Professional Documents
Culture Documents
1 CEMENT - OPC
Basic cost of material 211.00
Add - VAT 12.5 % 237.38
Add - Octroi 5 % 249.24
Add - Wastage @ 1 %
Site handling
Total cost of cement per bag
Total cost of cement per M TON
2 CEMENT - SRC
Basic cost of material 242.65
Add - VAT 12.5 % 272.98
Add - Octroi 5 % 286.63
Add - Wastage @ 1 %
Site handling
Total cost of cement per bag
Total cost of cement per M TON
5 Structural Steel
Basic Cost of struct-steel delivered at site 30500.00
Add - VAT 4 % 31720.00
Add - Octroi 2.5 % 32513.00
Add - Wastage @ 3 %
Unloading charges
Total cost of ms-steel
Less - Credit for Scrap 1MT give 30Kg @ Rs.15/kg
Net cost of Structural-Steel
Add cost of Fabrication
Total cost of St-steel including Fabrication
9 Fly Ash
Basic cost of material delivered at site
Add - VAT 12.5 %
Add - Octroi 2.5 %
Site Handling
Total cost of Fly Ash
10 HT Strand
Basic cost of material delivered at site 41000.00
Add - Excise 8.24 % 44378.40
Add - VAT 4 % 46153.54
Transportation Charges 800.00
Total Cost = 46953.54
Add - Octroi 4.5 % 49066.45
Add - Wastage @ 5 %
Unloading & site handling
Less - Credit for Scrap 50Kg @ Rs.10/kg
Total cost of HT Strand
9 ADMIXTURE
Basic cost of material delivered at site
Add - VAT 12.5 %
Add - Octroi 4 %
Site Handling
Total cost of Fly Ash
10 FORM WORK
A PILE CAP& FOUNDATION (BOQ item No. Part B- 1.6)
Total BOQ Quantity
Total shuttering Required (1 Sqm/Cum.)
Shuttering set required ( 30 x 2 Nos )
Shuttering set required ( 45 x 2 Nos )
Total shuttering Required
Weight of shuttering per sqm
Total Structural steel required ( 302 x 50 )
Cost of shuttering
Less - Scrap cost @ Rs 15 / kg
Net cost of shuttering
Cost per sqm ( 215305.35 / 4070 )
B BOX GIRDER & GIRDERS ( BOQ item no. Part C - 1.1 a, b & c)
Total concrete quantity
Number of Box Girder
Consider shuttering required per cum
approx concrete per girder
Consider shuttering required including
supporting arrangement
Total st. steel required @ 160 kg/sqm
say
Cost of shuttering & supporting
( 560 MT x Rs. 38158)
Less - Scrap cost @ Rs.15000/MT for 640 MT
Net cost of shuttering
Cost of shuttering per cum of Concrete
Labour Cost of fixing shuttering
Consumbale like nut, bolt, oil etc ( 4.25 Sqm x Rs 15 )
Packing timber, Ply, Thermocoal ( 4.25 Sqm x Rs 10 )
Total cost of shuttering per cum of concrete
SAY
C PIER & PIER CAP ( BOQ item no. Part B - 2.1 & 2.3)
Total concrete quantity ( 1530 + 780 )
Consider shuttering required per set (3 Sqm/Cum)
Consider shuttering required including
supporting arrangement
Consider shuttering required per cum
Total st. steel required @ 125kg/sqm
( 85 x 2 x 125 )
Total Structural Reqd. including supportings
Cost of shuttering & supporting @ Rs 43707.38 / MT
Less - Scrap cost @ Rs 15000 / MT
Net cost of shuttering
11 Aggregate 40 mm
Basic cost of material delivered at site incl. taxes
Add - Wastage @ 2 %
Total cost of Aggregate
13 Pile boring
Total Boring length
Labour cost for boring 04 Labours per day for 1 year
@ Rs 200 for 12 hrs (Taking 02 shifts) (2x4x350x200)
Spikes 1 Nos/meter @ Rs 400/spikes
Total required is ( 5700 Nos x 400)
Spike holder 0.20 Nos/meter @ Rs 1000/holder
Total required is ( 5700 Nos x 0.20Nos)
Other consumable like wirerope clamps etc.
