunches or an evening away from work in a social environment. Reward and recognize individual work efforts.

Arch. Sherif Elwishahy, PMP

Team Development Life Cycle

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques


4. Ground Rules: Help set performance and other expectations by the team members. Early commitment to clear guidelines decreases misunderstandings and increase productivity. All project team members share responsibility for enforcing the rules once they are established.

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques 5. Co-Location: Team members are places at the same location (War Room). It generally helps facilitate team-building by having people working together. While co-location is considered a good strategy, the use of virtual teams is sometimes unavoidable.

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques


6. Recognition and Rewards: It is part of the Develop Human Resource Plan. To help with cohesiveness, by including rewards that all on the project can win, not just a certain person or a few.

Arch. Sherif Elwishahy, PMP

9.3.2 Develop Project Team: Tools & Techniques 7. Personnel Assessment Tools:
These tools help project managers assess the team preferences, aspirations, how they process information, how they make decisions, and how they prefer to interact with people. Various tools are available such as attitudinal surveys, specific assessments, structured interviews, ability tests, and focus groups. These tools can provide improved understanding, trust, commitment, and communications among team members.
Arch. Sherif Elwishahy, PMP

9.3.3 Develop Project Team: Outputs


1.Team Performance Assessments: The evaluation may include: Improvement in skills. Improvements in competencies that help the team perform better as a team. Reduced staff turnover rate. Increased team cohesiveness. 2.Enterprise Environmental Factors (UPDATE).
Arch. Sherif Elwishahy, PMP

9.4 Manage Project Team

Arch. Sherif Elwishahy, PMP

9.4 Manage Project Team

Is the process of: Tracking team member performance. Providing feedback. Resolving issues. Managing changes to optimize project performance. It requires a variety of management skills to create high-performance teams.

Arch. Sherif Elwishahy, PMP

9.4 Manage Project Team

Arch. Sherif Elwishahy, PMP

9.4.1 Manage Project Team: Inputs


1.Human Resource Management Plan.

2.Project Staff Assignments.


3.Team Performance Assessment. 4. Issue Log. 5.Work Performance Reports. 6.Organizational Process Assets.
Arch. Sherif Elwishahy, PMP

9.4.2 Manage Project Team: Tools & Techniques


1. Observation and Conversation: Used to monitor work being accomplished, plus their attitude on the project. 2. Project Performance Appraisals: Used to evaluate team members performance. They can be formal or informal. Is sometimes called 360 degree feedback because the feedback comes from all around the team members including the member under review himself / herself.
Arch. Sherif Elwishahy, PMP

9.4.2 Manage Project Team: Tools & Techniques


3. Conflict Management: Helps raise productivity and enhance working relationships. Common sources of can be: Scheduling Project priorities. Resource. Technical Opinions.

Arch. Sherif Elwishahy, PMP

Conflict Resolution Techniques


Problem Solving (confrontation) Directly addresses disagreements this method is considered to be a win-win, should be the first choice. Compromising (bargaining) Both parties must give up something. Smoothing Emphasizes on commonalties keeps the atmosphere friendly.

Arch. Sherif Elwishahy, PMP

Conflict Resolution Techniques


Collaborating Involves incorporating multiple ideas and viewpoints from people with different perspectives. Withdrawal (avoidance) Retreating from actual or potential disagreements. Forcing Exerts one's viewpoint at the potential expense of another party, it provides resolution but is considered to be a win-lose.

Arch. Sherif Elwishahy, PMP

9.4.2 Manage Project Team: Tools & Techniques


4. Interpersonal Skills: Are keys to working with team members as needed to maximize team performance. Vital interpersonal skills : Leadership. Influencing. Effective decision making.

Arch. Sherif Elwishahy, PMP

Power of Project Manger


Legitimate (Formal) Power :

The power is based on position.


Reward Power : Stems from the ability to reward. Expert Power : The power comes from being the technical expert.

Referent Power:
Is based on the person liking the individual. Punishment Power: Comes from the ability to penalize.
Arch. Sherif Elwishahy, PMP

9.4.3 Manage Project Team: Outputs


1.Change requests
2.Project management plan updates 3. Project Document Update.

4.Enterprise environmental factors updates


5.Organizational process assets updates
Arch. Sherif Elwishahy, PMP

Motivational Theories
Arch. Sherif Elwishahy, PMP

Maslows Hierarchy of Needs

A Satisfied need is no longer a motivation!!

Arch. Sherif Elwishahy, PMP

Herzberg Hygiene Factor


Herzberg had two (2) main areas for workspace success: Hygiene Factors: Focus mainly on areas associated with workplace (safe work environment, steady pay, and stable job). Motivational Factors: Non financial characteristics of work (opportunity to improve, do more, education, and responsibility) Money does not create motivation.

Arch. Sherif Elwishahy, PMP

McClellands theory
Resolves around three (3) aspects: Achievement: Being successful. Power: Influencing others.

Affiliation: Belonging.

Arch. Sherif Elwishahy, PMP

McGregors Theory X & Theory Y


Theory X : Management assumed employees ARE lazy and hate work. Employees will avoid work Employees are only after $$ Managers blame & punish Managers job is to structure and energize employees.

Theory Y : Employees enjoy their physical and mental work. Employees MIGHT BE ambitious & self motivated Managers assume that if given the right conditions, people will DO WELL, which is THE MOTIVE.

Arch. Sherif Elwishahy, PMP

Expectancy Theory
The employee work a great deal on the project and assumes that the reward will be relative to the amount of effort or perceived effort. This assumption can usually be quite a disappointment for those believing they will be greatly rewarded when the project is done.

Arch. Sherif Elwishahy, PMP

Question No : 1
You are the project manager of the PUY Project. This project requires a chemical engineer for seven months of the project although there are no available chemical engineers within your department. This is an example of which of the following? A. Organizational interfaces B. Staffing requirements C. Contractor requirements D. Resource constraints

Question No : 2
You are the project manager for the LMG Project. Your project will have several human resource issues that must be coordinated and approved by the union. Which of the following statements is correct about this scenario? A. The union is considered a resource constraint. B. The union is considered a management constraint. C. The union is considered a project stakeholder. D. The union is considered a project team member.

