Professional Documents
Culture Documents
5 Cutting the grass and removing the roots breaking the large muds, leveling and cleaning the site
A3 For Rate analysis 1 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.02 586.50 13.49
Total - A 13.49
Total -A 13.49
B Add 15% Contractor's OHP 2.02
Total (A+B) : 15.51
Rate per sq.m = 15.51
Rate per sq.ft = 1.44
10 Earthwork excavation in soft clay, silty soil including lift upto 1.5m and disposal upto 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.70 586.50 410.55
Total - A 410.55
B Materials
Total -B
C Equipments
welder including rod 0.03 12.32
Total -C 12.32
Total (A+B+C) : 422.87
D Add 15% Contractor's OHP 63.43
Total (A+B+C+D) : 486.30
Rate per cu.m. of Earthwork in Excavation in soft soil= 486.30
Rate per cu.ft. of Earthwork in Excavation in soft soil= 13.77
Earthwork excavation in medium stone without Explosive including lift upto 1.5m and disposal upto
12 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 3.00 586.50 1,759.50
Total - A 1,759.50
B Materials
Total -B
C Equipments
0.03 52.79
Total -C 52.79
Total (A+B+C) : 1,812.29
D Add 15% Contractor's OHP 271.84
Total (A+B+C+D) : 2,084.13
Rate per cu.m. of Earthwork in Excavation of soil contaning medium stone = 2,084.13
Rate per cu.ft. of Earthwork in Excavation of soil contaning medium stone = 59.02
Back filling withimported soil including levelling, water spraying and compaction at 15 cm layers
including transportation from 10m distance. With mud from site
For Rate analysis 1 cu.m is used
1.5 Flat dry brick soling under floor and foundation including sand blinding - for 10 sq.m.
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.5 828.00 414.00
Unskilled md 1.00 586.50 586.50
Total - A 1,000.50
B Materials
Brick no 420.00 14.00 5,880.00
Sand cu.m. 0.71 2,200.00 1,562.00
Total - B 7,442.00
C Equipment
- -
Total - C -
Total (A+B+C) : 8,442.50
D Add 15% Contractor's OHP 1,266.38
Total (A+B+C+D) : 9,708.88
Rate per sq.m. of Dry Flat Brick soling = 970.89
Rate per sq.ft. of Dry Flat Brick soling = 90.23
11.1 500 Micron Two Layer Polythene Sheet below 75mm thick PCC
Total 1,761.70
Over-head 15 % 264.26
G. Total SM 202.60
Providing and laying chimney fired brick masonry works in cement mortar ( 1 : 4 ) above Ground
32 Floor,including material and transportation up to 30m
C2 For Rate analysis 1cu.m is used
110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ) with hoop iron
equivalent reinforcement / 2-6 mm dia. steel bar at every 4 courses of brick. (per 10 sq.m.)
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.90 828.00 1,573.20
Unskilled md 2.60 586.50 1,524.90
Total - A 3,098.10
B Materials
First class machine Made Brick no 673.00 15.00 10,095.00
Providing and Laying P.C.C. (1:3:6) in foundation, under floor, etc. as lean/levelling including
47 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 828.00 828.00
Unskilled md 4.00 586.50 2,346.00
Total - A 3,174.00
B Materials
Cement m.t 0.22 14,200.00 3,124.00
Aggregate 20 mm - 10 mm cu.m 0.65 1,850.00 1,202.50
Aggregate 10 mm & down cu.m 0.24 1,850.00 444.00
Sand cu.m 0.47 2,200.00 1,034.00
Water lit. 120.00 0.30 36.00
Total -B 5,840.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 9,014.50
D Add 15% Contractor's OHP 1,352.18
Total (A+B+C+D) : 10,366.68
Rate per cu.m. of P.C.C (1:3:6) = 10,366.68
Rate per cu.ft. of P.C.C (1:3:6) = 293.59
Providing and Laying P.C.C. (1:2:4) in foundation, under floor, etc. as lean/levelling including
48 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 828.00 828.00
Unskilled md 4.00 586.50 2,346.00
Total - A 3,174.00
B Materials
Cement m.t 0.32 14,200.00 4,544.00
Aggregate 20 mm cu.m 0.52 1,850.00 962.00
Aggregate 10 mm cu.m 0.22 1,850.00 407.00
Aggregate <10 mm & down cu.m 0.11 1,850.00 203.50
Sand cu.m 0.45 2,200.00 979.00
Water lit. 150.00 0.30 45.00
Total -B 7,140.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 10,314.50
D Add 15% Contractor's OHP 1,547.18
Total (A+B+C+D) : 11,861.68
Rate per cu.m. of P.C.C (1:2:4) = 11,861.68
Rate per cu.ft. of P.C.C (1:2:4) = 335.93
Providing & laying PCC for RCC of grade M20(1:1.5:3) in Superstructure, deck slab and beam
50 including Transportation up to 30m.
