Professional Documents
Culture Documents
Comisionamiento de Plantas Mineras
Comisionamiento de Plantas Mineras
COMMISSIONING
LARSEN & TOUBRO LIMITED
E & C DIVISION
SAFETY CONTROL DEPARTMENT
POWAI
E & C Division
Contents
Part III: Commissioning of plant
1. Corporate Policy
2. Safety responsibilities
2.1 Safety Control Department
2.2 Commissioning Team Leader
2.3 Commissioning Team members
3. Rules and regulations
3.1 Safety practices operating personnel
4.
5.
Plant Layout
Alarms / Trips / Interlocks
Control Systems
Corrosion / Selection of Materials
5.5
5.6
5.7
E & C Division
6.
7.
8.
8.6
9.
10.
11.
Contents
To Engineer and Execute projects with consistent quality, cost and delivery in
line with the requirements of our customers, and to exceed or meet their
expectations, whilst enhancing our shareholder value.
2.
3.
4.
5.
6.
7.
To comply with all applicable occupational Health & Safety legislation and
continually improve safe working practices through setting health and safety
objectives and ensure good health, safety and security of all our people, our
biggest asset.
8.
9.
10.
_____________________________
K . VENKATARAMANAN
E & C Division
2.
SAFETY RESPONSIBILITIES
2.1
The
of
the
Safety
Control
is
to
develop
safety
The commissioning team is familiar with the process hazards and the
hazards of chemicals being used / handled during commissioning. The
Safety Control will assist SBU for the procurement of Personnel
Protective Equipment.
Identifying
the
requirement
of
safety
equipment
and
____________________________________________________
Responsibility
1
E & C Division
Organise
regular
safety
meetings
with
client
safety
____________________________________________________
Responsibility
2
E & C Division
2.2
of
the
commissioning
team
and
the
facility
being
commissioned.
3. The CTL will ensure that:
a) The HSE manual for commissioning is accessible to the
commissioning team.
b) The Personnel Protective Equipment necessary for the safe
execution of job is inspected and is in order.
c) The
commissioning
team
members
are
briefed
on
the
7. The CTL will, before the start of commissioning, ensure that the
safety audit (Check) of the plant is completed and the checklist
neutralized (Corrective action completed).
____________________________________________________
Responsibility
3
E & C Division
8. The CTL will ensure that the commissioning team members are
aware of overall plot plan and familiar with the emergency escape
routes.
9. The CTL will ensure that a mock emergency drill is conducted and
emergency procedures followed.
10. The CTL will ensure before undertaking the commissioning that he
has all emergency phone numbers with him.
11. The CTL will ensure that he has the copy of the "On-site Emergency
Management Plan " and is conversant with its requirements.
____________________________________________________
Responsibility
4
E & C Division
2.3
__________________________________________________
Responsibility
5
E & C Division
specific
safety
rules
are
provided
by
the
client,
(the
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
14.
15.
Use of approved safety lights and torches. Use of only flame proof
24 V portable lamps inside tanks / confined locations.
____________________________________________________
Rules & Regulations
1
E & C Division
16.
17.
18.
Use of only authorized vehicles only with in the plant premises and
to driven by licensed persons within the speed limits.
19.
20.
21.
22.
23.
____________________________________________________
Rules & Regulations
2
E & C Division
2.
3.
4.
Safety clearance procedure: Any work carried out within the plant
must be covered by the work permit system prevailing in the
plant- Following types of work normally require work permits.
A.
Any work involving open flame and sparks such as welding, gas
cutting, soldering, grinding (hot working).
B.
C.
D.
E.
5.
F.
G.
Radiography
H.
6.
7.
__________________________________________________
Rules and Regulations
3
E & C Division
8.
9.
10.
11.
12.
13.
All electrical equipment used are properly grounded and fitted with
proper 3 pin plugs. All cables in one piece preferable.
14.
15.
16.
__________________________________________________
Rules and Regulations
4
E & C Division
4.
Pipework erection
All pipes shall be inspected before erection to ensure that they are free
from loose contamination.
Pipework shall be erected on permanent supports designated for the
line. Temporary supports shall be kept to an absolute minimum, but to
an extent sufficient to protect nozzles and adjacent piping from
excessive loads during the erection.