Question No : 3
Management has requested that you create a chart depicting all of the project resource needs and the associated activities. Management is looking for which type of chart? A. A roles chart B. A roles matrix C. A roles and responsibilities matrix D. A Gantt chart

Question No : 4
Which problem-solving technique is the best for most project management situations? A. Confronting B. Compromising C. Forcing D. Avoidance

Question No : 5
Mike is the project manager for a project with a very tight schedule. The project is running late and Mike feels that he does not have time to consider all the possible solutions that two team members are in disagreement over. Mike quickly decides to go with the team member with the largest amount of seniority. This is an example of which of the following? A. Problem solving B. Compromising C. Forcing D. Withdrawal

Project Communication Management

Miscommunication

Communication Activities

Internal External Vertical Horizontal Formal Informal Written and Oral Verbal and Non-verbal

Arch. Sherif Elwishahy, PMP

Communications Skills
listening actively and effectively, Questioning, probing ideas and situations to ensure better understanding, Educating to increase teams knowledge so that they can be more effective. Fact-finding to identify or confirm information, Persuading a person or organization to perform an action. Negotiating to achieve mutually acceptable agreements between parties. Resolving conflict to prevent disruptive impacts.
Arch. Sherif Elwishahy, PMP

Communication Types and Methods

Formal Written: charter, plans, long distance Formal verbal : Speeches, Press conferences Informal Written: emails, memos Informal verbal: meetings, conversations

Arch. Sherif Elwishahy, PMP

10. Communication Management


Planning Executing Monitoring

10.1

10.2

10.3

Arch. Sherif Elwishahy, PMP

10.1 Plan Communication Management


Arch. Sherif Elwishahy, PMP

10.1 Plan Communication


Is the process of: Developing an appropriate approach and plan for project communications. Based on stakeholders information needs and requirements, and available organizational assets. Key criteria here is: What information they need? When its needed? In what format?

Arch. Sherif Elwishahy, PMP

10.1 Plan Communication

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques

1. Communication Requirements Analysis: Factors in the communication requirements to ensure they are properly addressed in the Communication Management Plan. This analysis can include: Organization Charts. Responsibility Assignment Matrix [RAM]. Logistical needs. Internal and external information requirements.
Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques


Communications is a complex part of any project. The more people involved in a project, the more communication channels among them. The formula is: Number of communication channels =

N * (N-1) / 2
Where N is the number of people on the project.

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques

Arch. Sherif Elwishahy, PMP

Example
A Project Manager has a team of 6 working on the project. During a certain phase of the project, 2 new members have been added to the project. How many channels were added when the new members joined ?

Arch. Sherif Elwishahy, PMP

N Original = 7 Channels Original = 7 * 6 / 2 = 21 N New= 9 Channels New= 9 * 8 / 2 = 36 Added channels = 36 21 = 15 channel

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques


2. Communication Technology: Distributes project information per the requirements in the Communication Management Plan. Variables that influence the use of the technology could be: The importance of the information needed. The use of the technology infrastructure. Staffing levels. Project length. Project team culture.

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques


3. Communication Models: Are used to establish how communication will be encoded, decoded and what the medium of the message will be.
Message

Encode
sender Noise medium Noise

decode
receiver

decode
Feedback- message

encode

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques


Key components of a basic model of communication include: Encode - to translate thoughts or ideas into a language that is understood by others Message - output of encoding Medium - method used to convey the message Noise - anything that interferes with the transmission and understanding of the message Decode - translate the message back into meaningful thoughts or ideas

Arch. Sherif Elwishahy, PMP

10.1.2 Plan Communication: Tools & Techniques

4. Communication methods Interactive communications Push communications Pull communications

5. Meetings.

Arch. Sherif Elwishahy, PMP

10.1.3 Plan Communication: Outputs 1. Communications Management Plan: The plan defines: Communication needs of the stakeholders. Communication format. Communications frequency. The plan helps the PM do: Communication infrastructure for distributing information. Report performance on the project. Deal with communication issues that arise on the project.
Arch. Sherif Elwishahy, PMP

10.2 Manage Communication

Arch. Sherif Elwishahy, PMP

10.2 Manage Communication

Is the process of:


Ensuring that the information communicated has been appropriately generated, received and understood. Techniques for effective communications management: Sender-receiver models. Choice of media. Writing style. Meeting management techniques. Presentation techniques. Facilitation techniques. Listening techniques.

Arch. Sherif Elwishahy, PMP

10.2 Manage Communication

Arch. Sherif Elwishahy, PMP

10.2.2 Manage Communication: Tools & Techniques


1. Communication technology 2. Communication models 3. Communication methods 4. Information management systems 5. Performance reporting Analysis of past performance. Analysis of project forecasts (including time and cost). Current status of risks and issues. Work completed during the period. Work to be completed in the next period. Summary of changes approved in the period.

Arch. Sherif Elwishahy, PMP

10.2.3 Manage Communication: Outputs

1. Project communications
The activities that are required for information to be created, distributed, received, acknowledged, and understood.

2. Project management plan updates 3. Project documents updates 4. Organizational process assets updates
Arch. Sherif Elwishahy, PMP

10.3 Control Communications

Arch. Sherif Elwishahy, PMP

10.3 Control Communications


Is the process of: Monitoring and controlling communications throughout the entire Project life cycle to ensure the information needs of the project stakeholders are met.