D2 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.80 828.00 662.40
Unskilled md 7.00 586.50 4,105.50
Total - A 4,767.90
B Materials
Cement m.t 0.40 14,200.00 5,680.00
Aggregate 20 mm cu.m 0.57 1,850.00 1,054.50
Aggregate 10 mm cu.m 0.29 1,850.00 536.50
Sand cu.m 0.43 2,200.00 935.00
Water lit. 200.00 0.30 60.00
Total -B 8,266.00
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 13,033.90
D Add 15% Contractor's OHP 1,955.09
Total (A+B+C+D) : 14,988.99
Rate per cu.m. of P.C.C for R.C.C M20 (1:1.5:3) = 14,988.99
Rate per cu.ft. of P.C.C for R.C.C M20 (1:1.5:3) = 424.50
Providing,bending and placing properly according to drawing and binding of steel reinforcment along
59 witht transpotation up to 30m
D9 For rate analysis 1 mt is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 12.00 828.00 9,936.00
Unskilled md 12.00 586.50 7,038.00
Total - A 16,974.00
B Materials
TMT rod Mt 1.05 78,000.00 81,900.00
GI tying wire Kg 10.00 100.00 1,000.00
Total -B 82,900.00
Total (A+B) : 99,874.00
C Add 15% Contractor's OHP 14,981.10
Total (A+B+C) : 114,855.10
Rate per m.t= 114,855.10
62
E2 Plywood formworks with steel adjustable pipe props for floor and slab
For rate analysis 100 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 17.20 828.00 14,241.60
Unskilled md 25.70 586.50 15,073.05
Total - A 29,314.65
B Materials
19mm board sqm 16.50 1,304.35 21,521.78
Local wood cum 0.23 52,965.00 12,287.88
Iron pipe(NMB 50-M) No. 4.40 1,940.00 8,536.00
65
E5 19mm plywood formworks for beam including materials and removing with transpotation upto 30m
For rate analysis 10 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.67 828.00 2,210.76
Unskilled md 4.00 586.50 2,346.00
Total - A 4,556.76
B Materials
Ply board sqm 1.65 1,304.35 2,152.18
Local wood cum 0.04 52,965.00 2,065.64
Steel prop No. 0.40 1,940.00 776.00
Nail Kg 2.50 110.00 275.00
Total -B 5,268.81
Total (A+B) : 9,825.57
C Add 15% Contractor's OHP 1,473.84
Total (A+B+C) : 11,299.41
Rate per sq.m= 1,129.94
Rate per sq.ft= 105.01
737.09
78
F6 Providing materials and roofing with colourful corrugated sheet(0.50mm thick)
For rate analysis 10 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.10 828.00 910.80
Unskilled md 1.25 586.50 733.13
Total - A 1,643.93
B Materials
0.50mm colourful corrugated sheet sqm 12.00 820.38 9,844.59
7mm nut bolt No. 30.00 27.00 810.00
8mm J hook No. 25.00 30.00 750.00
Bitumen washer No. 55.00 1.50 82.50
Total -B 11,487.09
Total (A+B) : 13,131.02
C Add 15% Contractor's OHP 1,969.65
Total (A+B+C) : 15,100.67
Rate per sq.m= 1,510.07
Rate per sq.ft= 140.34
80
F4 Providing and constructing ridge with 0.50mm colourful GI sheet and also fixing
For rate analysis 10 Rm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.00 828.00 1,656.00
Unskilled md 3.00 586.50 1,759.50
Total - A 3,415.50
B Materials
0.5mm colourful sheet metre 12.00 400.00 4,800.00
nut bolt LS 70.00
Total -B 4,870.00
Total (A+B) : 8,285.50
C Add 15% Contractor's OHP 1,242.83
Total (A+B+C) : 9,528.33
120 38 mm (1½" ) thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing (per
11-1 10 sq.m.)
