Professional Documents
Culture Documents
RATIO
QUANTITY
TOTAL COST
COST OF CEMENT(PKR)
450.00
1.00
30.00
13,500.00
28.00
1.00
37.50
1,050.00
32.00
2.00
75.00
2,400.00
SUM OF RATIO
4.00
16,950.00
15.00
100.00
SUM OF MATERIAL+LABOUR
1,500.00
18,450.00
TOOLS,PLANT
4.00%
738.00
WATER
1.50%
276.75
WASTAGE
5.00%
922.50
SUM OF EQUIPMENT+MATERIAL+LABOUR
OVER HEAD (5%)
20,387.25
5.00%
21,406.61
6.00%
1,019.36
1,284.40
22,691.01
10.00%
2,269.10
24,960.11
250
PROJECT OF:
RATE ANALYSE FOR FORMWORK(WOODEN)
FOUNDATION
%AGE
FOUNDATION SIZE (5'X5'X1')
NAILS,PATTI,ETC(10%)
10.00%
5.00%
B(FT)
H(FT)
QUANTITY
RATE
TOTAL COST
4.00
5.00
5.00
1.00
20.00
20.00
400.00
40.00
22.00
462.00
6.00%
L(FT)
440.00
NOS
27.72
489.72
10.00%
48.97
538.69
22
PROJECT OF:
RATE ANALYSE FOR FORMWORK(WOODEN)
COLUMN
%AGE
COLUMN SIZE (0'-8"X1'-6")
NAILS,PATTI,ETC
10.00%
5.00%
B(FT)
H(FT)
QUANTITY
RATE
TOTAL COST
2.00
0.67
1.50
1.00
3.00
20.00
60.00
6.00
3.30
69.30
6.00%
L(FT)
66.00
SIDE
4.16
73.46
10.00%
7.35
80.80
80.76
PROJECT OF:
RATE ANALYSE FOR FORMWORK(WOODEN)
BEAM
%AGE
BEAM SIZE (0'-8"X1'-6")
NAILS,PATTI,ETC
10.00%
5.00%
B(FT)
H(FT)
QUANTITY
RATE
TOTAL COST
2.00
0.67
1.50
1.00
4.33
20.00
86.68
8.67
4.77
100.12
6.00%
L(FT)
95.35
SIDE
6.01
106.12
10.00%
10.61
116.73
116.68
PROJECT OF:
RATE ANALYSE FOR FORMWORK(WOODEN)
ROOF SLAB
10.00%
5.00%
B(FT)
H(FT)
QUANTITY
RATE
TOTAL COST
1.00
1.00
1.00
0.50
1.00
20.00
20.00
2.00
1.10
23.10
6.00%
L(FT)
22.00
SIDE
1.39
24.49
10.00%
2.45
26.93
53.87
PROJECT OF:
RATE ANALYSE FOR CONRETE WITH FORMWORK(WOODEN)
FOUNDATION
COLUMN
(1:4:8)
F.WORK CONCRETE
F.WORK
COST
COST
TOTAL COST COST
21.55
134
155.55
80.76
(1:3:6)
21.55
149
178
170.55
80.76
204
199.55
80.76
250
214.76
116.68
149
178
225.55
80.76
204
229.76
116.68
80.76
250
(1:4:8)
CONCRET TOTAL
E COST
COST
134
250.68
F.WORK
COST
53.87
149
258.76
116.68
178
265.68
53.87
116.68
204
294.68
53.87
116.68
250
187.87
149
202.87
178
231.87
(1:1.5:3)
320.68
53.87
(1:1:2)
330.76
134
(1:2:4)
(1:1.5:3)
284.76
(1:4:8)
CONCRET TOTAL
E COST
COST
(1:3:6)
(1:2:4)
(1:1:2)
271.55
ROOF SLAB
(1:3:6)
(1:1.5:3)
(1:1:2)
21.55
134
F.WORK
COST
(1:2:4)
(1:1.5:3)
21.55
(1:4:8)
CONCRET TOTAL
E COST
COST
(1:3:6)
(1:2:4)
21.55
204
257.87
(1:1:2)
366.68
53.87
250
303.87
PROJECT OF:
RATE ANALYSE FOR FORMWORK(STEEL)
FOUNDATION
%AGE
FOUNDATION SIZE (5'X5'X1')
MISCELINIOUS
10.00%
5.00%
6.00%
10.00%
SIDE
L(FT)
B(FT)
H(FT)
QUANTITY
RATE
4.00
5.00
5.00
1.00
20.00
60.00
PROJECT OF:
RATE ANALYSE FOR FORMWORK(STEEL)
COLUMN
10.00%