Arch. Sherif Elwishahy, PMP

10.3 Control Communications

Arch. Sherif Elwishahy, PMP

1. Work performance information 2. Change requests 3. Project management plan updates 4. Project documents updates 5. Organizational process assets updates

Arch. Sherif Elwishahy, PMP

Question No : 1
Of the following, which one is not an example of formal communications? A. Presentations to groups B. conversations C. Contractual agreements D. Presentations to management

Question No : 2
You are the project manager for the LKH Project. Management has requested that you create a document detailing what information will be expected from stakeholders and to whom that information will be disseminated. Management is asking for which one of the following? A. Roles and responsibilities matrix B. Scope Management Plan C. Communications Management Plan D. Communications worksheet

Question No : 3
You are the project manager for the JGI Project. You have 32 stakeholders on this project. How many communications channels do you have? A. Depends on the number of project team members. B. 496 C. 32 D. 1

Question No : 4
Which one of the following is an output from controlling communications? A. Trend analysis B. EVM C. Variance analysis D. Change requests

Project Risk Management

Objectives are to increase the probability and impact of positive events and decrease the probability and impact of negative events In the project A key overlying concept is consistency and proactively approach the risk on the project.

Arch. Sherif Elwishahy, PMP

11. Risk Management


Planning
11.1 11.2 11.3

Monitoring
11.6

11.4 11.5

Arch. Sherif Elwishahy, PMP

11.1 Plan Risk Management

Arch. Sherif Elwishahy, PMP

11.1 Plan Risk Management Is the process of: Defining how to conduct risk management activities for a project. The PM and the team proactively plan how to identify, rank, and address risk and risk management. The companys risk management policies help define what the team will do on the project regarding risk and risk management.
Arch. Sherif Elwishahy, PMP

11.1 Plan Risk Management

Arch. Sherif Elwishahy, PMP

1. Analytical Techniques Analytical techniques are used to understand and define the overall risk management context of the project. Stakeholder risk profile analysis is performed to grade and qualify the project stakeholder risk appetite and tolerance. Risk scoring sheets, are used to provide a highlevel assessment of the risk exposure of the project.
Arch. Sherif Elwishahy, PMP

1. Risk Management Plan Methodology: a guideline system for solving a problem, with specific components such as phases, tasks, methods, techniques and tools. Roles and Responsibilities Budgeting Timing Risk Categories Definition of Risk Probability and Impact Revised Stakeholders' Tolerance Reporting Formats Tracking Arch. Sherif Elwishahy, PMP

Risk Breakdown Structure

Arch. Sherif Elwishahy, PMP

Probability & Impact Matrix

Arch. Sherif Elwishahy, PMP

Probability & Impact Matrix


Impact Very Low 0.05 Low 0.10 Moderate 0.20 High 0.40 Very High 0.80

Probability Very High 90% .045 .035 .09 .07 .18 .14 .36 .28 .72 .56

High 70%
.025 Moderate 50% .015 Low 30% .01 Very Low 10 % Arch. Sherif Elwishahy, PMP .01 .02 .04 .08 .03 .06 .12 .24 .05 .10 .20 .40

Risk Tolerance
Risk tolerance for a person or organization can influence the project environment. There are three types of risk tolerance: Risk-Averse Is a mentality of risk avoidance. Risk-Neutral Is a middle ground mentality towards risk. Risk-Seeker Is a mentality of looking for risk,
Arch. Sherif Elwishahy, PMP

11.2 Identify Risks

Arch. Sherif Elwishahy, PMP

11.2 Identify Risks


Is the process of: The project Manager, team, and any key stakeholder determine which risks may affect the project and documenting their characteristics. These risks could be small impact risks with a low probability of happening, to large impact risks with a high probability of happening. The team could also use a predefined list from previous projects as a starting point for the project. When complete, the team moves any risks to Qualitative Risk Analysis. Or determine that they dont need to devote time to developing a response strategy.
Arch. Sherif Elwishahy, PMP

11.2 Identify Risks

Arch. Sherif Elwishahy, PMP

11.2.2 Identify Risks: Tools & Techniques


1. Documentation Reviews: Are done on a project to evaluate potential risk and trigger identification. One of the important documents to be revised is the WBS. 2. Information Gathering Techniques: This can include: Brainstorming. Delphi Technique. Interviewing. Root cause Identification

3. Checklist Analysis: Is useful for verification that things are done as planned.
Arch. Sherif Elwishahy, PMP

11.2.2 Identify Risks: Tools & Techniques


4. Assumption Analysis.

Arch. Sherif Elwishahy, PMP

11.2.2 Identify Risks: Tools & Techniques


5. Diagramming Techniques: Cause and Effect Diagram (Ishikawa Fishbone). System or Process Flow Charts. Influence Diagrams.

Arch. Sherif Elwishahy, PMP

11.2.2 Identify Risks: Tools & Techniques


6. SWOT Analysis: Is done to perform a review of the project environment to see: Strengths Weakness Opportunities Threats 7. Expert Judgment.
Arch. Sherif Elwishahy, PMP

11.2.3 Identify Risks: Outputs


1. Risk Register:

Arch. Sherif Elwishahy, PMP

11.3 Perform Qualitative Risk Analysis


Arch. Sherif Elwishahy, PMP

11.3 Perform Qualitative Risk Analysis


The process of prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact Comes from evaluating a component (risk) of a project as high, medium, or low.

