Professional Documents
Culture Documents
IS Project Management
Sc
ed
ule
pe
Sco
COST
Progressive Elaboration
Introduction
Integrates concepts of temporary and unique
As the product is unique it should be progressively elaborated.
The scope of the project should remain constant even as the
product scope is progressively elaborated.
Example:
Problem analysis
Requirements specification
Software design
Coding
Testing
Cost
Scope/quality
e
Ti m
Facilitating Function
Requirements Functional System Design Module Design Integration Acceptance Test Cutover
ACTIVITIES
Relative Effort
(PM)
(Total Staff)
(*) The requirements Document may or may not be part of the project
Program Pascasarjana, Universitas Gunadarma, Magister Management
IS Project Management
Introduction
Framework&Principles
Framework&Principles Rational Unified Process SPM Plan Suplement
(Royce Walker)
0.0
Analyse Define
DefineNew Write
WriteFunct. Negotiate
Interviews Analyse New Funct. Negotiate
Interviews Existing
ExistingSys. Sys. Function Specification Func.
Sys. Sys. Function Specification Func.Spec.
Spec.
When Do You
Stop?
Some person (or group for larger project) can take responsibility
for the task, or to accomplish the activities involved
You can get rough estimate of the effort (person days) needed to
perform the activity (or activities involved)
You can schedule the task
The task must be small and able to be completed
Analyses
Analyses
Existing
ExistingSys.
Sys.
Estimate (person-day) 2 2 1 1 3 2
Total 11 days
Mind-Mapping Approach
The person responsible for the plan (probably the project manager for a small to mid
sized project) then collate all the estimate and precedent, as follows
ACTIVITY EFFORT PRECEDENTS
Definition 20 -
Analysis 35 Definition
Design 25 Analysis
Program A (Control) 20 Design
Program B (Registration) 30 Design
Program C (Warehouse) 25 Design
System Test 10 Program A, B, C
Documentation 20 Design
Acceptance 5 System Test, Documentation
Training 10 Documentation
Operation
TOTAL
10
210
Acceptance
Network
Diagram
Note:
This example only the progranning had sub-component. If there are any sub-
component of any other major activity avaliable, they would also be listed
Program Pascasarjana, Universitas Gunadarma, Magister Management
IS Project Management
Introduction Framework&Principles Rational Unified Process SPM Plan Suplement
Network Diagram
Framework&Principles
PGMA
20
STRT DEF ANAL DES PGMB SYS TST ACC OPER END
0 20 35 25 30 10 5 10 0
PGMC
25
0 + 10 15
3
B C 21 + 5
5 day 6 day 21?
0 A 10 21 G 26
1 2 6 7
10 day 10 + 3 20? 5 day
D 13 + 4 17 + 3
F
3 day
3 day
13 E 17
4 5
4 day
15
3
B 15 C
5 day 6 day
0 A 10 21 G 26
1 2 10 ? 15 - 5 6 7
0 10 21 - 6 21
10 day 5 day 26
D
11 ? F
3 day
10 - 10 3 day 26 - 5
13 E 17
4 5
14 4 day 18
21 - 3
14 - 3
18 - 4
15
3
B 15 C
5 day 6 day
0 A 10 21 G 26
1 2 6 7
0 10 day 10 21 5 day 26
D
F
3 day
3 day
13 E 17
4 5
14 4 day 18
: Critical path