Pipework shall be fitted in place without springing or forcing to avoid
undue stressing of the line or strain being placed on a vessel or item of
equipment, etc.
All temporary pipe spools and supports that are an aid to erection,
testing/flushing, sea fastening, etc. are to be specially marked for
removal identification.
Flanged joints
Before assembly flanges shall be clean and free from any detritus
matter (e.g. rust, dirt or other contamination). The joints shall be
brought up flush and square without forcing so that the entire mating
surfaces bear uniformly on the gasket and then mated-up with uniform
bolt tension.
__________________________________________________
Precommissioning Activities
1
E & C Division
Gaskets
Gaskets
shall
be
treated
in
accordance
with
manufacturers'
Bolting
Bolting shall be in accordance with the requirements in the Piping and
valve material standard.
Manually pulled flange bolts and studbolts shall extend fully through
their nuts with minimum one, maximum five threads.
All flanged stud bolts shall be progressively controlled to equalise bolt
pressure on the gasket. A detailed procedure shall be developed prior
to start.
Hydraulic bolt thigthening shall be used on all bolts greater than 1"
diameter.
Calculation of the required bolt tension value shall be in accordance
with the DIN 2505, with the following exeptions:
Minimum required bolt tension value shall be multiplied with 1.5.
__________________________________________________
Precommissioning Activities
2
E & C Division
Maximum bolt tension value shall not exceed 2/3 of the specified
yield of the bolt or maximum allowable stress for the gasket.
Nuts and bolts shall have their grade marks visible after installation.
Studbolts cut from long lengths of studding shall have material grade
stamped on end of each cut.
Bolts larger than 1" shall be protected against mechanical damage and
corrosion.
Pipe support
Pipe supports shall be in accordance with the relevant pipe support
detail drawings developed for the project.
Piping shall not be forced to fit with support locations in such a manner
that additional stress is introduced.
Where spring support are installed the spring shall locked gagged until
commissioning/start up.
All piping shall be arranged to facilitate supporting, and shall be
planned for ease of removal of equipment for inspection and servicing.
Pipes shall not normally be supported by other pipes, i.e. individual
supporting is required.
Vent holes in wear plates and trunnions are generally not required.
However, when the wear plate or a trunnion covers a circumferential
weld that has not been pressure tested, a vent hole is required for leak
detection.
Maintenance access.
E & C Division
Pipe stress.
FLUSHING
General
The initial flushing shall be carried out prior to pressure testing. For
austenitic steelwork flushing can be performed after pressure testing,
upon agreement.
General requirements for flushing for specific systems are listed in
table 1, annex B.
Procedures for flushing shall be developed prior to start.
All pipework shall be free from dirt, grease and temporary protective
coating upon completion of flushing.
Hydro flushing
Items of equipment that would be sensitive to damage during hydro
flushing shall be removed, blocked off or isolated. A list shall be
prepared and be part of the flush & test procedure.
Ball valves shall be flushed in fully open position.
All piping systems shall be flushed using high-pressure jet flushing
equipment, such as rotating hose or rotating nozzle. Minimum
pressure shall be 600 bar.
Below 4", High Velocity Water Flushing (HVWF) may be used. Water
velocity shall be a minimum of 10m/s. On systems where high
pressure jet flushing cannot be used due to complicated shapes and/or
long runs HVWF may be used.
The flushing medium shall in general be fresh water. When flushing
stainless steel lines, the chloride ion content shall be less than 200
ppm.
After flushing, the piping systems shall be completely drained and
protected against corrosion.
__________________________________________________
Precommissioning Activities
4
E & C Division
Pneumatic flushing
In cases where water is not desirable in the piping system (e.g.
instrument/utility air), flushing by pressurised air or PAS shall be
carried out. When pressurised air is used, the minimum velocity shall
be 35m/s. Procedure covering all safety aspects shall be established.
PRESSURE TESTS
General
The test pressure shall, unless otherwise specified, be in accordance
with ASME B31.3.
Testing shall not take place with system temperatures 4C or less or
where the ambient temperature during test falls by 5C or more, nor
during rain or fog unless under suitable cover. Hydrostatic pressure
test may however be performed under a lower temperature with a
proper frost preventive added to the test water.
