You are on page 1of 21

SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Rate Analysis 2072/2073

5 Cutting the grass and removing the roots breaking the large muds, leveling and cleaning the site
A3 For Rate analysis 1 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.02 586.50 13.49
Total - A 13.49
Total -A 13.49
B Add 15% Contractor's OHP 2.02
Total (A+B) : 15.51
Rate per sq.m = 15.51
Rate per sq.ft = 1.44

10 Earthwork excavation in soft clay, silty soil including lift upto 1.5m and disposal upto 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 0.70 586.50 410.55
Total - A 410.55
B Materials
Total -B
C Equipments
welder including rod 0.03 12.32
Total -C 12.32
Total (A+B+C) : 422.87
D Add 15% Contractor's OHP 63.43
Total (A+B+C+D) : 486.30
Rate per cu.m. of Earthwork in Excavation in soft soil= 486.30
Rate per cu.ft. of Earthwork in Excavation in soft soil= 13.77

Earthwork excavation in medium stone without Explosive including lift upto 1.5m and disposal upto
12 10m distance.
B1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 3.00 586.50 1,759.50
Total - A 1,759.50
B Materials
Total -B
C Equipments
0.03 52.79
Total -C 52.79
Total (A+B+C) : 1,812.29
D Add 15% Contractor's OHP 271.84
Total (A+B+C+D) : 2,084.13
Rate per cu.m. of Earthwork in Excavation of soil contaning medium stone = 2,084.13
Rate per cu.ft. of Earthwork in Excavation of soil contaning medium stone = 59.02

Back filling withimported soil including levelling, water spraying and compaction at 15 cm layers
including transportation from 10m distance. With mud from site
For Rate analysis 1 cu.m is used

East West Engineering Service Pvt. Ltd Civil Works: Page 1 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Unskilled md 0.50 586.50 293.25
Total - A 293.25
B Materials
Soil cu.m 1.50 0.00 0.00
Water lit. 5.00 0.30 1.50
Total -B 1.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 294.75
D Add 15% Contractor's OHP 44.21
Total (A+B+C+D) : 338.96
Rate per cu.m. of Earthwork Earth Filling Works using soil from site 338.96
Rate per cu.ft. of Earthwork Earth Filling Works using soil from site 9.60

1.5 Flat dry brick soling under floor and foundation including sand blinding - for 10 sq.m.
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.5 828.00 414.00
Unskilled md 1.00 586.50 586.50
Total - A 1,000.50
B Materials
Brick no 420.00 14.00 5,880.00
Sand cu.m. 0.71 2,200.00 1,562.00
Total - B 7,442.00
C Equipment
- -
Total - C -
Total (A+B+C) : 8,442.50
D Add 15% Contractor's OHP 1,266.38
Total (A+B+C+D) : 9,708.88
Rate per sq.m. of Dry Flat Brick soling = 970.89
Rate per sq.ft. of Dry Flat Brick soling = 90.23

11.1 500 Micron Two Layer Polythene Sheet below 75mm thick PCC

S.No. Particulars Unit Quantity Rate Amount


A Labour :
Skilled md 0.6 828.00 496.80
Unskilled md 0.6 586.50 351.90
B Material :

Polythene sheet SM 11 83.00 913.00

Total 1,761.70
Over-head 15 % 264.26
G. Total SM 202.60

Providing and laying chimney fired brick masonry works in cement mortar ( 1 : 4 ) above Ground
32 Floor,including material and transportation up to 30m
C2 For Rate analysis 1cu.m is used

East West Engineering Service Pvt. Ltd Civil Works: Page 2 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 1.50 828.00 1,242.00
Unskilled md 2.20 586.50 1,290.30
Unskilled md 0.70 586.50 410.55
Total - A 2,942.85
B Materials
Chimney Fired Brick nos 560.00 14.00 7,840.00
Cement mt 0.10 14,200.00 1,420.00
River Sand cu.m 0.28 2,200.00 616.00
Water lit. 130.00 0.30 39.00
Total -B 9,915.00
C Equipments
0.03 12.32
Total -C 12.32
Total (A+B+C) : 12,870.17
D Add 15% Contractor's OHP 1,930.52
Total (A+B+C+D) : 14,800.69
Rate per cu.m. of Chimney Fired Brick work above Ground Floor in cement mortar 14,800.69
Rate per cu.ft. of Chimney Fired Brick1:4 = above Ground Floor in cement mortar
work 419.16
1:4 =
Providing and laying machine made brick masonry works with one side Fairface in cement mortar ( 1 :
25 4 ) ,including material and transportation up to 30m
C1 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 3.00 828.00 2,484.00
Unskilled md 4.40 586.50 2,580.60
Unskilled md 1.40 586.50 821.10
Total - A 5,885.70
B Materials
Machine Made Brick nos 530.00 15.00 7,950.00
Cement mt 0.10 14,930.00 1,493.00
River Sand cu.m 0.27 2,200.00 594.00
Water lit. 120.00 0.30 36.00
Total -B 10,073.00
C Equipments
3% 24.63
Total -C 24.63
Total (A+B+C) : 15,983.33
D Add 15% Contractor's OHP 2,397.50
Total (A+B+C+D) : 18,380.83
Rate per cu.m. of Machine made Brickwork in cement mortar 1:4 = 18,380.83
Rate per cu.ft. of Machine made Brickwork in cement mortar 1:4 = 520.56