Arch. Sherif Elwishahy, PMP

11.3 Perform Qualitative Risk Analysis

Arch. Sherif Elwishahy, PMP

11.3.2 Perform Qualitative Risk Analysis: Tools & Techniques


1. Risk Probability and Impact Assessment: Helps show what is likely to happen on the project and the effects of it by applying it to a Probability and Impact Matrix. Severity of Risk Event (Risk Score) = Impact X Probability
Impact Probability
Very Low 0.05 Low 0.10 Moderate 0.20 High 0.40 Very High 0.80

Very High 90% High 70% Moderate 50% Low 30% Very Low 10 %

.045 .035 .025 .015 .01

.09 .07 .05 .03 .01

.18 .14 .10 .06 .02

.36 .28 .20 .12 .04

.72 .56 .40 .24 .08

Arch. Sherif Elwishahy, PMP

11.3.2 Perform Qualitative Risk Analysis: Tools & Techniques


2. Probability and Impact Matrix:

Arch. Sherif Elwishahy, PMP

11.3.2 Perform Qualitative Risk Analysis: Tools & Techniques

3. Risk Data Quality Assessment: Qualitative risk analysis requires accurate and unbiased data for it to be credible. It provides a technique to evaluate the degree to which the data about risks is useful for risk management. Involves examining the: Degree to which the risk is understood. Accuracy, reliability, and integrity of the risk data.
Arch. Sherif Elwishahy, PMP

11.3.2 Perform Qualitative Risk Analysis: Tools & Techniques


4. Risk Categorization: Is used to help group sources of risk and areas of project risk. Grouping risks by common root causes can result in developing effective risk responses. Categories can be based on: Source of the risk using the Risk Breakdown Structure. Areas of the project affected using the Work Breakdown Structure. Other categories like project phases.

Arch. Sherif Elwishahy, PMP

11.3.2 Perform Qualitative Risk Analysis: Tools & Techniques


5. Risk Urgency Assessment: Review risk requiring near-term responses.

6. Expert Judgment: Is a key to assess the probability and impact of each risk. Experts with relevant experience of: Similar Projects. Business Areas. Experts bias needs to be taken into consideration here.

Arch. Sherif Elwishahy, PMP

11.4 Perform Quantitative Risk Analysis


Arch. Sherif Elwishahy, PMP

11.4 Perform Quantitative Risk Analysis

Is the process of: Numerically analyzing the effect of identified risks on overall project objectives. Quantitative Risk Analysis breaks down risks from a high, medium, and low ranking to actual numerical values and probabilities of occurrence. Risks that are higher in probability and impact are more likely to be evaluated via quantitative risk analysis.
Arch. Sherif Elwishahy, PMP

11.4 Perform Quantitative Risk Analysis

Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques 1. Date Gathering and Representation Techniques: Interviewing Probability Distributions

Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques

2. Quantitative Risk Analysis and Modeling Techniques: Commonly used techniques in Quantitative Risk Analysis include: Sensitivity Analysis. Expected Monetary Value Analysis (EMV). Decision Tree Analysis.

Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques


Sensitivity Analysis: A technique used to determine how different values of an independent variable will impact a particular dependent variable under a given set of assumptions. such as the effect that changes in interest rates will have on a bond's price.

Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques

EMV (Expected Monetary Value): Is a statistical concept that calculates the average outcome when the future includes scenarios that may or may not happen. Decision tree analysis: Is usually structured using a decision tree diagram that describes a situation under consideration.

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Case Study
FFP Contract Value
Per Day Penalty for delay Self Execute 80% chance the cost is $ 80,000

$ 100,000
$ 1,000

20% chance the cost is


Chance the project is on time Chance the project is delayed 2 days Out source

$ 90,000
95 % 5%

60% chance the cost is


40 % chance the cost is Chance the project is on time Chance the project is delayed 20 days

$ 70,000
$ 80,000 80 % 20 %
Arch. Sherif Elwishahy, PMP

Case Study

Self Exec. Or Out Source

EVM = 22000 $ The decision to out source the contract


Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques

Modeling & Simulation: Is using a model that translates the specified detailed uncertainties of the project into their potential impact on project objectives. Monte Carlo is a mock-up technique that uses software to simulate project characteristics to determine possible outcome. Probability Tables.

Arch. Sherif Elwishahy, PMP

11.4.2 Perform Quantitative Risk Analysis: Tools & Techniques

Arch. Sherif Elwishahy, PMP

11.4.3 Perform Quantitative Risk Analysis: Outputs

1.Project Documents Updates: Probabilistic analysis of the project. Probability of achieving cost and time objectives. Prioritized list of quantified risks. Trends in quantitative risk analysis results.

Arch. Sherif Elwishahy, PMP

11.5 Plan Risk Response

Arch. Sherif Elwishahy, PMP

11.5 Plan Risk Response


Is the process of: Developing options and actions to enhance opportunities and to reduce threats to project objectives. This could be anything from doing nothing, to full implementation of a detailed risk response.

Arch. Sherif Elwishahy, PMP

11.5 Plan Risk Response

Arch. Sherif Elwishahy, PMP

11.5.2 Plan Risk Response: Tools & Techniques


1. Strategies for Negative Risk or Threats:
Avoid

Changing the plan to eliminate a risk by avoiding the cause/source of risk


Transfer

Do it ourselves (do not subcontract)

Shift responsibility of risk consequence to another party


Mitigate

Buy/subcontract: move liabilities Use more qualified resources


Arch. Sherif Elwishahy, PMP

Seeks to reduce the impact or probability of the risk event to an acceptable threshold

11.5.2 Plan Risk Response: Tools & Techniques


2. Strategies for Positive Risk or Opportunity:
Strategy Definition Involves sharing the responsibility (and benefits) of the risk with a third party to maximize an opportunity Involves taking steps to ensure the risk and success of the event or project. Involves taking steps to improve the size / capacity of the risk event by determining the key components of the risk and maximize those components. Example The technology company formed a partnership with a marketing company to launch a sales campaign. The new project had the best resources assigned to maximize the probability of success When sales were exceeding projections, the company hired more sales people to ensure that as many customers as possible knew of their products
Arch. Sherif Elwishahy, PMP

Share

Exploit

Enhance

11.5.2 Plan Risk Response: Tools & Techniques


Strategy for Positive and Negative Risk: Acceptance: Involves tolerating the risk and dealing with it. It is a valid option if there are no other options available. Determining that if a union goes on strike, the project will have to stop until the strike is settled.

Arch. Sherif Elwishahy, PMP

11.5.2 Plan Risk Response: Tools & Techniques


3. Contingent Response Strategy: Created to be used if only certain conditions are present. This could be created if conditions change on the project or to accommodate for worst case situations. Example: The team developed a contingency plan to add staff to the project if the important development milestones was missed.