The following are excluded from pressure tests:
__________________________________________________
Precommissioning Activities
5
E & C Division
Test preparation
Pressure, temperature and time recorders shall be used for all
hydrostatic tests. The pressure shall be shown in bar. Pressure gauges
and recorders used to indicate and record test pressure shall be dead
weight tested for accuracy according to a procedure, dependent of
type of equipment.
Minimum of one gauge shall be positioned at the highest point and one
recorder to be positioned at the lowest point. Accuracy of pressure
gauge shall be at least 1-2% at full scale and 1-2% for the recorder.
The test pressure shall be within 60% of the gauge range (20% from
top and 20% from bottom).
If there is a deviation of more than 2% between gauge and recorder
during test, the test shall be stopped and the equipment recalibrate.
Piping joints and welds shall not be insulated or physically covered
until satisfactory completion of testing in accordance with this
specification, except for painting of prefabricated welds.
All piping shall be adequately supported before the pressure test.
Spring or other variable type supports shall be blocked to prevent
movement.
Unless otherwise noted, all valves are to be through body tested. First
block valve for pressure instruments shall be included in the test.
Piping containing check valves shall have the source of test pressure
on the upstream side. If this is not possible, the check valve disc shall
be removed or jacked open.
Ball valves shall be pressure tested in the half open position. Other
valves shall be tested in the fully open position.
Where the test pressure to be applied to the piping is greater than the
maximum allowable test pressure for valves, the valves shall be
blinded off on the side to be tested, or removed and replaced by
dummy spools.
__________________________________________________
Precommissioning Activities
6
E & C Division
Test media
For hydrostatic testing the test medium shall in general be fresh
water, except that other suitable liquid may be used if:
The chloride ion content of the water used for pressure testing
stainless steel lines shall be less than 200 ppm and the line shall be
properly drained soon after testing. pH value of the water shall be
between 6.5 and 7.5.
Carbon steel systems as defined in table 1, annex B shall be tested
with an acceptable preservation fluid. The preservation fluid shall be a
water impellent and emulsifiable rust preventive lubricating oils that
contain detergents and inhibitors that have been specially formulated
to prevent rust.
For pneumatic testing, the test media shall be oil free, dry air or any
inert gas. The use of air for testing shall be limited to a maximum
pressure of 7.0 barg. Above this pressure nitrogen shall be used. The
extent of pneumatic testing shall be approved.
For instrument/utility air systems, where the introduction of water is
undesirable, test media shall be air or inert gas.
__________________________________________________
Precommissioning Activities
7
E & C Division
Hydrostatic testing
The test pressure shall be maintained for a sufficient length of time to
permit visual examination to be made of all surfaces, welds and
connections, but not less than thirty minutes. A one hour test duration
shall apply for piping systems with pressure rating class 600# and
above. Care shall be taken to ensure that overpressuring due to static
head does not take place.
The piping systems shall not show any sign of plastic deformation or
leakage.
Pneumatic testing
The sequence of test pressuring installed systems shall be as follows:
The specified test pressure shall be kept for one hour. The
pressure shall than be reduced to the design pressure before
examining for leakage.
The piping systems shall not show any sign of plastic deformation or
leakage.
tested
systems
shall
be
depressurised
by
opening
the
E & C Division
Verification of cleanliness
All systems shall be internal visual inspected for acceptable cleanliness
by spot check. Internal visual inspection includes the use of
Boroscope, video etc.
If pipe configuration in critical parts of systems as defined in table 1,
annex B is too complicated for visual inspection, the PAS method or
other suitable methods shall be used for verification of cleanliness.
__________________________________________________
Precommissioning Activities
9
E & C Division
CHEMICAL CLEANING
Lines to be chemical cleaned shall be identified on the P&ID's and Line
Index.
A procedure shall describe in detail the steps for chemical cleaning.
Chemical cleaning shall include:
Degassing.
Chemical cleaning/descaling.
Neutralisation.
Passivation.
Water flushing.
Drying.
Flexible hoses.
Vessels.
Exchangers.
Pumps.
__________________________________________________
Precommissioning Activities
10
E & C Division
The systems to be cleaned shall have high and low point vents and
drains installed. "Dead legs" shall be avoided.
Cleaning shall be carried out after pressure testing unless otherwise
specified.
