1. It is being observed that in a project cost of testing is very high. After going in
detail, Test manager found that the testers are testing the software, which is not
left with many defects. How will you make sure that this is correct? Any three
ways? What are the disadvantages of Over Testing? (15 Points)
2. You find that the senior testers are making more mistakes then junior testers. You
found that the test plan was not achieving the 100% coverage. You need to
communicate this aspect to the senior tester. Also, you don't want to loose this
tester. How should one go about the constructive criticism. (15 Points)
3. Your customer does not have experience in writing Acceptance Test Plan. How
will you do that in coordination with customer? What will be the contents of
Acceptance Test Plan? (15 Points)
4. Differentiate Validation and Verification? (10 Points)
5. Explain give examples of the following black box techniques? Boundary Value
testing, Equivalence testing, Error Guessing. (15 Points)
8. What is objective of Unit Testing? Write below 3 types of unit testing methods.
(10 Points)