PreliminaryEstimate:HMainFourStoryBuilding
Client:Mr.AliShiyam
(TotalFllorarea68.00x4=272Sq.m)
Option(A)WithRCCstructure

BillNo
1
2
3
4
5
6
7
8
9
10
11
12

Description

Amount(Mvr)

Preliminaries
Groundworks
Concreteworks
Masonryandplastering
Doorsandwindows
FloorandwallTilling
PuttyandPainting
Ceiling
Hydraulicsanddrainage
Electricalinstallation
Metalwork
Roof
Grandtotal

TotalcostwithRCCconcretestructure
Rate per m2
Rate per ft2

MVR

60,000.00
75,000.00
1,400,000.00
375,000.00
210,000.00
200,000.00
150,000.00
95,000.00
170,000.00
185,000.00
50,000.00
80,000.00
3,050,000.00

MVR 3,050,000.00
MVR
MVR

11,214.00 /m2
1,042.19 /ft2

Option(B)WithPrefabricatedstructure
Totalcostwithprefabricatedstructure
Rate per m2
Rate per m2

MVR
MVR
US$

1,258,272.00
4,626.00 /m2
300.00 /m2

Option(C)WithPrefabricatedstructure
Totalcostwithprefabricatedstructure
Rate per m2
Rate per m2

Note: This cost ( Option -B & C)


Ground work/Foundation

MVR
MVR
US$

2,097,120.00
7,710.00 /m2
500.00 /m2

does not include the cost

for preliminaries and