110 mm ( Half Brick ) Thick chimney Fired brick works in cement mortar( 1 : 4 ) with hoop iron
equivalent reinforcement / 2-6 mm dia. steel bar at every 4 courses of brick. (per 10 sq.m.)
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.90 828.00 1,573.20
Unskilled md 2.60 586.50 1,524.90
Total - A 3,098.10
B Materials
First class machine Made Brick no 673.00 15.00 10,095.00

East West Engineering Service Pvt. Ltd Civil Works: Page 3 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Cement mt 0.11 14,200.00 1,510.88


Sand cu.m. 0.30 2,200.00 660.00
Steel kg 16.32 78.00 1,272.96
Scaffolding 3% of Labour 3.00% 92.94
Total - B 13,631.78
C Equipment
- -
Total - C -
Total (A+B+C) : 16,729.88
D Add 15% Contractor's OHP 2,509.48
Total (A+B+C+D) : 19,239.37
Rate per sq.m. of Chimney Fired Brickwork half-brickwork in Superstructure in cement mortar 1,923.94
1:4 =
Providing and laying stone masonry works in cement mortar ( 1 : 6) including block stone and
40 transportation of 10 m
C6 For Rate analysis 1cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.50 828.00 1,242.00
Unskilled md 5.00 586.50 2,932.50
Total - A 4,174.50
B Materials
Cement mt 0.11 14,200.00 1,505.20
Sand cu.m 0.47 2,200.00 1,034.00
Block Stone cu.m 1.00 2,354.00 2,354.00
Bond Stone cu.m 0.10 2,354.00 235.40
Water lit. 70.00 0.30 21.00
Total -B 5,149.60
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 9,324.10
D Add 15% Contractor's OHP 1,398.62
Total (A+B+C+D) : 10,722.72
Rate per cu.m. = 10,722.72
Rate per cu.ft. = 303.67

44 Gravel Filling in Foundation, leveling and transportation up 30 m.


C10 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled md 1.50 586.50 879.75
Total - A 879.75
B Materials
Block Stone cu.m 1.00 2,354.00 2,354.00
Bond Stone cu.m 0.20 2,354.00 470.80
Total -B 2,824.80
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 3,704.55
D Add 15% Contractor's OHP 555.68
Total (A+B+C+D) : 4,260.23

East West Engineering Service Pvt. Ltd Civil Works: Page 4 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Rate per cu.m. = 4,260.23


Rate per cu.ft. = 120.65

Providing and Laying P.C.C. (1:3:6) in foundation, under floor, etc. as lean/levelling including
47 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 828.00 828.00
Unskilled md 4.00 586.50 2,346.00
Total - A 3,174.00
B Materials
Cement m.t 0.22 14,200.00 3,124.00
Aggregate 20 mm - 10 mm cu.m 0.65 1,850.00 1,202.50
Aggregate 10 mm & down cu.m 0.24 1,850.00 444.00
Sand cu.m 0.47 2,200.00 1,034.00
Water lit. 120.00 0.30 36.00
Total -B 5,840.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 9,014.50
D Add 15% Contractor's OHP 1,352.18
Total (A+B+C+D) : 10,366.68
Rate per cu.m. of P.C.C (1:3:6) = 10,366.68
Rate per cu.ft. of P.C.C (1:3:6) = 293.59

Providing and Laying P.C.C. (1:2:4) in foundation, under floor, etc. as lean/levelling including
48 transportation up to 30m
D1 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.00 828.00 828.00
Unskilled md 4.00 586.50 2,346.00
Total - A 3,174.00
B Materials
Cement m.t 0.32 14,200.00 4,544.00
Aggregate 20 mm cu.m 0.52 1,850.00 962.00
Aggregate 10 mm cu.m 0.22 1,850.00 407.00
Aggregate <10 mm & down cu.m 0.11 1,850.00 203.50
Sand cu.m 0.45 2,200.00 979.00
Water lit. 150.00 0.30 45.00
Total -B 7,140.50
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 10,314.50
D Add 15% Contractor's OHP 1,547.18
Total (A+B+C+D) : 11,861.68
Rate per cu.m. of P.C.C (1:2:4) = 11,861.68
Rate per cu.ft. of P.C.C (1:2:4) = 335.93