For Rate Analysis 10 sqm. is used
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.25 828.00 1,035.00
Unskilled md 2.00 586.50 1,173.00
Total - A 2,208.00
B Materials
cement MT 0.13 14,200.00 1,846.00
sand cu 0.18 2,200.00 396.00
12mm aggregate cu 0.36 1,850.00 666.00
Total -B 2,908.00
C Equipments
Total -C
Total (A+B+C) : 5,116.00
D Add 15% Contractor's OHP 767.40
Total (A+B+C+D) : 5,883.40
Rate per sq.m 588.34
Rate per sq.ft 54.68
133 Flooring of 25mm -37.5mm thick stone( flagstone) with 1:4 cement sand mortar.
11-9 For Rate Analysis 10 sqm.
H9
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.00 828.00 1,656.00
Unskilled md 4.50 586.50 2,639.25
Total - A 4,295.25
B Materials
37.5mm stone sqm 11.00 990.00 10,890.00
cement MT 0.06 14,200.00 852.00
sand from river cum 0.17 2,200.00 363.00
Total -B 12,105.00
C Equipments
Total -C
Total (A+B+C) : 16,400.25
D Add 15% Contractor's OHP 2,460.04
Total (A+B+C+D) : 18,860.29
Hardened Concrete Floor 38mm thick IPS Floor Finish with Floor Hardner (per 10 sq.m.)
Total - B 5,240.50
C Equipment/Others
Electrical Floor Finisher, etc. -
Total - C -
Total (A+B+C) : 10,249.90
D Add 15% Contractor's OHP 1,537.49
Total (A+B+C+D) : 11,787.39
Rate per sq.m. = 1,178.74
169 12.5mm thick plastering of cement sand mortar of ratio 1:4 on ceiling.
I1 Rate analysis per 100 Sqm
Total -B 10,851.60
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 35,001.60
D Add 15% Contractor's OHP 5,250.24
Total (A+B+C+D) : 40,251.84
Rate per Sq.m. 402.52
Rate per Sq.ft. 37.41
Total -B 13,264.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 35,999.50
D Add 15% Contractor's OHP 5,399.93
Total (A+B+C+D) : 41,399.43
Rate per Sq.m. 413.99
Rate per Sq.ft. 38.48
180 Flush Pointing on Brick wall by cement sand mortar of ratio 1:2
I8 Rate analysis per 100 Sqm
Total -C
Total (A+B+C) : 23,538.60
D Add 15% Contractor's OHP 3,530.79
Total (A+B+C+D) : 27,069.39
Rate per sq.m 270.69
Rate per sq.ft 25.16
199 One coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm
Total - A 9,556.50
B Materials
Astar Ltr 8.10 360.00 2,916.00
Readymade paint Ltr 9.00 450.00 4,050.00
Total -B 6,966.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 16,522.50
D Add 15% Contractor's OHP 2,478.38
Total (A+B+C+D) : 19,000.88
Rate per Sq.m. 190.01
Rate per Sq.ft. 17.66
200 Two coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm
206
J26 Two coats weather coat (apex or similar) with one coat primer painting work
For rate analysis 100sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 5.80 828.00 4,802.40
Unskilled md 5.80 586.50 3,401.70
Total - A 8,204.10
B Materials
Astar litre 8.00 240.00 1,920.00
Weather coat litre 16.00 650.00 10,400.00
Total -B 12,320.00
Total (A+B) : 20,524.10
C Add 15% Contractor's OHP 3,078.62
Total (A+B+C) : 23,602.72
Rate per s.qm= 236.03
Rate per s.ft= 21.94
227
Double coating aluminium paint excluding astar
East West Engineering Service Pvt. Ltd Civil Works: Page 13 of 21
SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)
238
Providing and applying Dustban/Permise chemicals for Anti Termite Treatment all complete
J29
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials
Providing and applying
Dustban/Permise chemicals for sqm 10.00 412.50 4,125.00
Anti Termite Treatment all
complete.
