PROJECT MANAGEMENT Assignment No: 4 1. A project has the following characteristics: Sr.

No A B C D E F G H I J K L M N Preceding Activity A A B D D D B C,E G F,I,J K H,G M Expected completion time(Days) 5 2 6 12 10 9 5 9 1 2 3 9 7 8

Draw a network for the project. Define the critical path and find the project duration. Determine EST, LST, EFT, and LFT. 2. The following table lists the activities, duration and their sequence of operation. Draw the network for these activities, find the critical path and project duration. Determine EST,LST,EFT and LFT. Activity Duration(Days) Activity Duration(Days) 1-2 8 4-7 0 1-3 10 5-6 4 1-4 5 5-7 3 2-7 6 5-8 6 3-4 3 6-8 5 4-5 7 7-8 5 3. The following table lists the activities and their duration. Draw the network for the activities. Find the critical path and project duration. Determine EST, LST, EFT, and LFT. Determine Free float, Total float, Interfering float and Independent float. Activity 1-2 2-3 Duration(Days) 5 7 Activity 4-6 5-7 Duration(Days) 0 6

2-4 8 6-7 2 3-6 9 7-8 3 3-5 0 4-5 4 4. For the network shown below determine EST, LST, EFT, and LFT. Determine Free float, Total float, Interfering float and Independent float.

2 2 36 8

20 9 9

20 10

1 4 3 2

10 9 4 7

15 4 5 6

5. Listed below are the activities of a small construction project along with their durations in weeks. (i-j)Activity Duration 1-2 5 1-3 10 2-4 0 2-7 10 3-5 5 3-6 4 4-7 5 5-7 8 6-7 9 a)Draw a network and calculate total project duration. Show the critical path. b) Calculate EST, EFT, LST, LFT total floats, free floats for the activities. Also find independent float and Interferring float.