East West Engineering Service Pvt. Ltd Civil Works: Page 5 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Providing & laying PCC for RCC of grade M20(1:1.5:3) in Superstructure, deck slab and beam
50 including Transportation up to 30m.
D2 For Rate analysis 1 cu.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.80 828.00 662.40
Unskilled md 7.00 586.50 4,105.50
Total - A 4,767.90
B Materials
Cement m.t 0.40 14,200.00 5,680.00
Aggregate 20 mm cu.m 0.57 1,850.00 1,054.50
Aggregate 10 mm cu.m 0.29 1,850.00 536.50
Sand cu.m 0.43 2,200.00 935.00
Water lit. 200.00 0.30 60.00
Total -B 8,266.00
C Equipments
0.00 0.00
Total -C 0.00
Total (A+B+C) : 13,033.90
D Add 15% Contractor's OHP 1,955.09
Total (A+B+C+D) : 14,988.99
Rate per cu.m. of P.C.C for R.C.C M20 (1:1.5:3) = 14,988.99
Rate per cu.ft. of P.C.C for R.C.C M20 (1:1.5:3) = 424.50

Providing,bending and placing properly according to drawing and binding of steel reinforcment along
59 witht transpotation up to 30m
D9 For rate analysis 1 mt is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 12.00 828.00 9,936.00
Unskilled md 12.00 586.50 7,038.00
Total - A 16,974.00
B Materials
TMT rod Mt 1.05 78,000.00 81,900.00
GI tying wire Kg 10.00 100.00 1,000.00
Total -B 82,900.00
Total (A+B) : 99,874.00
C Add 15% Contractor's OHP 14,981.10
Total (A+B+C) : 114,855.10
Rate per m.t= 114,855.10

62
E2 Plywood formworks with steel adjustable pipe props for floor and slab
For rate analysis 100 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 17.20 828.00 14,241.60
Unskilled md 25.70 586.50 15,073.05
Total - A 29,314.65
B Materials
19mm board sqm 16.50 1,304.35 21,521.78
Local wood cum 0.23 52,965.00 12,287.88
Iron pipe(NMB 50-M) No. 4.40 1,940.00 8,536.00

East West Engineering Service Pvt. Ltd Civil Works: Page 6 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Nail Kg 25.00 110.00 2,750.00


Total -B 45,095.66
Total (A+B) : 74,410.31
C Add 15% Contractor's OHP 11,161.55
Total (A+B+C) : 85,571.85
Rate per sq.m= 855.72
Rate per sq.ft= 79.53

Note:Wood re-use upto 6 times with 25% salvage value (1.6875x1.1x0.7516=0.23


:Ply re-use upto 6 times with 10% salvage value(100x1.1x0.9/6=16.5)
:Pipe re-use upto 15 times with 25% salvage value(88/15x0.75=4.4)

65
E5 19mm plywood formworks for beam including materials and removing with transpotation upto 30m
For rate analysis 10 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.67 828.00 2,210.76
Unskilled md 4.00 586.50 2,346.00
Total - A 4,556.76
B Materials
Ply board sqm 1.65 1,304.35 2,152.18
Local wood cum 0.04 52,965.00 2,065.64
Steel prop No. 0.40 1,940.00 776.00
Nail Kg 2.50 110.00 275.00
Total -B 5,268.81
Total (A+B) : 9,825.57
C Add 15% Contractor's OHP 1,473.84
Total (A+B+C) : 11,299.41
Rate per sq.m= 1,129.94
Rate per sq.ft= 105.01

Note:Wood re-use upto 6 times with 25% salvage value (0.02885/1.1/6x0.75=0.0


:Ply re-use upto 6 times with 10% salvage value(11.11/6x0.90=1.65)
:Pipe re-use upto 15 times with 25% salvage value(8/15x0.75=0.4)

66 19mm plywood formworks for column including materials,erection,nailing, removing with


E6 transpotation upto 30m(formwork on 2m dia column)
For rate analysis 4.20 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.57 828.00 1,303.27
Unskilled md 2.36 586.50 1,384.73
Total - A 2,688.00
B Materials
Ply board sqm 0.69 1,304.35 903.91
Local wood cum 0.02 52,965.00 1,006.34
Steel prop Kg 0.54 144.00 77.76
Nail Kg 2.50 110.00 275.00
Total -B 2,263.01
Total (A+B) : 4,951.01
C Add 15% Contractor's OHP 742.65
Total (A+B+C) : 5,693.66

East West Engineering Service Pvt. Ltd Civil Works: Page 7 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Rate per sq.m= 1,355.63


Rate per sq.ft= 125.99

Note:Wood re-use upto 6 times with 25% salvage value (0.155/6x0.75=0.019)


:Ply re-use upto 6 times with 10% salvage value(4.62/6x0.90=0.693)
:Pipe re-use upto 15 times with 25% salvage value(10.68/15x0.75=0.54)

2.4.4 Weighted mean Rate of Formwork


Formwork Location Quantity Rate
Qty. Column/Shear Wall 152.82 1,355.63
Qty. Beam 365.93 1,129.94
Qty. Slab 173.01 855.72
Qty. Lintels/Sills 45.33 855.72