If more than 3 months to start up of commissioning activities, system
shall be preserved with nitrogen. Overpressure shall be 0.5 bar.
Filling of lubricant oil shall take place through filters with 10m ABS.
Flushing and sampling to verify cleanness shall take place at turbulent
flow, upstream any filters.
The Reynolds number shall be min. 4000.
The level of cleanness shall be documented from an automatic particle
counter or a membrane checked in a microscope before a flushing
operation is considered finalised.
A flowmeter shall be installed to verify flow used during flushing
operation.
Maximum water content in oil used for flushing shall be less than
500ppm.
Marking
Piping spools or systems that have been chemical cleaned or hot oil
flushed shall be marked in a unique manner.
__________________________________________________
Precommissioning Activities
11
E & C Division
5.1
Plant Layout
The most important factors of plant layout as far as safety aspects are
concerned are those to:
E & C Division
E & C Division
Fire
A fire can spread in four ways:
Direct burning (including running liquid fires);
Convection;
Radiation;
Conduction.
The spread of fire from its origin to other parts of the premises can be
prevented by vertical and horizontal compartmentation using fireresisting walls and floors. Consideration should also be given to the
spread of flammable material via drains, ducts and ventilation systems.
Delayed ignition following a release may result in spread of flames
through such systems via dispersed flammable gases and vapours.
Protection against domino effects by convection, conduction and radiation
can be achieved by inherent safety principles i.e. ensuring that the
distances between plant items are sufficient to prevent overheating of
adjacent plants compromising safety of those plants also. Where this is
not possible due to other restrictions, other methods such as fire walls,
active or passive fire protection may be considered.
Explosion
Explosion propagation may be directly by pressure waves or indirectly by
missiles. As for fires, inherently safe methods that should be
considered are:
arranging separation distances such that damage to adjacent plants
will not occur even in the worst case;
E & C Division
inherently safer principles and a suitable control room (see section below
on Occupied Buildings).
Reduction
of
Consequences
of
Event
On
and
Off
Site
eliminated.
Risk management techniques should be used to identify control measures
that can be adopted to reduce the consequences of on or off site events.
See references cited in further reading material.
Positioning of Occupied Buildings
The distance between occupied buildings and plant buildings will be
governed by the need to reduce the dangers of explosion, fire and
toxicity. In particular, evacuation routes should not be blocked by poor
plant layout, and personnel with more general site responsibilities should
usually be housed in buildings sited in a non-hazard area near the main
entrance. Consideration should be given to siting of occupied buildings
__________________________________________________
Plant Layout
4
E & C Division
outside the main fence. In all cases occupied buildings should not be
sited downwind of hazardous plant areas.
Aggregation / Trapping of Flammable Vapours
To avoid aggregation and trapping of flammable / toxic vapours which
could lead to a hazardous event, buildings should be designed so that all
parts of the building are well ventilated by natural or forced ventilation.
Flammable storages should be sited in the open air so that minor leaks or
thermal outbreathing can be dissipated by natural ventilation.
Segregation of Incompatible Substances (particularly in warehouses /
storage areas)
This is detailed in the Technical Measures Document on Segregation of
Hazardous Materials.
__________________________________________________
Plant Layout
5
E & C Division
5.2
Alarm Systems
Alarm systems alert operators to plant conditions, such as deviation from
normal operating limits and to abnormal events, which require timely
action or assessment.
Alarm systems are not normally safety related, but do have a role in
enabling operators to reduce the demand on the safety-related systems,
thus improving overall plant safety.
However, where a risk reduction of better than 10-1 failures on demand is
claimed then the alarm system, including the operator, is a safety related
system,
which
requires
a
suitable
safety
integrity
level.
EEMUA 191 Alarm systems - a guide to design, management and
procurement considers alarm settings, the human interface (alarm
presentation), alarm processing and system management controls for
both safety related and other alarm systems. It provides the following
guidance in regard to safety related alarm systems:
E & C Division
the alarm system survives common cause failures, such as a power loss,
should also be adequately defined.
Alarm settings
The type of alarm and its setting should be established so as to enable
the operator to make the necessary assessment and take the required
timely action. Settings should be documented and controlled in
accordance
with
the
alarm
system
management
controls.