Arch. Sherif Elwishahy, PMP

Important Notes
Residual Risk is the amount of risk remaining after a risk response has been implemented. Secondary Risk is a jeopardy that results from the implementation of a risk response (side effects). Work around is a contingency put into action when a risk response and any backup plan dont work.
Arch. Sherif Elwishahy, PMP

Important Notes
Contingency Reserves: Known Unknowns: for risk events that you know can occur on a project. Example: Something costing more than planned, taking longer than planned, or scope creep. Management Reserves: Unknown Unknowns: for risk events you cant forecast potentially occurring on a project. Example: Natural disaster or terrorist attack.

Arch. Sherif Elwishahy, PMP

11.6 Control Risks


Arch. Sherif Elwishahy, PMP

11.6 Monitor & Control Risks


Is the process of: Implementing risk response plans. Tracking identified risks. Monitoring residual risks. Identifying new risks. Evaluating risk process effectiveness throughout the project. It can include verifying if project assumptions are still applicable.

Arch. Sherif Elwishahy, PMP

11.6 Control Risks

Arch. Sherif Elwishahy, PMP

11.6 Control Risks: Tools & Techniques


1. Risk Reassessment: Should go on throughout the project. Reevaluate the probability and impact of the identified risk. Monitor for any new risk. 2. Risk Audits: Are used for effectiveness. Periodic project Risk Reviews can help detect potential risk exposure.
Arch. Sherif Elwishahy, PMP

11.6 Control Risks: Tools & Techniques


3. Variance and Trend Analysis: Trends in projects execution should be reviewed using performance data. Earned value analysis and other trend analysis may be used for monitoring overall project performance. 4. Technical Performance Measurement: Helps verify if the project is performing compared to the planned standard.
Arch. Sherif Elwishahy, PMP

11.6 Control Risks: Tools & Techniques


5. Reserve Analysis: Analyze the amount of schedule or budget contingency reserve to the remaining risk on the project. 6. Meetings: Can be an agenda item at periodic status meetings.

Arch. Sherif Elwishahy, PMP

11.6 Control Risks: Outputs

1. 2. 3. 4. 5.

Work performance information Change requests Project management plan updates Project documents updates Organizational process assets updates

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Question No : 1
The customers of the project have requested additions to the project scope. The project manager brings notice that additional risk planning will need to be added to the project schedule. Why? A. The risk planning should always be the same amount of time as the activities required by the scope change. B. Risk planning should always occur whenever the scope is adjusted. C. Risk planning should only occur at the project managers discretion. D. The project manager is incorrect; risk planning does not need to happen at every change in the project.

Question No : 2
You are the project manager of the KLJH Project. This project will last two years and has 30 stakeholders. How often should risk identification take place? A. Once at the beginning of the project. B. Throughout the execution processes. C. Throughout the project. D. Once per project phase.

Question No : 3
You are the project manager for a project that will create a new and improved web site for your company. Currently, your company has over eight million users around the globe. You Would like to poll experts within your organization with a simple, anonymous form asking for any foreseeable risks with the design, structure, and intent of the web site. With the collected information, subsequent anonymous polls are submitted to the group of experts. This is an example of ____. A. Risk identification B. A trigger C. An anonymous trigger D. The Delphi Technique

Question No : 4
You have just been assigned as the project for a new telecommunications project that is entering the second phase of the project. There appear to be many risks on this project but no one has evaluated them to assess the range of possible project outcomes. What needs to be done? A. Plan risk management. B. Perform quantitative risk analysis. C. Plan risk responses. D. Monitor and control risks.

Question No : 5
The water sanitation project manager has determined the risks associated with handling certain chemicals are too high. He has decided to allow someone else to complete this portion of the project, and so has outsourced the handling and installation of the chemicals and filter equipment to an experienced contractor. This is an example of which of the following? A. Avoidance B. Acceptance C. Mitigation D. Transference

Project Procurement Management

12. Procurement Management


Planning
12.1

Executing
12.2

Monitoring
12.3

Closing
12.4

Arch. Sherif Elwishahy, PMP

Includes the processes to purchase or acquire the products, services, needed from outside the project team to perform the work.

Arch. Sherif Elwishahy, PMP

12.1 Plan Procurement Management


Arch. Sherif Elwishahy, PMP

12.1 Plan Procurement Plan procurements is the process of documenting project purchasing decisions, specifying the approach, and identifying potential sellers. Plan procurement process includes consideration of the risks involved with each make-or-buy decision.

Arch. Sherif Elwishahy, PMP

12.1 Plan Procurement

Arch. Sherif Elwishahy, PMP

1. Make-or-buy analysis A general management technique used to determine whether particular work can be best accomplished by the project team or must be purchased from outside sources.

Budget constraints may influence make-or-buy decisions, or purchase/lease decision.

Arch. Sherif Elwishahy, PMP

Example Purchase investment cost is $2000, Daily cost is $40 and Daily Lease cost $240. How long will it take for the lease cost to be the same as the purchase cost? Solution:
2000 + 40 * X = 240 * X

2000=240*x-40*x
2000=(240-40)x X = 2000 / 200 = 10 days
Arch. Sherif Elwishahy, PMP

Contracts: are a legally binding documents (formal agreement), should state all requirements.
Contract must be followed and everything provided in it must be done.

Any change must be written and formally controlled and approved by both parties.

Arch. Sherif Elwishahy, PMP

Contracts mainly fall into one of following 4 Categories: Purchase Order (PO). Fixed Price (FP). Known as Lump Sum. Cost Reimbursement (CR). Time and Materials (TM) (T&M).