737.09

Weighted Mean Rate of Formwork per sq.m. = 1,095.50


Weighted Mean Rate of Formwork per sq.ft. = 101.81

78
F6 Providing materials and roofing with colourful corrugated sheet(0.50mm thick)
For rate analysis 10 sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.10 828.00 910.80
Unskilled md 1.25 586.50 733.13
Total - A 1,643.93
B Materials
0.50mm colourful corrugated sheet sqm 12.00 820.38 9,844.59
7mm nut bolt No. 30.00 27.00 810.00
8mm J hook No. 25.00 30.00 750.00
Bitumen washer No. 55.00 1.50 82.50
Total -B 11,487.09
Total (A+B) : 13,131.02
C Add 15% Contractor's OHP 1,969.65
Total (A+B+C) : 15,100.67
Rate per sq.m= 1,510.07
Rate per sq.ft= 140.34

80
F4 Providing and constructing ridge with 0.50mm colourful GI sheet and also fixing
For rate analysis 10 Rm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.00 828.00 1,656.00
Unskilled md 3.00 586.50 1,759.50
Total - A 3,415.50
B Materials
0.5mm colourful sheet metre 12.00 400.00 4,800.00
nut bolt LS 70.00
Total -B 4,870.00
Total (A+B) : 8,285.50
C Add 15% Contractor's OHP 1,242.83
Total (A+B+C) : 9,528.33

East West Engineering Service Pvt. Ltd Civil Works: Page 8 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Rate per 1Rm= 952.83


Rate per 1sqm= 1,588.05

Note:Breadth of plain sheet is assumed to be 2' (10.00Rm=10.00x0.60=6.00sqm)

120 38 mm (1½" ) thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing (per
11-1 10 sq.m.)
For Rate Analysis 10 sqm. is used
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 1.25 828.00 1,035.00
Unskilled md 2.00 586.50 1,173.00
Total - A 2,208.00
B Materials
cement MT 0.13 14,200.00 1,846.00
sand cu 0.18 2,200.00 396.00
12mm aggregate cu 0.36 1,850.00 666.00
Total -B 2,908.00
C Equipments

Total -C
Total (A+B+C) : 5,116.00
D Add 15% Contractor's OHP 767.40
Total (A+B+C+D) : 5,883.40
Rate per sq.m 588.34
Rate per sq.ft 54.68

Cement Sand Skirting 5" ht.

S.No. Particulars Unit Quantity Rate Amount


Cement skirting rm. 1.00 63.95 63.95
Total 63.95
B Add 15% Contractor's OHP 9.59
Total (A+B) : 73.54
Rate per linear meter of cement skirting = 73.54
Rate per linear feet of cement skirting = 22.42

133 Flooring of 25mm -37.5mm thick stone( flagstone) with 1:4 cement sand mortar.
11-9 For Rate Analysis 10 sqm.
H9
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 2.00 828.00 1,656.00
Unskilled md 4.50 586.50 2,639.25
Total - A 4,295.25
B Materials
37.5mm stone sqm 11.00 990.00 10,890.00
cement MT 0.06 14,200.00 852.00
sand from river cum 0.17 2,200.00 363.00
Total -B 12,105.00
C Equipments

Total -C
Total (A+B+C) : 16,400.25
D Add 15% Contractor's OHP 2,460.04
Total (A+B+C+D) : 18,860.29

East West Engineering Service Pvt. Ltd Civil Works: Page 9 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Rate per sq.m 1,886.03


Rate per sq.ft 175.28

Hardened Concrete Floor 38mm thick IPS Floor Finish with Floor Hardner (per 10 sq.m.)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 1.25 828.00 1,035.00
Unskilled md 2.00 586.50 1,173.00
Total - A 2,208.00
B Materials
Cement mt. 0.13 14,200.00 1,846.00
Sand cu.m. 0.18 2,200.00 396.00
Aggregate cu.m. 0.36 1,850.00 666.00
Floor Hardner kg. 30.00 119.00 3,570.00
Total - B 6,478.00
C Equipment/Others
Electrical Floor Finisher, etc. 2.00% 44.16
Total - C 44.16
Total (A+B+C) : 8,730.16
D Add 15% Contractor's OHP 1,309.52
Total (A+B+C+D) : 10,039.68
Rate per sq.m. of Hardened Concrete floor finish = 1,003.97

Terrazzo Cast-in Situ Dado For 10 sq.m


S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 3.50 828.00 2,898.00
Unskilled md 3.60 586.50 2,111.40
Total - A 5,009.40
B Materials
Cement mt. 0.089 14,200.00 1,263.80
Sand cu.m. 0.122 2,200.00 268.40
White Cement mt 0.089 32,500.00 2,892.50
Marble chips cu.m 0.061 10,000.00 610.00
Oxalic acid kg 0.37 190.00 70.30
Wax polish kg 0.118 200.00 23.60
Terpentine Oil ltr 0.538 208.00 111.90
Carbondum stoe LS

Total - B 5,240.50
C Equipment/Others
Electrical Floor Finisher, etc. -
Total - C -
Total (A+B+C) : 10,249.90
D Add 15% Contractor's OHP 1,537.49
Total (A+B+C+D) : 11,787.39
Rate per sq.m. = 1,178.74

169 12.5mm thick plastering of cement sand mortar of ratio 1:4 on ceiling.
I1 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours

East West Engineering Service Pvt. Ltd Civil Works: Page 10 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Skilled md 15.00 828.00 12,420.00


unskilled md 20.00 586.50 11,730.00
Total - A 24,150.00
B Materials
Cement MT 0.54 14,200.00 7,639.60
Sand from river Cum 1.46 2,200.00 3,212.00

Total -B 10,851.60
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 35,001.60
D Add 15% Contractor's OHP 5,250.24
Total (A+B+C+D) : 40,251.84
Rate per Sq.m. 402.52
Rate per Sq.ft. 37.41

176 20mm thick plastering of cement sand mortar of ratio 1:6.


