1. Following table lists the activities, their predecessors and three time estimates for a (25) construction project.

Activity A B C P Q R S T L M N i) ii) iii) iv)

Proceeding activity A A B C P B,Q R,S,M C L L

to tm tp (Weeks) (Weeks) (weeks) 2 4 6 6 8 12 5 6 9 3 6 9 4 7 10 8 10 14 5 7 9 2 3 5 4 5 6 3 5 7 4 6 8

Draw PERT network Determine the critical path and find the average expected project duration Determine the probability of completing the project with in 35 weeks What is the duration corresponding to 82% certainty of project timely completion

2. A-O-A network schedule for a project is as given below i) ii) iii) Draw A-O-A network Work out activity times and floats Determine the critical path and project duration

H 5 M 6 N 2 P

A 3 B 5 C 7

Q G 10 L 4 9

3. Draw a network on the basis of information given below and determine the critical path and project duration

Duration Acticvity (weeks) A 2 B 5 C 4 D 6 E 7 F 5 G 8 H 7

Preceding Relationship activity Constraints A FS A FS(+1) C,E SS(+4) , FF(+2) B FS E FS(-2) D FS F,G FF(+2) , FS(+1)