Arch. Sherif Elwishahy, PMP

Fixed Price (FP)


Firm fixed price contracts (FFP ) The most commonly used contract type is the FFP. Any cost increase due to adverse performance is the responsibility of the seller. The buyer must precisely specify the product or services to be procured. Fixed price incentive fee contracts (FPIF ) It allows for deviation from performance, with financial incentives tied to achieving agreed to metrics. Under FPIF contracts, a price ceiling is set. Fixed price with economic price adjustment contracts (FB-EPA) Is used when the work required spans a period of years.
Arch. Sherif Elwishahy, PMP

Cost-reimbursable contracts
Cost plus fixed fee contracts (CPFF) The seller is reimbursed for all allowable costs for performing the contract work. The seller receives a fixed fee payment calculated as a percentage of the initial estimated project costs. Cost plus award fee contracts (CPAF) The seller is reimbursed for all legitimate costs. The majority of the fee is earned based on the satisfaction of certain broad subjective performance criteria. Cost plus incentive fee contracts (CPIF) The seller is reimbursed for all allowable costs. The seller receives a predetermined incentive fee based upon achieving certain performance objectives.
Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

Description

Arch. Sherif Elwishahy, PMP

Description

Arch. Sherif Elwishahy, PMP

Description

Arch. Sherif Elwishahy, PMP

Example Cost Plus Incentive Fee


Given the data in the table calculate the total cost of the contract and the sellers total fee.
Target Cost Target Fee $200k $50k

Target Price
Sharing Ratio

$250k
60/40 $190k $290K

Actual Cost Solution: Ceiling Price Seller saved on cost. Cost savings = 200 190 = $10k Incentive = 40% * 10 = $4k Sellers total fees = 50 + 4 = $54k Final price = cost + fees = 190 + 54= $244k

Arch. Sherif Elwishahy, PMP

1. Procurement Management Plan: A document that describes how the procurement process will be managed . It can include guidance to: Types of contracts to be used. Standardized procurement documents. Coordinating procurement with other project aspects. Risk Management issues. Managing multiple suppliers. Any constraints and assumptions that affects procurement. Identify prequalified sellers if any.
Arch. Sherif Elwishahy, PMP

2. Procurement Statement Of Work The part of contract that describes what the seller will do for the buyer. Approaches to develop the Scope of Work in the contract, such as: Performance. Design. Functionality.

Arch. Sherif Elwishahy, PMP

3. Make-or-buy decisions. 4. Procurement Documents: Used to solicit proposals from prospective sellers. Buyer and seller organizations ensure that nondisclosure agreements are approved and accepted before disclosing any project specific intellectual property information to the other party.

Arch. Sherif Elwishahy, PMP

5. Source Selection Criteria: Sometimes included as part of the procurement solicitation documents. May include: Overall or life-cycle cost. Technical Capability. Risk. Warranty. Financial Capacity. Production Capacity and interest. Business size and type. Past performance of sellers. Intellectual property rights.
Arch. Sherif Elwishahy, PMP

12.2 Conduct Procurement

Arch. Sherif Elwishahy, PMP

12.2 Conduct Procurement

Is the process of: Obtaining sellers responses. Selecting a seller. Award a contract. The overall process can be repeated. A short list of qualified sellers can be established based on preliminary proposal.

Arch. Sherif Elwishahy, PMP

12.2 Conduct Procurement

Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques


1. Bidder Conferences: It is a meeting during which companies considering

bidding on a project can ask a buyer any questions


and get clarification on any potential issue before creation of proposal.

Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques

2. Proposal Evaluation Techniques: A formal evaluation review process will be defined by the buyers procurement policies. It is usually done by a previously defined weighted criteria. The evaluation committee will make their selection for approval by management.

Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques


2. Proposal Evaluation Techniques:

Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques


3. Independent Estimates: Are used to help validate what a project should cost. These estimates could be created from within the company or by an outside source. Sellers offers are evaluated against this estimate for guidance.

4. Expert Judgment: Will often be required to assess the inputs to and outputs from this process. Can be used to evaluate offers or proposals made by sellers.
Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques

5. Advertisement : Placing advertisements in general-circulation publications, such as newspapers, or in specialty publications, such as journals. 6. Analytical Techniques.

Arch. Sherif Elwishahy, PMP

12.2.2 Conduct Procurement: Tools & Techniques

7. Procurement Negotiations : PMI considers this is a partnership contract rather than a supplier agreement. PMI requests a Win / Win situation from any contract. Involves clarification and mutual agreement on the structure and requirements of the contract, prior to the signing of the contract.

Arch. Sherif Elwishahy, PMP

12.3 Control Procurement

Arch. Sherif Elwishahy, PMP

12.3 Administer Procurement Is the process of: Managing procurement relationships. Monitoring contract performance. Making changes and corrections as needed.

many organizations treat contract administration as a


function separate from the project organization.

Arch. Sherif Elwishahy, PMP

12.3 Control Procurement

Arch. Sherif Elwishahy, PMP

12.3.2 Control Procurement: Tools & Techniques

1. Contract Change Control System: Defines the procedures for how the contract may be changed, is part of Integrated Change Control. The process for changing the contract includes: Paper work. Tracking system. Dispute resolution procedures. Procedures for getting the changes approved within the performing organization.

Arch. Sherif Elwishahy, PMP

12.3.2 Control Procurement: Tools & Techniques

2. Procurement Performance Reviews: Is a structured review of the sellers progress to deliver project scope and quality, within cost and on schedule, as compared to the contract. 3. Inspections and Audits: Are performed as the contract is executing. To ensure the appropriate work and quality of work is being completed per the terms of the contract. If we identify any weaknesses in the sellers work proper corrective actions must be taken.
Arch. Sherif Elwishahy, PMP

12.3.2 Control Procurement: Tools & Techniques

4. Performance Reporting: Provides management with information about how effectively the seller is achieving the contractual objectives. 5. Payment System: The system must include the appropriate reviews and approvals by the project management team.