Total cost of boring
Cost/RM
PILE CONCRETE
Considering length of pile
Concrete Qty. of per Rm pile
Concrete Qty in one pile ( 1m extra)
Cost of concete M:35
Cost of concete in one pile
Labour cost of concreting per pile@ Rs.100/cum
Pile Head breaking
Total
Concrete cost per RM
Muck Removal
Volume per meter
Cost of removel per cum
Cost per meter of pile
Consider 2 nos trimme of 12 M each
Consider cost of 2 trimmes Rs.2.0L
Cost of trimme per RM of Pile
23 2.0 - SUBSTRUCTURE
M35 Concrete in Pier, Pier Cap
Cost of Grade M-35
Labour Charges (Concreting)
Curing Cost
Repair & finishing
Shuttering Cost (Labour + Material)
Extra charge for F3 finish
Total Cost
27 PTFE Bearing
Long. Guided 2100 KN.
Free POT 2100 KN.
Fixed POT 4200 KN.
Trans. Guided 4200 KN.
Long. Guided 4200 KN.
Free POT 4200 KN.
29 BOX GIRDER & GIRDERS ( BOQ item no. Part C - 1.1 a, b & c)
Total concrete quantity
Number of Box Girder
Consider shuttering required per cum
approx concrete per girder
Consider shuttering required including
supporting arrangement
Total st. steel required @ 160 kg/sqm
Total Cost =
31 Pre-Stressing Works
Pre tension strands of 15.4/12.7 mm dia
Basic Cost of H.T. Strands delivered at site
Add - Exise 8.24 %
Add - VAT 4 %
Add - Transportation Cost
Total Cost =
Add - Octroi 4.5 %
Add - Extra Consumption for Jack Fixing.
(non-payable item) @ 7%
Add - Wastage @ 1.5 %
Unloading charges
Cost of site handling
Total cost of H.T. Strands
Less - Credit for Scrap 1MT give 15Kg @ Rs.10/kg
Net cost of H.T. Strands
Length of Sheathing Required of HT (1000 kg/1.08x12)
Cost of HDPE sheathing per MT of HT wire
HDPE Shaething @ Rs 100 Rs
End Coupler 6nos. @ Rs 30 + 4% Rs
End Set (Guide Cone, Bearing Plates,
Rs
Wedges) 6 Sets @ Rs 2600 + 4%
Grout vent 3nos @ Rs 80 + 4% Rs
Snapfit Coupler 1 Nos. @ Rs 35 + 4% Rs
Cost of HDPE sheathingper MT of HT wire
Cost of stressing,Jacks,supervision
Labour cost for threading, stressing etc.
Consumable like tapes, cutting wheel etc.
Sheathing pipe fixing @ Rs. 25 / RM
Cement ( 77.16 x 6.60 Kg ) for grouting 509.26
Intraplas NN 1% of cement weigh 5.09
Total
c Facia Panel
For Design, drawings, galvanised strips,
supervision except murrum
filling and compaction cost
Cost of Concrete (M40)
Cost of Reinforcement Steel
Coal Tar Epoxy Paint
Labour Charges (For Concreting and Shuttering)
Cost of Curing
Cost of Repair and Finishing
Cost For Transportation (Casting yard to
Site)
Labour Cost For Erection
e Crash Parapet
RMC M35
Labour Charges (For Concreting )
Cost of Curing
Cost For Finishing
Cost for Shuttering. (material)
Cost for Shuttering. (labour)
Total Cost =
42 EARTHWORK
a Excavation for road work
Excavation in Soil (By JCB)
Cost of Excavation
Curting disposal (800/ 4)
Compaction watering & Dressing
Total Cost =
b Earthwork in embankment
Murrum
L/C incl. dressing
Watering compaction and testing
c Filter media
Cost of Rubble
Breaking Charge
Labour Charges
43 Road Works
a GSB 200 thick
Material incl. L/C
b WBM 2 x 115 mm
Material incl. L/C
c WBM 3 x 75 mm
Material incl. L/C
d BBM 75 mm thick
Material incl. L/C
e BM 50 mm th.