__________________________________________________
Alarms/Trips/Interlocks
2
E & C Division
Alarm processing
The alarms should be processed in such a manner as to avoid operator
overload at all times (alarm floods). The alarm processing should ensure
that fleeting or repeating alarms do not result in operator overload even
under the most severe conditions.
The presentation of alarms should not exceed that which the operator is
capable of acting upon, or alternatively the alarms should be prioritised
and presented in such a way that the operator may deal with the most
important alarms without distraction of the others. Applicable alarm
processing techniques include grouping and first-up alarms, eclipsing of
lower grade alarms (e.g. suppression high alarm when the high-high
activates) suppression of out of service plant alarms, suppression of
selected alarms during certain operating modes, automatic alarm load
shedding and shelving.
Care should be taken in the use of shelving or suppression to ensure that
controls exist to ensure that alarms are returned to an active state when
they are relevant to plant operation.
Alarm system management procedures
Management systems should be in place to ensure that the alarm system
is operated, maintained and modified in a controlled manner. Alarm
response procedures should be available, and alarm parameters should
be documented.
The performance of the alarms system should be assessed and monitored
to ensure that it is effective during normal and abnormal plant conditions.
The monitoring should include evaluation of the alarm presentation rate,
operator acceptance and response times, operator workload, standing
alarm count and duration, repeat or nuisance alarms, and operator views
of operability of the system. Monitoring may be achieved by regular and
systematic auditing.
Matters which are not worthy of operator attention should not be
alarmed.
__________________________________________________
Alarms/Trips/Interlocks
3
E & C Division
Systems
(Trips
and
Interlocks)
E & C Division
__________________________________________________
Alarms/Trips/Interlocks
5
E & C Division
E & C Division
(switches);
Use of positively actuated switches operating in a positive mode
together with idle current (de-energise to trip);
Proof testing procedures should clearly set out how sensors are
reinstated and how such reinstatement is verified after proof testing.
Maintenance procedures should define how sensors/transmitters are
calibrated with traceability back to national reference standards by use of
calibrated test equipment.
Other matters which will need to have been considered are:
Cross sensitivities of analysers to other fluids which might be
present in the process;
__________________________________________________
Alarms/Trips/Interlocks
7
E & C Division
Signal conditioning (e.g. filtering) and which may affect the sensor
response times;
Degradation of measurement signals (distance between sensor and
transmitter may be important);
__________________________________________________
Alarms/Trips/Interlocks
8
E & C Division
Overrating of equipment.
Valves should be properly selected for their duty, and it should not
be assumed that a control valve can satisfactorily perform isolation
functions;
Logic
systems
Commonly, the logic systems for protective systems are electronic, but
programmable
and
other
technology
fluidic/pneumatic) have been used.
systems
(magnetic
or
E & C Division
E & C Division
Utilities
Utilities which are required for the protective system to perform its safety
function may include power supplies such as electricity, air, inhibitor
materials and their propellants, inert gas such as nitrogen, cooling water,
steam, pilot flames and their gases all of which should be adequately
reliable. Measures such as redundancy, and uninterruptable/reservoir
supplies, and availability monitoring (e.g. loss of air alarm) may be
required. Confirmation that the designed capacity of reserves is adequate
should
be
demonstrated
by
test.
Utilities may also introduce external influences into the protective
systems
(e.g.
from
electrical
supplies).
Measures
to
protect
against
external
influences
may
include:
Proof testing
The probability of failure on demand, or the failure rate of a protective
system is critically dependent upon the frequency of proof testing and its
ability to detect previously unrevealed failures of the system. The proof
test interval should therefore be established accordingly, and as a rule of
thumb for low demand systems, should be an order of magnitude less
than the mean time between failure of the system and the demand rate.
Proof
test
procedures
should
be
available
which
specify
the
success/failure criteria and detail how the test will be performed safely,
including any management arrangements, operating restrictions and
competence of personnel.