Arch. Sherif Elwishahy, PMP

12.3.2 Control Procurement: Tools & Techniques

6. Claims Administration: They are those requested changes where the buyer and seller cannot agree on compensation for the change, or cannot agree that a change has even occurred. Can be invoked prior to or after contract closure. 7. Records Management System: Is part of the Project Management Information System. It is used to ensure that appropriate contract-related records are created, communicated, and archived.
Arch. Sherif Elwishahy, PMP

12.4 Close Procurement

Arch. Sherif Elwishahy, PMP

12.4 Close Procurement


Is the process of: Complete each project procurement. Verification that all work and deliverables were acceptable. Formal Acceptance should be achieved.

Arch. Sherif Elwishahy, PMP

12.4 Close Procurement

Arch. Sherif Elwishahy, PMP

12.4.2 Close Procurement: Tools & Techniques

1. Procurement Audits: Structured reviews of the procurement process, from procurement planning through contract administration Are used to determine success and failure of the procurement process for this project. Lessons can be applied to this project and others within the organization.

Arch. Sherif Elwishahy, PMP

12.4.2 Close Procurement: Tools & Techniques

2. Procurements Negotiations: The final equitable settlement of all outstanding issues, claims, and disputes by negotiation is a primary goal. Alternative Dispute Resolution [ADR] including mediation or arbitration may be explored. When all else fails, litigation in courts is the least desirable option.

3. Records Management System:

Arch. Sherif Elwishahy, PMP

Question No : 1
Bonnie is the project manager for the HGH Construction Project. She has contracted a portion of the project to the ABC Construction Company. Bonnie has offered a bonus to ABC if they complete their portion of the work by August 30. This is an example of which one of the following? A. Project requirement B. Project incentive C. Project goal D. Fixed price contract

Question No : 2
Sammy is the project manager of the DSA Project. He is considering proposals and contracts presented by vendors for a portion of the project work. Of the following, which contract is least dangerous to the DSA Project? A. Cost plus fixed fee B. Cost plus percentage of costs C. Cost plus incentive fee D. Fixed price

Question No : 3
Martha is the project manager of the MNB Project. She wants a vendor to offer her one price to do all of the detailed work. Martha is looking for which type of document? A. RFP B. RFI C. Proposal D. IFB

Question No : 4
Mary is the project manager of JHG Project. She has created a Statement of Work (SOW) for a vendor. For Marys SOW to be a legal contract, what must be included? A. Affidavit of agreement B. Signatures of both parties agreeing to SOW C. Signature of vendor D. Signature of Mary

Question No : 5
You are completing the closeout of a project to design a warehouse in Columbus, Ohio. The contract is a cost plus incentive fee contract. The target costs are $300,000, with a 10 percent target profit. However, the project came in at $275,000. The incentive split is 80/20. How much is the total contract cost?? A. $300,000 B. $275,000 C. $310,000 D. $330,000

Project Stakeholder Management

Project Stakeholder Management


Includes the processes required to identify the people, groups, or organizations that could impact or be impacted by the project.

Analyze stakeholder expectations and their


impact on the project. Focuses on continuous communication with stakeholders to understand their needs and expectations.

Arch. Sherif Elwishahy, PMP

13. Stakeholder Management


Initiating Planning
13.1

13.2

Executing

13.3

Monitoring

13.4

Arch. Sherif Elwishahy, PMP

13.1 Identify Stakeholders

Arch. Sherif Elwishahy, PMP

13.1 Identify Stakeholders


The process of: Identifying the people, groups, or organizations that could impact or be impacted by the project. Analyzing and documenting relevant information regarding their interests, involvement, influence, and potential impact on project success.

Arch. Sherif Elwishahy, PMP

13.1 Identify Stakeholders

Arch. Sherif Elwishahy, PMP

13.1.2 Identify Stakeholders: tools and techniques


1. Stakeholder Analysis: Stakeholder analysis follows the steps described below: Identify all potential project stakeholders and relevant information. Analyze the potential impact or support each stakeholder could generate. Assess how key stakeholders are likely to react or respond in various situations.

Arch. Sherif Elwishahy, PMP

13.1.2 Identify Stakeholders: tools and techniques

Power/Interest Grid with Stakeholders


Arch. Sherif Elwishahy, PMP

13.1.3 Identify Stakeholders: outputs


1. Stakeholder Register: This contains all details related to the identified stakeholders including, but not limited to: Identification information: Name, organizational position, location, role in the project, contact information. Assessment information: Major requirements, main expectations, potential influence in the project, phase in the life cycle with the most interest. Stakeholder classification: Internal/external, supporter/neutral/resistor, etc.
Arch. Sherif Elwishahy, PMP

13.2 Plan Stakeholder Management


Arch. Sherif Elwishahy, PMP

is the process of: Developing appropriate management strategies to effectively engage stakeholders throughout the project life cycle. Based on the analysis of their needs, interests, and potential impact on project success.

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

13.2.2 Plan Stakeholder management :

Tools & Techniques


3. Analytical Techniques The current engagement level of all stakeholders is compared to the planned engagement levels. The engagement level of the stakeholders is classified to: Unaware: Unaware of project and potential impacts. Resistant: Aware of project and potential impacts and resistant to change. Neutral: Aware of project yet neither supportive nor resistant. Supportive: Aware of project and potential impacts and supportive to change. Leading: Aware of project and potential impacts and actively engaged in ensuring the projects success.
Arch. Sherif Elwishahy, PMP

13.2.2 Plan Stakeholder management : Tools & Techniques

Stakeholders Engagement Assessment Matrix

Arch. Sherif Elwishahy, PMP

1. Stakeholder management plan: Desired and current engagement levels of key stakeholders. Scope and impact of change to stakeholders. Identified interrelationships between stakeholders. Stakeholder communication requirements. Information to be distributed to stakeholders. Reason for the distribution of that information and the expected impact to stakeholder engagement. Time frame and frequency for the distribution information. Method for updating and refining the stakeholder management plan as the project progresses and develops.
Arch. Sherif Elwishahy, PMP

13.3 Manage Stakeholder Engagement

Arch. Sherif Elwishahy, PMP

is the process of: Communicating and working with stakeholders to meet their needs/expectations. Address issues as they occur. Foster appropriate stakeholder engagement in project activities throughout the project life cycle.