I4 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 14.00 828.00 11,592.00
unskilled md 19.00 586.50 11,143.50
Total - A 22,735.50
B Materials
Cement MT 0.57 14,200.00 8,094.00
Sand from river Cum 2.35 2,200.00 5,170.00

Total -B 13,264.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 35,999.50
D Add 15% Contractor's OHP 5,399.93
Total (A+B+C+D) : 41,399.43
Rate per Sq.m. 413.99
Rate per Sq.ft. 38.48

180 Flush Pointing on Brick wall by cement sand mortar of ratio 1:2
I8 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 10.50 828.00 8,694.00
unskilled md 12.00 586.50 7,038.00
Total - A 15,732.00
B Materials
cement MT 0.21 14,200.00 2,982.00
Sand from river Cum 0.29 2,200.00 638.00
Total -B 3,620.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 19,352.00

East West Engineering Service Pvt. Ltd Civil Works: Page 11 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

D Add 15% Contractor's OHP 2,902.80


Total (A+B+C+D) : 22,254.80
Rate per Sq.m. 222.55
Rate per Sq.ft. 20.68

182 Pointing Work in Stone Masonry with Cement Mortar (1:2)


I9 For Rate Analysis 100 sqm.
S.No.. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 10.00 828.00 8,280.00
Unskilled md 14.00 586.50 8,211.00
Total - A 16,491.00
B Materials
Cement mt 0.41 14,200.00 5,793.60
Sand Cu.m 0.57 2,200.00 1,254.00
Total -B 7,047.60
C Equipments

Total -C
Total (A+B+C) : 23,538.60
D Add 15% Contractor's OHP 3,530.79
Total (A+B+C+D) : 27,069.39
Rate per sq.m 270.69
Rate per sq.ft 25.16

196 Two coat distempering


J2 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 5.80 828.00 4,802.40
unskilled md 5.80 586.50 3,401.70
Total - A 8,204.10
B Materials
Astar kg 8.00 360.00 2,880.00
Distemper powder kg 11.50 220.00 2,530.00
Total -B 5,410.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 13,614.10
D Add 15% Contractor's OHP 2,042.12
Total (A+B+C+D) : 15,656.22
Rate per Sq.m. 156.56
Rate per Sq.ft. 14.55

199 One coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 8.00 828.00 6,624.00
unskilled md 5.00 586.50 2,932.50

East West Engineering Service Pvt. Ltd Civil Works: Page 12 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Total - A 9,556.50
B Materials
Astar Ltr 8.10 360.00 2,916.00
Readymade paint Ltr 9.00 450.00 4,050.00
Total -B 6,966.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 16,522.50
D Add 15% Contractor's OHP 2,478.38
Total (A+B+C+D) : 19,000.88
Rate per Sq.m. 190.01
Rate per Sq.ft. 17.66

200 Two coat ready enamel painting (including one coat primer)
J4 Rate analysis per 100 Sqm

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 12.00 828.00 9,936.00
unskilled md 8.00 586.50 4,692.00
Total - A 14,628.00
B Materials
Astar Ltr 8.10 360.00 2,916.00
Readymade paint Ltr 16.00 450.00 7,200.00
Total -B 10,116.00
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 24,744.00
D Add 15% Contractor's OHP 3,711.60
Total (A+B+C+D) : 28,455.60
Rate per Sq.m. 284.56
Rate per Sq.ft. 26.45

206
J26 Two coats weather coat (apex or similar) with one coat primer painting work
For rate analysis 100sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 5.80 828.00 4,802.40
Unskilled md 5.80 586.50 3,401.70
Total - A 8,204.10
B Materials
Astar litre 8.00 240.00 1,920.00
Weather coat litre 16.00 650.00 10,400.00
Total -B 12,320.00
Total (A+B) : 20,524.10
C Add 15% Contractor's OHP 3,078.62
Total (A+B+C) : 23,602.72
Rate per s.qm= 236.03
Rate per s.ft= 21.94

227
Double coating aluminium paint excluding astar
East West Engineering Service Pvt. Ltd Civil Works: Page 13 of 21
SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