Material incl. L/C
44 C.C. Road
Regarding Ghodbbunder Road in project area
with
rigid pavement
a Subgrade 500 thick (murrum)
Murrum
L/C
Watering, dressing & compaction
h Manholes
Agency Rate
Rs. 1.60 Kg
Rs. 1.80 Kg
Rs. 1.85 Kg
Rs. 0.04 Kg
Rs. 1.88 Kg
Rs. 68.00 Kg
Rs. 76.50 Kg
Rs. 79.56 Kg
Rs. 1.59 Kg
Rs. 81.15 Kg
4070.00 Cum
4070.00 Sqm
60.00 Sqm
90.00 Sqm
150.00 Sqm
50.00 Kgs
7500.00 Kgs
Rs. 286187.93
Rs. 112500.00
173687.93
Rs. 42.68
Rs. 173687.93
Rs. 366300.00
Rs. 61050.00
Rs. 20350.00
Rs. 621387.93
152.68 Sqm.
Rs. 152.68 Cum
1 a, b & c)
5800.00 Cum
31.00 Nos
4.25 Sqm
187.10 Cum
5.00 Sets
636.13 Mton
640.00 Mton
Rs 24421369.60
Rs 9600000.00
Rs 14821369.60
Rs. 2555.41 Cum
Rs. 1700.00 Cum
Rs. 63.75 Cum
Rs. 42.50 Cum
Rs. 4361.66 Cum
Rs. 4050.00 Cum
2310.00 Cum
85.00 Sqm
3.00 Sets
3.00 Sqm
31.88 Mton
35.00 Mton
Rs 1510543.65
Rs 525000.00
Rs 985543.65
Nos.
No 1.00 16800.00 16800.00
16800.00
Sqm
Sqm 1.00 1.00 1.00
1.00
Rm 5700.00 Rmt.
Rs. 2280000.00
Rs. 1140000.00
Rs. 600000.00
Rs. 4860000.00 Rmt.
Rs. 852.63 Rmt. A
12.00 Rmt.
0.7855 Cum.
10.21 Cum.
4013.73 Cum.
40986.20
1021.15
450.00 Nos.
42457.35
3538.11 Rmt. B
0.79 Cum.
250.00 Cum.
196.38 Cum. C
70.18 Rmt. D
4657.29 Rmt.
Cum
Cum 1.1 60 66.00
Cum 1 35.34 35.34
Cum 0.35 35 12.25
Cum 0.65 152.94 99.41
Cum 0.35 10 3.50
216.50
RM
Cum 21.00 55 1155.00
Cum 0.00 50 0.00
Cum 21.00 20 420.00
Cum 1575.00
RM 225.00
Cum 1.00 2690.41 2690.41
Cum 1.00 100 100.00
LS 0.05 2790.41 139.52
Sqm 1.50 75 112.50
Cum 3042.43
Cum
Cum 1.00 3463.78 3463.78
Cum 1.00 100 100.00
Cum 1.00 35 35.00
Cum 1.00 10 10.00
Sqm 1.00 152.68 152.68
Cum 3761.45
d Substructure
MT. 1.00 60662.00 60662
MT. 1.00 2500 2500.00
MT. 63162.00
Cum 13100.00
months 457230.06 18.00 8230141.08
13100.00
142237345.23
-2167500.00
140069845.23
0.00 10692.35
5535.28
16227.63
1 a, b & c)
4900.00 Cum
31.00 Nos
5.00 Sqm
158.06 Cum
5.00 Sets
632.26 Mton
say 640.00 Mton
Rs 13653852.60
Rs (5100000.00)
Rs 8553852.60
Rs 11447517.00
Rs 4292818.88
Rs 12846671.48 128.47
Rs. 2621.77 Cum
Rs. 2000.00 Cum
Rs. 75.00 Cum
Rs. 50.00 Cum
Rs. 4746.77 Cum
Rs. 5535.28 Cum
Rs. 150.00 Cum
Rs. 35.00 Cum
Rs. 15.00 Cum
Rs. 10482.05 Cum
Cum
Rs. 3707.13 Cum
Rs. 100.00 Cum
Rs. 50.00 Cum
Rs. 15.00 Cum
Rs. 3872.13 Cum
2575.00 Cum
110.00 Sqm
21.45 Mton
25.00 Mton
Rs 1003959.75
Rs 375000.00
Rs 628959.75
7716.05
187.20
16224.00
249.60
36.40
Rs 24413.25 MT
Rs 13000.00 MT
Rs 3500.00 MT
Rs 500.00 MT
Rs 1929.01 MT
5.11 2602.31 MT
150.00 763.89 MT
95680.72 MT
RM 1.00 4000.00
RM 1.00 4329.60
RM 1.00 4870.80
RM 1.00 100.00
RM 1.00 4970.80
RM 1.00 5194.49 5194.49
RM 1.00 550.00 550.00
5744.49
SQM 25000.00
Cum 0.50 331.03 165.52
Cum 0.50 35.00 17.50
Cum 0.50 10.00 5.00
188.02
SQM 25000.00
Sqm 1.00 195.00 195.00
195.00
SQM 25000.00
Sqm 1.00 240.00 240.00
240.00
SQM 25000.00
Sqm 1.00 344.04 344.04
344.04
SQM 25000.00
Sqm 1.00 1262.14 1262.14
SQM 1.00 9.00 9.00
1271.14
MT
MT 1.00 49690.00 49690.00
MT 1.00 1000.00 1000.00
50690.00
Rm.
