Professional Documents
Culture Documents
Geotechnical Report 01 PDF
Geotechnical Report 01 PDF
= Ultimate bearing capacity equation for shallow strip footings, (kN/m
2
) (lb/ft
2
)
Q
u
= 1.3 c N
c
+ D N
q
+ 0.4 B N
= Ultimate bearing capacity equation for shallow square footings, (kN/m
2
) (lb/ft
2
)
Q
u
= 1.3 c N
c
+ D N
q
+ 0.3 B N
= Ultimate bearing capacity equation for shallow circular footings, (kN/m
2
) (lb/ft
2
)
Where:
c = Cohesion of soil (lb/ft
2
),
= effective unit weight of soil (lb/ft
3
)
D = depth of footing (ft)
B = width of footing)(ft),
N
c
=cot(N
q
1)
N
q
=e
2
(3
/4-/2)tan
/ [2 cos
2
(45+/2)],
9 | P a g e
N
=(1/2) tan(k
p
/cos
2
- 1)
e = Napier's constant = 2.718
k
p
= passive pressure coefficient
= angle of internal friction (degrees).
Taking into consideration the above described criteria the net allowable bearing pressure has
been calculated at 3 ft (1 m) depth below the existing ground surface. The recommended
allowable bearing pressure values in general are as follows:
Depth of
Foundation
Type of
Foundation
Least lateral
Dimension
of
Foundation
Net
Allowable
Bearing
Pressure
3 ft
Isolated
Square
5.25 ft 6,564 Ib/ft
2
The actual net bearing pressure value for any particular Isolated Square foundation can be
seen from Table 03.
8. The Earthwork
8.1. Clearing, Grubbing, Leveling And Grading
Prior to any construction activity at the site, it must be cleared of all debris, and surface
vegetation. This can be carried out by graders/dozers. For leveling and grading, stakes should
be installed on a grid marked by Surveying Crews. The required levels to be attained through
cut or fill at the grid points must also be identified.
The leveling and grading can be carried out by normal earth moving machine. As
predominantly sandy soils will be encountered in excavation throughout the project area, no
special problems are anticipated in excavating and moving these soils with excavators,
scrappers and dozers.
8.2. Excavations
The excavations for construction of foundations, other substructures or for trenches for utility
lines can be made by using conventional earth moving machinery including scrappers, dozers
and trenchers etc. All the excavations should be properly sloped or supported to avoid any
stability failure as well as movement in the adjacent structures.
10 | P a g e
After reaching the designed foundation level and before placing the foundation, it is
recommended that the soil should be well compacted by using an appropriate roller or
equivalent.
8.3. Fill Materials
The on-site materials after removing about 1.5 ft. of topsoil can be used for general backfilling
at the site. However preferably the backfill material should be granular and the quantities of
fines should limit to the recommended values.
9. Constructional Aspects
We recommend the following measures for long-term stability of the structures.
Well compact the bottom of the excavation using appropriate compaction equipment (such
as tamping plates) before placing the foundations.
A pad of at least 6 inches of 1:4:8 PCC (well compacted) should be placed on the prepared
ground before placing foundations.
Engineering fill (A-1-a, A-1-b or A-3) should be used as a back fill material. The commonly
available back fill material is A-3 (sand).
Plinth protection slab sloping away from the buildings should be provided around the
structure to reduce ingress of water to foundation soils.
Proper surface drainage should be provided in the project area and the area should be
graded to keep the surface runoff away from the structure. The ingress of water from any
source should be avoided.
10. Inspection And Monitoring
It is necessary that all the geotechnical aspects of foundation construction and earthwork be
monitored by competent construction supervision staff including qualified and experienced
engineers. For this purpose a comprehensive inspection and monitoring program should be
prepared. The program must specifically address the following aspects.
1. Inspection of all stripping work to ensure that the undesirable topsoil containing refuse
and organic material has been adequately removed.
2. Making sure that all the stripped off material and other unwanted materials from the
site are disposed off in designated disposal area without any environmental hazard.
3. Identification of in-situ conditions of the subsurface during foundation excavation and
preparation of sub grades, so that over excavation is avoided. Senior engineer should
ensure that the foundation has been placed on well compacted soil.
11 | P a g e
4. Identify the areas on the excavated slopes requiring protection, and provide suitable
remedial measures, where required to ensure stability of slopes during construction.
5. Special precautions should be observed during excavation and proper protection
should be provided to neighboring structures. Full time monitoring by an experienced
engineer should be ensured.
11. Summary Of Recommendations
11.1. Type Of Foundation
Shallow foundation Isolated Square type can be used; however foundations should be tied to
reduce chances of differential settlement.
11.2. Minimum Depth Of Foundation
Minimum depth of foundation should be 3 ft below the existing ground level on well
compacted soil.
11.3. Bearing Pressure
The recommended allowable bearing pressure values in general are as follows:
Depth of Foundation Type of Foundation
Least lateral
Dimension of
Foundation
Net Allowable
Bearing Pressure
3 ft Isolated Square 5.25 ft 6,564 Ib/ft
2
12. General Comments
Foundation should be placed on well compacted soil; a senior qualified engineer should
inspect the site before placing foundations and should ensure that the foundation has been
placed on well compacted soil.
Sulphate Resistance cement should be used for the foundation works.
Special precautions should be observed during excavation and proper protection
should be provided to neighboring structures. Full time monitoring by an experienced
engineer should be ensured.
12 | P a g e
13. APPENDIX - A
Tables
Bore Hole Logs
13 | P a g e
TABLE-1
Empirical Values For , Q
u
, D
r
and Unit Weight Of Soils Based on The SPT
Table-2
Soil Parameters Used In The Analysis Of Settlement and Bearing Pressure
DESCRIPTION OF PARAMETER VALUE OF PARAMETER
Bulk unit weight 120 Ib/ft
3
Corrected average N-value 25 blows/1 ft
Angle of internal friction of top soil 33
o
Cohesion , c 0
14 | P a g e
Table-3
Calculation of Foundation Width
Given
bearing pressure from building = 180,000 lbs/ft
2
unit weight of soil, = 120 lbs/ft
3
Cohesion, c = 0
angle of Internal Friction, = 33 degrees
footing depth, D = 3 ft
Solution
Try a width, B = 5.25 foot
Use a factor of safety, F.S = 3
Determine bearing capacity factors N
, N
c
and N
q
. See typical bearing capacity factors relating
to the soils' angle of internal friction.
N
g
= 31
N
q
= 33
N
c
= 49
Solve for ultimate bearing capacity,
Q
u
= c N
c
+ D N
q
+ 0.4 B N