J21 Double coating aluminium paint excluding astar


For rate analysis 100sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 7.75 828.00 6,417.00
Unskilled md 7.75 586.50 4,545.38
Total - A 10,962.38
B Materials
Ready made aluminium paint litre 10.76 500.00 5,380.00
Abrasive 4.00 10.00 40.00
5,420.00
Total (A+B) : 16,382.38
C Add 15% Contractor's OHP 2,457.36
Total (A+B+C) : 18,839.73
Rate per s.qm= 188.40
Rate per s.ft= 17.51

238
Providing and applying Dustban/Permise chemicals for Anti Termite Treatment all complete
J29
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials
Providing and applying
Dustban/Permise chemicals for sqm 10.00 412.50 4,125.00
Anti Termite Treatment all
complete.
Total 4,125.00
B Add 15% Contractor's OHP 618.75
Total (A+B) 4,743.75
Rate per s.qm= 474.38
Rate per s.ft= 44.09

245
K4 Laying one layer 500 gauge polyethene sheet
For rate analysis 10sqm is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.60 828.00 496.80
Unskilled md 0.60 586.50 351.90
Total - A 848.70
B Materials
Polyethene sheet 500 gauge sqm 11.00 83.00 913.00
913.00
Total (A+B) : 1,761.70
C Add 15% Contractor's OHP 264.26
Total (A+B+C) : 2,025.96
Rate per s.qm= 202.60
Rate per s.ft= 18.83

Constructing,Painting 3x20 mm metal grills with red oxide and rubbing with abrasive material and also
278 fixing
M1 For Rate analysis 10sq.m is taken
S.No. Particulars Unit Quantity Rate Amount
A Materials

East West Engineering Service Pvt. Ltd Civil Works: Page 14 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

3x20mm metal grill construction


and fixing sq.m 10.00 2,017.50 20,175.00
Total 20,175.00
B Add 15% Contractor's OHP 3,026.25
Total (A+B) : 23,201.25
Rate per sq.m 2,320.13
Rate per sq.ft 215.63

Note: 1.00sq.m=16.14kg

280
M4 For Rate analysis 18.94kg is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.69 828.00 568.84
Unskilled md 0.78 586.50 458.06
Total - A 1,026.89
B Materials
Different types of steel angles kg 18.94 85.00 1,609.90
primer paint LS 110.00
Total -B 1,719.90
Total (A+B) 2,746.79
C Add 15% Contractor's OHP 412.02
Total (A+B+C) : 3,158.81
Rate per kg 166.78
Metal spiral stairway:Using 4"-6" dia medium class black pipe post than in 2/4"x2/4" scawire using
medium class 1 1/4" dai black pipe handrail 2'-2'6" width metal spiral stair with necessary materials
287
M11 For Rate analysis 18.94kg is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.69 828.00 568.84
Unskilled md 0.78 586.50 458.06
Total - A 1,026.89
B Materials
All types of black pipes making and kg 18.94 95.00 1,799.30
Primer paint Ls 110.00
Total -B 1,909.30
Total (A+B) 2,936.19
C Add 15% Contractor's OHP 440.43
Total (A+B+C) : 3,376.62
Rate per kg 178.28

Structural Steel Works


For Rate analysis 18.94kg is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 0.69 828.00 568.84
Unskilled md 0.78 586.50 458.06
Total - A 1,026.89
B Materials
All types of Structural Steel makin kg 18.94 105.00 1,988.70
Primer paint Ls 110.00
Total -B 2,098.70

East West Engineering Service Pvt. Ltd Civil Works: Page 15 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Total (A+B) 3,125.59


C Add 15% Contractor's OHP 468.84
Total (A+B+C) : 3,594.43
Rate per kg 189.78

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 0.00
Unskilled md 0.00
Total - A 0.00
B Materials
Materail With Fixing r.m 1.00 667.61 667.61
Fitting Charge Ls 1.00 250.00 250.00
Total -B 917.61
Total (A+B) 917.61
C Add 15% Contractor's OHP 137.64
Total (A+B+C) : 1,055.25
Rate per r.m 1,055.25

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 0.00
Unskilled md 0.00
Total - A 0.00
B Materials
Materail With Fixing sq.m 1.00 3,332.74 3,332.74
Ls
Total -B 3,332.74
Total (A+B) 3,332.74
C Add 15% Contractor's OHP 499.91
Total (A+B+C) : 3,832.65
Rate per sq.m 3,832.65

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 0.00
Unskilled md 0.00
Total - A 0.00
B Materials
Materail With Fixing sq.m 1.00 5,913.24 5,913.24
Ls
Total -B 5,913.24
Total (A+B) 5,913.24
C Add 15% Contractor's OHP 886.99
Total (A+B+C) : 6,800.22
Rate per sq.m 6,800.22

A Metal Railing, For Rate Analysis 6.5X0.95 is used

East West Engineering Service Pvt. Ltd Civil Works: Page 16 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