Rm. 1.00 665.00 665.00
Cum 0.60 250.00 150.00
Rm. 1.00 125.00 125.00
Cum 0.30 40.00 12.00
Rm. 0.30 3707.13 1112.14
2064.14
SQM 25000.00
Cum 0.50 331.03 165.52
Cum 0.50 35.00 17.50
Cum 0.50 10.00 5.00
188.02
SQM 25000.00
Sqm 1.00 195.00 195.00
195.00
SQM 25000.00
Sqm 1.00 240.00 240.00
240.00
SQM 25000.00
Sqm 1.00 344.04 344.04
344.04
SQM 25000.00
Sqm 1.00 1262.14 1262.14
SQM 1.00 9.00 9.00
1271.14
Rm.
Cum 1.00 210.00 210.00
Cum 0.19 560.00 107.52
Cum 0.06 2790.41 156.26
Cum 0.75 3238.20 2428.65
Sqm 8.00 225.00 1800.00
MT 0.06 49690.00 2981.40
MT 0.06 2000.00 120.00
Rm. 7803.84
Rm.
Cum 0.09 3113.20 280.19
Cum
Cum 1.00 1236.75 1236.75
Cum 1.00 35.00 35.00
1271.75
Cum
Cum 1.00 3463.78 3463.78
Cum 1.00 100.00 100.00
Cum 1.00 40.00 40.00
Cum 1.00 356.76 356.76
Cum 1.00 625.00 625.00
4585.53
MT
MT 1.00 60662.00 60662.00
MT 1.00 2500.00 2500.00
MT 63162.00
No.
No. 1.00 1750.00 1750.00
No. 1.00 100.00 100.00
1850.00
RM
RM 1.00 1400.00 1400.00
1400.00
RM
Rm. 1.00 712.00 712.00
Cum 0.60 250.00 150.00
Rm. 1.00 125.00 125.00
Cum 0.30 40.00 12.00
Rm. 0.30 3707.13 1112.14
2111.14
No.
No. 1.00 8500.00 8500.00
8500.00
LS
LS 1.00 550000.00 550000.00
550000.00
No.
No. 1.00 150000.00 150000.00
150000.00
No.
No. 1.00 250000.00 250000.00
250000.00
Sqm
Cum 0.150 700.00 105.00
Cum 0.150 150.00 22.50
127.50
Cum
Cum 1.00 2690.41 2690.41
Cum 1.00 125.00 125.00
L.S. 0.015 2815.41 42.23
2857.64
Cum
Cum 1.00 3463.78 3463.78
Cum 1.00 125.00 125.00
LS 0.015 3588.78 53.83
Sqm 10.00 325.00 3250.00
6892.61
Cum
Cum 1.00 331.03 331.03
Cum 1.00 45.00 45.00
Cum 1.00 10.00 10.00
386.03
MT
MT 1.00 60662.00 60662.00
MT 1.00 2250.00 2250.00
62912.00
L.S.
L.S. 1.00 1000000.00 1000000.00
1000000.00
550.00
sq.m.
Sqm 1.00 650.00 100.00
650.00
L.S.
Cum
Cum
Cum
MT.
Per Test
Per Test
Per Test
Per Test
Per Test
82.30
45.33
66.00
119.45
109.65
35.41
12.25
4.00
474.38 A
140.12
0.65
7.74
148.51
150.00 B
67.50
63.00
29.25
C
4.37
2.69
9.10
7.50
36.92
67.50 28800000
8640000
12.45
117.00
104.80
33.58
15.00
30.00
80.50
521.41 D
0.04
116.83 E
979.58
3621.22
A
500.00
Rs. 800 Per MT.