5.00%
6.00%
10.00%
SIDE
L(FT)
B(FT)
H(FT)
QUANTITY
RATE
2.00
0.67
1.50
1.00
3.00
60.00
PROJECT OF:
RATE ANALYSE FOR FORMWORK(STEEL)
BEAM
10.00%
5.00%
6.00%
10.00%
SIDE
L(FT)
B(FT)
H(FT)
QUANTITY
RATE
2.00
0.67
1.50
1.00
4.33
60.00
PROJECT OF:
RATE ANALYSE FOR FORMWORK(STEEL)
ROOF SLAB
10.00%
5.00%
6.00%
10.00%
SIDE
L(FT)
B(FT)
H(FT)
QUANTITY
RATE
1.00
1.00
1.00
0.50
1.00
60.00
TOTAL COST
1,200.00
120.00
1,320.00
66.00
1,386.00
83.16
1,469.16
146.92
1,616.08
65
TOTAL COST
180.00
18.00
198.00
9.90
207.90
12.47
220.37
22.04
242.41
242.29
TOTAL COST
260.04
26.00
286.04
14.30
300.35
18.02
318.37
31.84
350.20
350.03
TOTAL COST
60.00
6.00
66.00
3.30
69.30
4.16
73.46
7.3458
80.80
162
PROJECT OF:
RATE ANALYSE FOR CONRETE WITH FORMWORK(STEEL)
FOUNDATION
COLUMN
(1:4:8)
CONCRET TOTAL
E COST
COST
F.WORK
COST
65
134
F.WORK
COST
199
242
(1:3:6)
65
149
178
214
242
204
243
242
250
376
350
149
178
269
242
204
391
350
242
250
(1:4:8)
CONCRET TOTAL
E COST
COST
134
F.WORK
COST
484
162
149
420
350
178
499
162
350
204
528
162
350
250
296
149
311
178
340
(1:1.5:3)
554
162
(1:1:2)
492
134
(1:2:4)
(1:1.5:3)
446
(1:4:8)
CONCRET TOTAL
E COST
COST
(1:3:6)
(1:2:4)
(1:1:2)
315
ROOF SLAB
(1:3:6)
(1:1.5:3)
(1:1:2)
65
134
F.WORK
COST
(1:2:4)
(1:1.5:3)
65
(1:4:8)
CONCRET TOTAL
E COST
COST
(1:3:6)
(1:2:4)
65
204
366
(1:1:2)
600
162
250
412
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT
RATE
THICK(3/4")
COST OF CEMENT(PKR)
450.00
0.06
30.00
SUM OF RATIO
THC(1/2")
0.042
RATIO
QUANTITY
TOTAL COST
1.00
1.40
630.00
4.00
7.00
210.00
5.00
840.00
10.00
SUM OF MATERIAL+LABOUR
100.00
1,000.00
1,840.00
TOOLS,PLANT (2%)
3.00%
55.20
WATER (2%)
2.00%
36.80
WASTAGE
5.00%
92.00
SUM OF EQUIPMENT+MATERIAL+LABOUR
OVER HEAD (5%)
2,024.00
5.00%
2,125.20
6.00%
101.20
127.51
2,252.71
10.00%
225.27
2,477.98
25
PROJECT OF:
RATE ANALYSE OF PLASTER PER SFT
THICNESS
RATIO
(1:2)
(1:3)
(1:4)
(1:5)
(1:6)
(1:7)
1/2"
25.00
23.00
22.00
21.00
20.00
20.00
3/4"
30.00
27.00
25.00
23.00
22.00
22.00
1"
35.00
30.00
27.00
26.00
24.00
24.00
1-1/2"
44.00
37.00
33.00
30.00
28.00
27.00
PROJECT OF:
RATE ANALYSE OF STEEL REINFORCEMENT(1000 KG)
COST OF STEEL
RATE
TON/KG
TOTAL COST
78,000.00
1.00
78,000.00
10.00%
7,800.00
CARTAGE
550.00
PER TON
550.00
BINDING WIRE
99.00
10.00
990.00
87,340.00
3,500.00
PER TON
3,500.00
90,840.00
5.00%
4,542.00
95,382.00
5.00%
4,769.10
6.00%
5,722.92
105,874.02
10.00%
10,587.40
116,461.42
116
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT (4"THC)
RATE
NO
THINKNESS
SOLID MATERIALS