S.No. Particulars Unit Quantity Rate Amount


A Materials
Mild Steel Sections Pipe
40mm dia Hand Rail kg 21.78 196.11 4,270.25
25mm square Horizontal Pipe kg 22.81 196.11 4,472.59
32mm dia Vertical Pipe kg 18.53 196.11 3,632.90
100x100x6 mm Base Plate kg 2.83 215.72 609.62
M12 Bolt 75mm (Nos.) nos 24.00 27.00 648.00
Bends - -
25 mm square pipe nos 4.00 150.00 600.00
40 mm dia Pipes nos 1.00 225.00 225.00
Painting works sq.m. 5.85 190.01 1,111.55
Total - A 15,569.91
B Fixing in Position
Cutting & fixing charge -
Total - B -
Total (A+B) : 15,569.91
C Add 15% Contractor's OHP 2,335.49
Total (A+B+C) : 17,905.40
Rate per linear meter of custom made 900 mm high Mild Steel Railing = 2,754.68
Rate per linear Feet of custom made 900mm high Mild Steel Railing = 839.64
Rate per sq.m of custom made 900mm high Mild Steel Railing = 3,060.75
Rate per kg of Raling only 283.73

Cement Board Partation


2" thick boars(per 12 sq.m)
S.No. Particulars Unit Quantity Rate Amount
A Labours
Fixing Charge Sq.m 12.00 828.00 9,936.00

Total - A 9,936.00
B Materials
Cement Board Sq.m 27.00 344.32 9,296.64
Fixture R.m 15.40 450.00 6,930.00
Joint Filling R.m 36.00 125.00 4,500.00
Total - B 20,726.64
C Equipment/others
LS 150.00
Total - C 150.00
Total (A+B+C) : 30,812.64
D Add 15% Contractor's OHP 4,621.90
Total (A+B+C+D) : 35,434.54
Rate per sq.m. of V-board = 2,952.88

6.14 Gypsum Board False Ceiling (per 103.79 sq.m.)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 40.00 828.00 33,120.00
Unskilled md 70.00 586.50 41,055.00
Total - A 74,175.00
B Materials
Cement Board sq.m. 109.00 344.32 37,530.88

East West Engineering Service Pvt. Ltd Civil Works: Page 17 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Ceiling Sections rm. 242.00 90.00 21,780.00


Perimeter Channel rm. 42.00 55.00 2,310.00
Intermediate Channel rm. 91.50 90.00 8,235.00
Strap Hanger nos. 11.00 75.00 825.00
Connection Clips nos. 190.00 12.00 2,280.00
6 mm dia. Nuts & bolts nos. 22.00 5.00 110.00
Soffit Cleats nos. 75.00 6.50 487.50
Joint Filler kg. 24.00 50.00 1,200.00
Joint Finisher kg. 35.00 71.00 2,485.00
Joint Tape roll 1.50 280.00 420.00
12 mm dia. 40 mm long with 6mm
dia. Bolt dash fastener nos. 75.00 15.00 1,125.00
Total - B 78,788.38
C Equipment/others

Add 5% for cutting channels, angle


iron, drilling holes, welding, rebating 5.00% 3,708.75
Total - C 3,708.75
Total (A+B+C) : 156,672.13
D Add 15% Contractor's OHP 23,500.82
Total (A+B+C+D) : 180,172.95
Rate per sq.m. of Cement Board False Ceiling = 1,735.94
Rate per sq.ft. of Cement Board False Ceiling = 161.33

256
L1
Demolition of wall on mud and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 1.06 586.50 621.69
Total 621.69
B Add 15% Contractor's OHP 93.25
Total (A+B) 714.94
Rate per cu.m= 714.94
Rate per s.ft= 20.25

257
L2
Demolition of wall on cement and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount
A Labours
Unskilled No. 2.12 586.50 1,243.38
Total 1,243.38
B Add 15% Contractor's OHP 186.51
Total (A+B) 1,429.89
Rate per cu.m= 1,429.89
Rate per s.ft= 40.50

258
L3
Demolition of RCC and RBC works and disposal of waste at a distance of 10m
For rate analysis 1cum is taken
S.No. Particulars Unit Quantity Rate Amount

East West Engineering Service Pvt. Ltd Civil Works: Page 18 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

A Labours
Unskilled No. 11.00 586.50 6,451.50
Total 6,451.50
B Add 15% Contractor's OHP 967.73
Total (A+B) 7,419.23
Rate per cu.m= 7,419.23
Rate per s.ft= 210.12

Dismantling of completely damaged building and disposing the debris including Transportation. For
Rate Analysis 100 sq.m is used
S.No. Particulars Unit Quantity Rate Amount
A Labours

Total - A 0.00
B Materials
Stone Masonry cu.m 47.70 714.94 34,102.80
Slab Dismanteling cu.m 10.00 3,709.61 37,096.13
Transportation cu.m 57.70 476.69 27,504.72

Total -B 98,703.65
C Equipments
0.00
Total -C 0.00
Total (A+B+C) : 98,703.65
D Add 15% Contractor's OHP 14,805.55
Total (A+B+C+D) : 113,509.20
Dismantling of Damaged Building per sq.m 1,135.09
Dismantling of Damaged Building per sq.ft 105.49

