Market Analysis Start: Mon 3/3/14 ID: 1 Finish: Fri 3/28/14 Dur: 20 days Res:
Manufaturing Study Start: Mon 3/31/14 ID: 3 Finish: Mon 6/23/14Dur: 60 days Res:
Product Design Start: Mon 3/31/14 ID: 2 Finish: Mon 6/9/14 Dur: 50 days Res:
Product Design Selection Start: Tue 6/24/14 ID: 4 Finish: Tue 7/22/14 Dur: 20 days Res:
Product Trials Start: Wed 7/23/14 ID: 5 Finish: Tue 8/26/14 Dur: 25 days Res:
Product Launch Preperation Start: Thu 9/25/14 ID: 7 Finish: Wed 11/5/14Dur: 30 days Res:
Production Testing Start: Wed 7/23/14 ID: 6 Finish: Wed 9/24/14Dur: 45 days Res:
Celebrate Start: Thu 11/6/14 ID: 8 Finish: Thu 11/6/14 Dur: 1 day Res:
Page 1
Critical Noncritical
Page 2
Market Analysis Mon 3/3/14 Fri 3/28/14 Mon 3/3/14 Product Design Mon 3/31/14 Mon 6/9/14 Mon 4/14/14 Manufaturing Study Mon 3/31/14Mon 6/23/14 Mon 3/31/14 Product Design Selection Tue 6/24/14 Tue 7/22/14Tue 6/24/14 Product Trials Wed 7/23/14 Tue 8/26/14 Wed 8/20/14 Production Testing Wed 7/23/14Wed 9/24/14 Wed 7/23/14 Product Launch Preperation Thu 9/25/14Wed 11/5/14Thu 9/25/14 Celebrate Thu 11/6/14 Thu 11/6/14Thu 11/6/14
10 days
20 days
Project Summary Rolled Up Critical Rolled Up Critical Split Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only
Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress
ID
Project1
1 2 3 4 5 6 7 8
Task Mode
Task Name
Duration
Start
Market Analysis Product Design Manufaturing Study Product Design Selection Product Trials Production Testing Product Launch Preperation Celebrate
Mon 3/3/14 Mon 3/31/14 Mon 3/31/14 Tue 6/24/14 Wed 7/23/14 Wed 7/23/14 Thu 9/25/14 Thu 11/6/14
Page 1
Finish
Project1
Predecessors
Resource Names
Fri 3/28/14 Mon 6/9/14 Mon 6/23/14 Tue 7/22/14 Tue 8/26/14 Wed 9/24/14 Wed 11/5/14 Thu 11/6/14
1 1 2,3 4 4 5,6 7
Page 2