THICK(4")
0.33
100.00
DRY MATERIALS
THC(6")
0.500
THC(8")
0.667
(THC 12")
RATIO
RATIO
QTY(CFT)
1.00
1.00
33.33
3.00
4.00
51.67
1.00
6.00
SUM OF RATIO
10.00
5.00
85.00%
43.92
15.00%
7.75
460.00
3.51
460.00
1.24
28.00
13.18
28.00
6.20
34.00
26.35
5.00
165.00
850.00
1.00
PROJECT OF:
HELPER & CODE PER DAY (2 No)
450.00
TOTAL COST
TOOLS AND SCAFFOLDING
4.00%
5.00%
5.00%
6.00%
10.00%
2.00
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT (6"THC)
RATE
SOLID MATERIALS
NO
100.00
THICK(4")
0.33
DRY MATERIALS
THC(6")
0.500
THC(8")
0.667
(THC 12")
1.00
RATIO
RATIO
QTY(CFT)
1.00
1.00
50.00
3.00
4.00
77.50
6.00
SUM OF RATIO
10.00
5.00
85.00%
65.88
15.00%
11.63
460.00
5.27
460.00
1.86
28.00
19.76
28.00
9.30
34.00
39.53
6.00
165.00
700.00
1.25
400.00
2.50
PROJECT OF:
TOTAL COST
TOOLS AND SCAFFOLDING
2.00%
5.00%
5.00%
6.00%
10.00%
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT (8"THC)
RATE
SOLID MATERIALS
NO
100.00
THICK(4")
0.33
DRY MATERIALS
THC(6")
0.500
THC(8")
0.667
(THC 12")
1.00
RATIO
RATIO
QTY(CFT)
1.00
1.00
66.67
3.00
4.00
103.33
6.00
SUM OF RATIO
10.00
5.00
85.00%
87.83
15.00%
15.50
460.00
7.03
460.00
2.48
28.00
26.35
28.00
12.40
34.00
52.70
7.00
165.00
700.00
1.50
400.00
3.00
PROJECT OF:
TOTAL COST
TOOLS AND SCAFFOLDING
2.00%
5.00%
5.00%
6.00%
10.00%
TOTAL COST
1,616.13
570.40
2,186.53
368.90
173.60
542.50
895.90
825.00
850.00
900.00
6,200
248.00
6,447.93
322.40
6,770.33
338.52
7,108.84
426.53
7,535.37
753.54
8,288.91
83
TOTAL COST
2,424.20
855.60
3,279.80
553.35
260.40
813.75
1,343.85
990.00
875.00
1,000.00
8,302
166.05
8,468.45
423.4224
8,891.87
444.59
9,336.46
560.19
9,896.65
989.67
10,886.32
109
TOTAL COST
3,232.27
1,140.80
4,373.07
737.80
347.20
1,085.00
1,791.80
1,155.00
1,050.00
1,200.00
10,655
213.10
10,867.96
543.3982
11,411.36
570.57
11,981.93
718.92
12,700.85
1,270.08
13,970.93
140
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT(FLOORING)
RATE
THCK
RATIO
QTY
TOTAL COST
120.00
2.50
1.00
100.00
12,000.00
WASTAGE
10.00%
2.00
1,200.00
L.S
4.00
200.00
7.00
DRY MATERIAL
100.00
32.29
COST OF CEMENT
460.00
3.69
1,697.62
28.00
9.23
258.33
34.00
18.45
627.38
60.00
100.00
6,000.00
CHEMICAL POLISHING
35.00
100.00
3,500.00
TOTAL COST
MISCELINIOUS
25,483.33
5.00%
26,757.50
5.00%
1,337.88
28,095.38
6.00%
1,274.17
1,685.72
29,781.10
10.00%
2,978.11
32,759.21
328
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT(FLOORING)(CERAMIC TILE)
RATE
THCK
RATIO
QTY
TOTAL COST
80.00
2.50
1.00
100.00
8,000.00
10.00%
2.00
800.00