Hollow Concrete Block Wall


A 150x200x400

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 0.25 828.00 207.00
Unskilled md 0.25 586.50 146.63
Total - A 353.63
B Materials
150x200x400 mm Hollow No. 13.00 47.00 611.00
concrete Block
Cement m.t 0.01 14,200.00 198.80
Sand cu.m 0.04 2,200.00 96.80
Water Li 12.00 0.30 3.60
Total -B 910.20
Total (A+B) 1,263.83
C Add 15% Contractor's OHP 189.57
Total (A+B+C) : 1,453.40
Rate per sq.m 1,453.40

8.2 Providing & fixing in position Glazed Ceramic Tile on wall using tile adhesive and grout
(per 10 sq.m.)
S.No. Particulars Unit Quantity Rate Amount
A Labours
Skilled md 13.00 828.00 10,764.00
Unskilled md 4.50 586.50 2,639.25

East West Engineering Service Pvt. Ltd Civil Works: Page 19 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Total - A 13,403.25
B Materials
Cement mt. 0.056 14,200.00 795.20
Sand cu.m. 0.15 2,200.00 334.40
White cement kg. 3.23 26.12 84.32
Ceramic Glazed Tile sq.m. 10.48 1,076.00 11,276.48
border tile sq.m. 0.52 -
Total - B 12,490.40
C Equipment/others
-
Total - C -
Total (A+B+C) : 25,893.65
D Add 15% Contractor's OHP 3,884.05
Total (A+B+C+D) : 29,777.69
Rate per sq.m. of Glazed Ceramic Tile on Wall = 2,977.77
Rate per sq.ft. of Glazed Ceramic Tile on Wall = 276.74

5.1 Non-Skid Vitrified Ceramic Tile (per 10 sq.m.)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 13.00 828.00 10,764.00
Unskilled md 4.50 586.50 2,639.25
Total - A 13,403.25
B Materials
Non-Skid Vitrified Ceramic Tile sq.m. 11.00 1,076.00 11,836.00
Cement mt. 0.06 14,200.00 795.20
Sand cu.m. 0.15 2,200.00 334.40
White cement with pigment kg. 3.23 32.50 104.91
Total - B 13,070.51
C Equipment
-
Total - C -
Total (A+B+C) : 26,473.76
D Add 15% Contractor's OHP 3,971.06
Total (A+B+C+D) : 30,444.82
Rate per sq.m. of Non-Skid Vitrified Ceramic Tile Flooring = 3,044.48

Coloured GI Gutter: Providing and fixing in position 100 mm x 450 mm overall


trapizoidal
S.No. type Pre-finished colour G.I. Sheet gutter with
Particulars Unit G.I. brackets
Quantity 40 x 3Rate
mm size Amount
A Labours
skilled md 1.75 828.00 1,449.00
unskilled md 2.00 586.50 1,173.00
Total - A 2,622.00
B Materials
24 gauge colour sheet m 13.50 241.02 3,253.77
Brackets no 32.00 81.54 2,609.28
10 mm bolts to fix bracket no 48.00 9.50 456.00
Bitumen Washer no 48.00 3.00 144.00

Total - B 6,463.05
C Equipment/others

East West Engineering Service Pvt. Ltd Civil Works: Page 20 of 21


SEED STORAGE, Kiwool, Sindhupalchowk Rate Analysis, Sindupalchowk,(2072-2073)

Scaffolding & carriage -


Contingency -
Total - C -
Total (A+B+C) : 9,085.05
D Add 15% Contractor's OHP 1,362.76
Total (A+B+C+D) : 10,447.81
Rate per linear meter of G.I. Gutter = 822.66

5.2 50 thk. Cement Concrete Flooring (1:2:4) with Neat Cement Finishing (per 10 sq.m.)

S.No. Particulars Unit Quantity Rate Amount


A Labours
Skilled md 1.64 828.00 1,361.84
Unskilled md 2.63 586.50 1,543.42
Total - A 2,905.26
B Materials
Cement mt. 0.17 14,200.00 2,428.95
Sand cu.m. 0.24 2,200.00 521.05
12 mm Aggregates cu.m. 0.47 1,850.00 876.32
Total - B 3,826.32
C Equipment/Others
- -
Total - C -
Total (A+B+C) : 6,731.58
D Add 15% Contractor's OHP 1,009.74
Total (A+B+C+D) : 7,741.32
Rate per sq.m. of cement concrete flooring = 774.13

7 MOISTURE PROTECTION WORKS


7.1 Water Proofing Works Crystallization System Providing & Applying MC-Dichtament
DS+Nafufill BB2 by coating system on new & old concrete structures (per 1 sq.m.)
S.No. Particulars Unit Quantity Rate Amount
A Materials & Labours
Material + Labour complete sq.m. 1.00 753.20 753.20
Total - A 753.20
B Add 15% Contractor's OHP 112.98
Total (A+B) : 866.18
Rate per sq.m. of waterproofing coating works = 866.18

East West Engineering Service Pvt. Ltd Civil Works: Page 21 of 21

You might also like