Cum
Cum
Including all the Taxes
Sqm
Cum
Including Shuttering
(Including curing)
(Cost includes Kerb stone
casting and restoration)
1 CEMENT - OPC
Basic cost of material (including Taxes) Rs. 210.00 Bag
Add - Wastage @ 1 % Rs. 0.00 Bag
Site handling Rs. 3.00 Bag
Total cost of cement per bag Rs. 213.00 Bag
Total cost of cement per M TON Rs. 4260.00 Mton 4.26
3 Structural Steel
Basic Cost of struct-steel delivered at site Rs. 42000.00 Mton
Add - Wastage @ 1 % (Burning Losses) Rs. 420.00 Mton
Add - Wastage @ 5 % (Site wastage) 2100.00
Unloading charges Rs. 120.00 Mton
Total cost of ms-steel Rs. 44640.00 Mton
Less - Credit for Scrap 1MT give 50Kg @ Rs.15/kg Rs. (750.00) Mton
Net cost of Structural-Steel Rs. 43890.00 Mton
4 Aggregate 20mm & 10mm
Basic cost of material delivered at site incl. Taxes Rs. 700.00 Cum
Add 3% Wastage Rs. 21.00
Site Handling Rs. 14.00 Cum
Total cost of Aggregate Rs. 735.00 Cum
9 Fly Ash
Basic cost of material delivered at site Rs. 1.60 Kg
Add - VAT 12.5 % Rs. 1.80 Kg
Add - Octroi 2.5 % Rs. 1.85 Kg
Site Handling Rs. 0.04 Kg
Total cost of Fly Ash Rs. 1.88 Kg
10 HT Strand
Basic cost of material delivered at site Rs. 53500.00 Mton
Add - Wastage @ 5 % Rs. 2675.00 Mton
Unloading & site handling Rs. 100.00 Mton
Less - Credit for Scrap 50Kg @ Rs.10/kg Rs. (500.00) Mton
Total cost of HT Strand Rs. 56275.00 Mton
9 ADMIXTURE
Basic cost of material delivered at site Rs. 35.00 Kg
Site Handling and wastage Rs. 0.35 Kg
Total cost of Fly Ash Rs. 35.35 Kg
e Aggregate 40 mm
Basic cost of material delivered at site incl. taxes Rs. 734.98 Cum
Add - Wastage @ 2 % Rs. 14.70 Cum
Total cost of Aggregate Rs. 749.68 Cum
23 2.0 - SUBSTRUCTURE
24 M40 Grade Concrete in Pedestals
Cost of Grade M-40 Cum 1.00 3319.88 3319.88
Labour Charges (Concreting) Cum 1.00 200.00 200.00
Curing Cost Cum 1.00 50.00 50.00
Repair & finishing Cum 1.00 5.00 5.00
Shuttering Cost (Labour + Material) Cum 1.00 500.00 500.00
Total Cost Cum 4074.88
31 Pre-Stressing Works
Pre tension strands of 12.7 mm dia
Basic Cost of H.T. Strands delivered at site Rs. 53500.00 Mton
Add - Extra Consumption for Jack Fixing. (non-
Rs. 3745.00 Mton
payable item) @ 7%
Add - Wastage @ 3 % Rs. 1717.35 Mton
Unloading charges Rs. 100.00 Mton
Cost of site handling Rs. 150.00 Mton
Total cost of H.T. Strands Rs. 59212.35 Mton
Less - Credit for Scrap 1MT give 30Kg @ Rs.10/kg Rs. (300.00) Mton
Net cost of H.T. Strands Rs. 58912.35 Mton
Length of Sheathing Required of HT (1000 kg/1.08x12) 107.11 RM
Cost of HDPE sheathing per MT of HT wire
HDPE Shaething @ Rs 100 Rs 10711.23
End Coupler 6nos. @ Rs 30 + 4% Rs 187.20
End Set (Guide Cone, Bearing Plates, Wedges) 6
Rs 16224.00
Sets @ Rs 2600 + 4%
Grout vent 3nos @ Rs 80 + 4% Rs 249.60
Snapfit Coupler 1 Nos. @ Rs 35 + 4% Rs 36.40
Cost of HDPE sheathingper MT of HT wire Rs 27408.43 MT
Cost of stressing,Jacks,supervision Rs 15000.00 MT
Labour cost for threading, stressing etc. Rs 3500.00 MT
Consumable like tapes, cutting wheel etc. Rs 500.00 MT
Sheathing pipe fixing @ Rs. 25 / RM Rs 2677.81 MT
Cement ( 77.16 x 6.60 Kg ) for grouting 706.94 4.26 3011.57 MT
Intraplas NN 1% of cement weigh 7.07 150.00 1060.41 MT
Total 112070.56 MT
c Stone Pitching
Cost of Rubble Cum 1.00 530.04 530.04
Add for voids Cum 0.30 600.71 180.21
Labour Charges Cum 1.00 75.00 75.00
785.25
f Final wearing coat 40 mm thick
Cost of Concrete Sqm 0.04 3319.88 132.80
Cost of Rein. Steel Sqm 2.00 101.00 202.00
Preparation of deck surface Sqm 1.00 15.00 15.00
Labour Cost For Rein. Steel and shutteri ng Sqm 1.00 25.00 25.00
Labour cost for concreting Sqm 1.00 15.00 15.00
Cost of Curing Sqm 1.00 5.00 5.00
Cost of repairs Sqm 1.00 2.00 2.00
396.80
D Precast I- Girders
Total concrete quantity 925.00 Cum
Number of I -Girder 52.00 Nos
Consider shuttering required per cum 4.50 Sqm 4162.5
approx concrete per girder 17.79 Cum
Consider shuttering required including
supporting arrangement 2.00 Sets
Total st. steel required @ 100 kg/sqm Including supportings, etc.