Arch. Sherif Elwishahy, PMP

Arch. Sherif Elwishahy, PMP

1. Communication Methods. 2. Interpersonal Skills: The project manager applies interpersonal skills to manage stakeholders expectations. For example: Building trust, Resolving conflict, Active listening, and Overcoming resistance to change.
Arch. Sherif Elwishahy, PMP

3. Management Skills: The project manager applies management skills to coordinate and harmonize the group toward accomplishing the project objectives. For example: Facilitate consensus toward project objectives. Influence people to support the project. Negotiate agreements to satisfy the project needs. Modify organizational behavior to accept the project outcomes.
Arch. Sherif Elwishahy, PMP

13.4 Control Stakeholder Engagement


Arch. Sherif Elwishahy, PMP

13.4 Control Stakeholder Engagement Is the process of: Monitoring overall project stakeholder
relationships and adjusting strategies and plans for engaging stakeholders. The key benefit of this process is that it will maintain or increase the efficiency and effectiveness of stakeholder engagement activities.

Arch. Sherif Elwishahy, PMP

13.4 Control Stakeholder Engagement

Arch. Sherif Elwishahy, PMP

Question No : 1
Information in the stakeholder register should be: A. Accessible only to the project manager B. Available to the project manager and the PMO staff C. Available to all stakeholders and team members D. Shared with others at the discretion of the project manager

Question No : 2
The degree to which a particular stakeholder may be able to positively or negatively affect a project is his/her : A. Level of engagement B. Level of interest C. Level of commitment D. Level of influence

Question No : 3
The key objective of stakeholder management is A. Communication B. Coordination C. Satisfaction D. Relationships

Question No : 4
The stakeholder register is an input to which of the following processes: A. Plan risk management and collect requirements B. Perform integrated change control and plan communication management C. Plan quality management and perform quality assurance D. Identify risks and develop project charter

Question No : 5
A stakeholders belief about or mental picture of the future is a(n): A. Requirement B. Heuristic C. Expectation D. Constraint

Professional & Social Responsibility

Arch. Sherif Elwishahy, PMP

Professional & Social Responsibility


Project Management Professional Code Of Conduct: RESPONSIBILITY RESPECT FAIRNESS HONESTY

Arch. Sherif Elwishahy, PMP

Responsibility Ownership of Decisions and Actions.

Make decisions based on the best interest of the company and the team. Make sure the sponsor knows of any gaps in your qualifications before accepting the assignment. Do what you say you will do. Acknowledge your own errors. Respect confidentiality requirements. Uphold law. Report unethical behavior to management. Report violations of PMIs code of ethics when you have factual proof.
Arch. Sherif Elwishahy, PMP

Respect
The appropriate treatment of others

Maintain an attitude of mutual cooperation. Respect cultural differences. Do not gossip or say things that could damage another persons reputation. Engage in good faith negotiations. Respect others. Be direct in dealing with conflict. Do not use your power to influence others for your own personal benefit.

Arch. Sherif Elwishahy, PMP

Fairness
Being objective

Act impartially without favoritism. Continuously look for conflicts of interest and disclose them. Do not discriminate against others. Honor your duty of loyalty to those companies and organizations you are affiliated with. Do not use your position for personal or business gain.

Arch. Sherif Elwishahy, PMP

Honesty
Understanding the truth

Try to understand the truth. Be truthful in all communications. Make sure the information you are using or sending out is truthful. Work to create an environment where others tell the truth. Do not deceive others.

Arch. Sherif Elwishahy, PMP

Question No : 1
You are the project manager of the JKN Project. The project customer has requested that you inflate your cost estimates by 25 percent. He reports that his Management always reduces the cost of the estimates so this is the only method to get the monies needed to complete the project. Which of the following is the best response to this situation? A. Do as the customer asked to ensure the project requirements can be met by adding the increase as a contingency reserve. B. Do as the customer asked to ensure the project requirements can be met by adding the increase across each task. C. Do as the customer asked by creating an estimate for the customer management and another for the actual project implementation. D. Complete an accurate estimate of the project. In addition, create a risk assessment on why the project budget would be inadequate.

Question No : 2
You are the project manager for the BNH Project. This project takes place in a different county than where you are from. The project leader from this country presents a team of workers that are only from his family. You should do which one of the following? A. Reject the team leaders recommendations and assemble your own project team. B. Review the rsum and qualifications of the proposed project team before approving the team. C. Determine if the countrys traditions include hiring from the immediate family before hiring from outside the family. D. Replace the project leader with an impartial project leader.

Question No : 3
You are about to begin negotiations on a new project that is to take place in another country. Which of the following should be your guide on what business practices are allowed and discouraged? A. The project charter B. The project plan C. Company policies and procedures D. The PMP code of conduct

Question No : 4
You are the project manager of the PMH Project. You have been contracted to design the placement of several pieces of equipment. You have completed the project scope and are ready to pass the work over to the installer. The installer begins to schedule you to help with the installation of the equipment. You should: A. Help the installer place the equipment according to the design documents. B. Help the installer place the equipment as the customer sees fits. C. Refuse to help the installer since the project scope has been completed. D. Help the installer place the equipment, but insist that the quality control be governed by your design specifications.

Question No : 5
You are a project manager within an organization that completes technical projects for other entities. You have plans to leave your company within the next month to launch your own consulting businesswhich will compete with your current employer. Your company is currently working on a large proposal for a government contract that your new company could also benefit from. What should you do? A. Resign from your current job and bid against your employer to get the contract. B. Decline to participate due to a conflict of interest. C. Help your employer prepare the proposal. D. Inform your employer that you will be leaving their company within a month and it would be inappropriate for you to work on the current proposal.

You might also like