The Dhalipur Power Plant, commissioned in 1965, has an installed capacity of 51 MW from three Francis turbine units. It is a surface run-of-river power station located downstream of the Dhakrani Power Station, with a design head of 30.48 meters and a design discharge of 199.2 m³/s. The annual generation over the last five years has varied, with the highest generation recorded at 224.44 MU in 2008-09.

Uploaded by

Amit Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
80 views3 pages

Dhalipur

The Dhalipur Power Plant, commissioned in 1965, has an installed capacity of 51 MW from three Francis turbine units. It is a surface run-of-river power station located downstream of the Dhakrani Power Station, with a design head of 30.48 meters and a design discharge of 199.2 m³/s. The annual generation over the last five years has varied, with the highest generation recorded at 224.44 MU in 2008-09.

Uploaded by

Amit Kumar
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

8/26/2014 Welcome to Uttarakhand Jalvidyut Nigam Limited Dehradun...

http://www.uttarakhandjalvidyut.com/cms_ujvnl/dhalipur.php 1/3
Associated Sites | Site Map | Feedback | RTI | Contact Us | Home
>> Service Regulations (Draft) of UJVN ltd. >> Mom of Wholetime Directors Dated 09.06.2014 >> OM regarding Mobile Handset
<< back
Dhalipur Power Plant
Dhalipur Power Plant (3x17=51 MW)
The Power Station is located on the downstream of the Dhakrani Power Station at a distance of 4 km on the Power Channel which takes off
from the Dakpathar Barrage. The Power Station was commissioned in the year 1965. The surface Power Station comprises of 3 units of 17
MW each with Francis Turbine of 24,000 HP output. The water from the Tail Race of the Power Station joins Asan River at Asan Barrage.
Design head of the HEP is 30.48m.



SALIENT FEATURES

Installed Capacity : 3x17 MW
Type of Power Station : Surface Run-of-River
Commissioning Year : 1965
Water Conductor System : Power Channel
Water Outlet : TRC
Design Head : 30.48 m
Design Discharge : 199.2 m/s
Turbine Type : Francis
Turbine Output : 24000 HP
Generator Type : Umbrella
Generator Output : 19 MVA
Main Transformer : 20 MVA 11/132 kV
Switchyard : 132 kV
Design Energy : 192 MU

8/26/2014 Welcome to Uttarakhand Jalvidyut Nigam Limited Dehradun...
http://www.uttarakhandjalvidyut.com/cms_ujvnl/dhalipur.php 2/3
The annual generation from the HEP in the last five years is as follows:

Year 2006-07 2007-08 2008-09 2009-10 2010-11
Generation(MU) 214.28 210.70 224.44 160.15 210.84

The Plant Availability of the HEP for the last five years is as follows:

Year 2006-07 2007-08 2008-09 2009-10 2010-11
Generation(MU) 77.88 78.17 83.81 83.14 86.77

RMU Status of HEPs
8/26/2014 Welcome to Uttarakhand Jalvidyut Nigam Limited Dehradun...
http://www.uttarakhandjalvidyut.com/cms_ujvnl/dhalipur.php 3/3


Privacy Policy | Enquiry | Associated Sites | Site Map | Feedback | RTI | Contact Us | Home | Uttarakhandjalvidyut.com Webmail | UJVNL.com Webmail
Copyright UJVNL

You might also like