16.01 Mton
say 16.01 Mton
Cost of shuttering & supporting
(16 MT x Rs. 60000) Rs 960576.92
50% to be debitt to DFCC Site Rs 480288.46
Net cost of shuttering Rs 480288.46
Total cost of shuttering and launching per cum of concrete Rs. 3835.00 Cum
Cost of Bed Preparation For casting of I Girders 400.00 Sqm
Cost For Excavation Rs. 8400.00 Span.
Rubble Soaling Rs. 90000.00 Span.
M15 PCC Rs. 120000.00 Span.
Total Cost For Bed Preparation (For 3 Bridges) Rs. 218400.00 Span.
Net Cost Per Cum. Of Concrete = Rs. 236.11 Cum.
Cost of Concrete (M-45 Grade) Rs. 3319.88 Cum.
Laying Charges of Concreting Rs. 150.00 Cum
Curing cost Rs. 35.00 Cum
Repair & finishing Rs. 15.00 Cum
Total Cost Of Concrete = Rs. 3519.88 Cum
Total Cost of Concrete = Rs. 7590.99 Cum.
D Precast Box - Girders
Total concrete quantity 31600.00 Cum
Number of box - Girder 316.00 Nos
Consider shuttering required per cum 4.50 Sqm
approx concrete per girder 100.00 Cum
Consider shuttering required including
supporting arrangement 20.00 Sets
Total st. steel required @ 140 kg/sqm Including supportings, etc.
1000.00 Mton
say 1000.00 Mton
Cost of shuttering & supporting
(1000 MT x Rs. 60000) Rs 60000000.00
50% debitted to DFCC Site Rs (30000000.00)
Net cost of shuttering Rs 30000000.00
Total cost of shuttering and launching per cum of concrete Rs. 7429.46 Cum A
Cost of Bed Preparation For casting of Box Girders 12500.00 Sqm
At csting yards (extra 1500 Rm excluding approaches)
Qty of Filling for Casting Bed Cum 62500.00
Cost For Filling for Casting Bed (Per Cum) Including compaction Rs. 225.00
Total Cost For Filling for Casting Bed (murrum) Rs. 14062500.00
Excavation For Foundn of beds Rs. 195000.00
Rubble Soaling (300 mm tk) Rs. 347200.00
PCC For base slab Rs. 260000.00
RCC For base slab Rs. 5400000.00
Rein. Steel for base slab Rs. 7200000.00
Total Cost of Casting yard = Rs. 27464700.00
Cost of Casting yard = Rs. 869.14 B
Cost of Concrete (M-45 Grade) Rs. 3319.88 Cum.
Laying Charges of Concreting Rs. 120.00 Cum
Curing cost Rs. 30.00 Cum
Repair & finishing Rs. 10.00 Cum
Total Cost Of Concrete = Rs. 3479.88 Cum C
Total Cost of Concrete = Rs. 11778.48 Cum.
a Crash Parapet
RMC M45 Cum 3319.88 3319.88
Labour Charges (For Concreting ) Cum 100.00 100.00
Cost of Curing Cum 50.00 50.00
Cost For Finishing Cum 15.00 15.00
Cost for Shuttering. (material) Cum 1200.00 1200.00
Cost for Shuttering & Rein. (labour) Cum 750.00 750.00
Total Cost = Cum 5434.88
43707.38
MT.
MT.
MT.
Sqm.
Per Test
Per Test
Per Test
Per Test
Per Test
A
Rs. 800 Per MT.
ring Height of Staging is 10 M.
ring Height of Staging is 10 M.