Total 4,125.00
B Add 15% Contractor's OHP 618.75
Total (A+B) 4,743.75
Rate per s.qm= 474.38
Rate per s.ft= 44.09
245
K4 Laying one layer 500 gauge polyethene sheet
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.60 828.00 496.80
Unskilled md 0.60 586.50 351.90
Total - A 848.70
B Materials
Polyethene sheet 500 gauge sqm 11.00 83.00 913.00
913.00
Total (A+B) : 1,761.70
C Add 15% Contractor's OHP 264.26
Total (A+B+C) : 2,025.96
Rate per s.qm= 202.60
Rate per s.ft= 18.83
Constructing,Painting 3x20 mm metal grills with red oxide and rubbing with abrasive material and also
278 fixing
M1 For Rate analysis 10sq.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials
Note: 1.00sq.m=16.14kg
280
M4 For Rate analysis 18.94kg is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.69 828.00 568.84
Unskilled md 0.78 586.50 458.06
Total - A 1,026.89
B Materials
Different types of steel angles kg 18.94 85.00 1,609.90
primer paint LS 110.00
Total -B 1,719.90
Total (A+B) 2,746.79
C Add 15% Contractor's OHP 412.02
Total (A+B+C) : 3,158.81
Rate per kg 166.78
Metal spiral stairway:Using 4"-6" dia medium class black pipe post than in 2/4"x2/4" scawire using
medium class 1 1/4" dai black pipe handrail 2'-2'6" width metal spiral stair with necessary materials
287
M11 For Rate analysis 18.94kg is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.69 828.00 568.84
Unskilled md 0.78 586.50 458.06
Total - A 1,026.89
B Materials
All types of black pipes making and kg 18.94 95.00 1,799.30
Primer paint Ls 110.00
Total -B 1,909.30
Total (A+B) 2,936.19
C Add 15% Contractor's OHP 440.43
Total (A+B+C) : 3,376.62
Rate per kg 178.28
Total - A 9,936.00
B Materials
Cement Board Sq.m 27.00 344.32 9,296.64
Fixture R.m 15.40 450.00 6,930.00
Joint Filling R.m 36.00 125.00 4,500.00
Total - B 20,726.64
C Equipment/others
LS 150.00
Total - C 150.00
Total (A+B+C) : 30,812.64
D Add 15% Contractor's OHP 4,621.90
Total (A+B+C+D) : 35,434.54
Rate per sq.m. of V-board = 2,952.88
256
L1
Demolition of wall on mud and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 1.06 586.50 621.69
Total 621.69
B Add 15% Contractor's OHP 93.25
Total (A+B) 714.94
Rate per cu.m= 714.94
Rate per s.ft= 20.25
257
L2
Demolition of wall on cement and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 2.12 586.50 1,243.38
Total 1,243.38
B Add 15% Contractor's OHP 186.51
Total (A+B) 1,429.89
Rate per cu.m= 1,429.89
Rate per s.ft= 40.50
258
L3
Demolition of RCC and RBC works and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 11.00 586.50 6,451.50
Total 6,451.50
B Add 15% Contractor's OHP 967.73
Total (A+B) 7,419.23
Rate per cu.m= 7,419.23
Rate per s.ft= 210.12
Dismantling of completely damaged building and disposing the debris including Transportation. For
Rate Analysis 100 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Total - A 0.00
B Materials
Stone Masonry cu.m 47.70 714.94 34,102.80
Slab Dismanteling cu.m 10.00 3,709.61 37,096.13
Transportation cu.m 57.70 476.69 27,504.72
Total -B 98,703.65
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 98,703.65
D Add 15% Contractor's OHP 14,805.55
Total (A+B+C+D) : 113,509.20
Dismantling of Damaged Building per sq.m 1,135.09
Dismantling of Damaged Building per sq.ft 105.49
8.2 Providing & fixing in position Glazed Ceramic Tile on wall using tile adhesive and grout
(per 10 sq.m.)
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 13.00 828.00 10,764.00
Unskilled md 4.50 586.50 2,639.25
Total - A 13,403.25
B Materials
Cement mt. 0.056 14,200.00 795.20
Sand cu.m. 0.15 2,200.00 334.40
White cement kg. 3.23 26.12 84.32
Ceramic Glazed Tile sq.m. 10.48 1,076.00 11,276.48
border tile sq.m. 0.52 -
Total - B 12,490.40
C Equipment/others
-
Total - C -
Total (A+B+C) : 25,893.65
D Add 15% Contractor's OHP 3,884.05
Total (A+B+C+D) : 29,777.69
Rate per sq.m. of Glazed Ceramic Tile on Wall = 2,977.77
Rate per sq.ft. of Glazed Ceramic Tile on Wall = 276.74
Total - B 6,463.05
C Equipment/others
5.2 50 thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing (per 10 sq.m.)