L.S
4.00
200.00
SUM OF RATIO
7.00
DRY MATERIAL
100.00
32.29
COST OF CEMENT
460.00
3.69
1,697.62
28.00
9.23
258.33
34.00
18.45
627.38
60.00
100.00
6,000.00
TOTAL COST
MISCELINIOUS
17,583.33
5.00%
18,462.50
5.00%
923.13
19,385.63
6.00%
879.17
1,163.14
20,548.76
10.00%
2054.88
22,603.64
226
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT(ON WALLS)(CERAMIC TILE)
RATE
THCK
RATIO
QTY
TOTAL COST
80.00
0.75
1.00
100.00
8,000.00
10.00%
4.00
800.00
L.S
SUM OF RATIO
200.00
5.00
DRY MATERIAL
100.00
9.69
COST OF CEMENT
460.00
1.55
713.00
28.00
7.75
217.00
34.00
0.00
0.00
60.00
100.00
6,000.00
TOTAL COST
MISCELINIOUS
15,930.00
5.00%
16,726.50
5.00%
836.33
17,562.83
6.00%
796.50
1,053.77
18,616.59
10.00%
1861.65945
20,478.25
205
PROJECT OF:
RATE ANALYSE BASED ON 100 SFT(FLORING)
RATE
THCK
RATIO
QTY
TOTAL COST
50.00
0.75
1.00
100.00
5,000.00
10.00%
2.00
500.00
L.S
4.00
200.00
SUM OF RATIO
7.00
DRY MATERIAL
100.00
9.69
COST OF CEMENT
460.00
1.11
509.29
28.00
2.77
77.50
34.00
5.54
188.21
60.00
100.00
6,000.00
CHEMICAL POLISHING
35.00
100.00
3,500.00
TOTAL COST
MISCELINIOUS
15,975.00
5.00%
16,773.75
5.00%
838.69
17,612.44
6.00%
798.75
1,056.75
18,669.18
10.00%
1866.92
20,536.10
205
PROJECT OF:
P/F FLUSH DOOR SHUTTER SOLID BOTH SIDE COMMERCIAL PLY
DOOR (3'-0"X7'-0")
RATE
H(FT)
B(FT)
QTY
TOTAL COST
COST OF SHUTTER
120.00
7.00
3.50
24.50
2,940.00
LIPPING
15.00
21.00
315.00
ARCHITRAVI
30.00
35.00
1,050.00
HINGES
50.00
4.00
200.00
HANDLES
75.00
2.00
150.00
SLIDING BOLTS
75.00
2.00
150.00
DOOR STOPPER
150.00
1.00
150.00
LOCK/LATCH
500.00
1.00
500.00
LABOUR
50.00
24.50
1,225.00
TOTAL COST
6,680.00
MISCELLINIOUS
5.00%
334.00
OVER HEAD
5.00%
334.00
7,348.00
6.00%
440.88
7,788.88
10.00%
778.89
8,567.77
350
PROJECT OF:
P/F DEODAR WOOD DOOR FRAME 2"X7"
FOR DOOR 3'-0"X7'-0"
RATE
H(FT
B(FT)
WASTAGE
H(FT)
B(FT)
QTY
TOTAL COST
3,500.00
7.00
3.00
135.00%
0.75
0.17
2.87
10,040.63
35.00
17.00
595.00
15.00
17.00
255.00
HOLDFAST,NAILS,TERMITE TREATMENT
20.00
17.00
340.00
TOTAL COST
OVER HEAD
11,230.63
5.00%
11,792.16
6.00%
561.53
707.53
12,499.69
10.00%
1,249.97
13,749.65
808.80
PROJECT OF:
P/F DEODAR WOOD DOOR FRAME 2"X7"
H(FT)
B(FT)
THC
THC
7.00
2.50
396.00
0.42
0.17
7.00
3.00
7.00
14,972.43
369.00
487.42
16,035.14
3.50
350.00
487.42
17,104.85
7.00
2.50
396.00
648.11
17,623.82
7.00
3.00
369.00
648.11
18,766.87
7.00
3.50
350.00
648.11
19,916.93
7.00
2.50
396.00
808.80
20,275.20
7.00
3.00
369.00
808.80
21,498.60
7.00
3.50
350.00
808.80
22,729.00
0.58
0.75
0.17
0.17