The tests should be arranged to reveal all dangerous failures which have
been unrevealed in normal operation including the following measures:
__________________________________________________
Alarms/Trips/Interlocks
11
E & C Division
Operation
Procedures should be available which detail the operation of the
protective system including:
Override
management
(authorisation,
security,
recording,
monitoring and review of overrides, reset requirements);
Maintenance
Procedures should be available for maintenance activities including:
Maintenance instructions;
Control of spares (segregation of faulty or non-conforming parts,
identification to prevent interchange of similar parts etc.);
__________________________________________________
Alarms/Trips/Interlocks
12
E & C Division
Modification
A management system for control of modifications should be available to
ensure that:
Unauthorised modifications are prevented;
possible);
Potential for operation outside restricted mode under fault
conditions;
Protection of safety functions from unauthorised modification;
Change control;
Competence of personnel.
__________________________________________________
Alarms/Trips/Interlocks
13
E & C Division
SHE Manual (Commissioning)
____________________________________________________
5.3
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
and cost benefit used to determine if additional measures should be
applied.
In consideration of toxic gas releases the control room should provide a
safe haven for its occupants. This will include arranging that the building
is adequately sealed to prevent ingress of gases to levels of concentration
that will affect the health and thereby the ability of the operators to
maintain control of the plant. Careful consideration of the building
ventilation system is required to ensure that air intakes are situated away
from areas that may be affected or to arrange that there is no air intake
during an incident, preferably by closure of an automatic valve linked to a
gas analyser.
Measures for protection from fires should ensure the control room will
withstand thermal radiation effects without collapse and that smoke
ingress is controlled. Materials of construction should be fire resistant for
the duration of any possible fire event. Smoke ingress may be controlled
in a similar manner to toxic gas ingress.
Each of these methodologies should be applied to control rooms within
buildings as well as separate control buildings. Control panels on the
plant itself cannot be so easily be protected, therefore diversity and
redundancy should be applied to ensure that plant control can be
maintained in an emergency. Risk Assessments should be undertaken to
demonstrate that primary and secondary (domino) risks are within
acceptable limits.
Human Factors/Ergonomics
Operators should be able to demonstrate that appropriate human factors
considerations have been given to the design, commissioning, and
operation of control rooms under both normal and abnormal plant
operating conditions to reduce the frequency of human error due to
control room deficiencies.
It is vitally important that a control room and its operators are considered
as a whole system and not in isolation of each other. For example a well
designed control room for use by 4 operators is dangerous when staffed
by 3 operators. Similarly, the best-trained operators cannot guarantee
high reliability in a poorly designed control room.
Factors to be taken in account are included on the following paragraphs.
Environmental issues
Layout
Control room dimensions should take into account the 5th and 95th
percentile user.
______________________________________________________________________
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
Maintenance
Adequate access should be provided so that inadvertent operation
of equipment during maintenance is not possible.
Behind panel equipment should be appropriately coded to reduce
the potential for human error.
Thermal environment
Temperature and airflow should be adjustable. As a guide,
comfortable temperature for office work should be between 18.3C
and 20.0C with airflow between 0.11 and 0.15 m/s.
Visual
environment
Lighting should be such that it does not create veiling reflections on VDUs
or
other
reflective
surfaces
that
require
monitoring.
The type of lighting should be adequate for the task. i.e. for office work a
lux (lux is the unit of illuminance - measured using a light meter at the
work surface) figure of between 500 - 800 is suggested.
There should be no perceptible flicker from strip lighting.
______________________________________________________________________
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
It is desirable to provide adjustable lighting for control rooms that are
manned 24 hours a day. During night-time operation lighting is often
dimmed.
Windows in control rooms should not cause veiling reflections on
reflective surfaces. Adequate means of blocking out direct sunlight should
be provided.
Auditory environment
The average noise level within the control room shall not exceed 85
dB(A) during the length of the working day.
For office work a noise level below 40 dB(A) is not desirable as it can
cause interference between operators.
Prolonged, very low or very high frequency noises should be avoided.
Noise levels should not interfere with communications, warning signals,
mental performance (i.e. be distracting).
Man Machine Interface (MMI)
For mental workload, conditions of over and under-arousal should be
avoided. The duration of tasks that have an associated low or high level
of mental workload should be limited. Both these extremes will increase
the likelihood of human error affecting the system. The design of the MMI
should be based on a full Task Analysis.
An interface should provide the operator with the general following
information:
After initiating an action within a system the operator should be
clearly informed of the result of their action.
If there is a delay in the system that prevents the operator from
being informed of the result of his/her action, the system should
inform the operator of this fact.
If an action is made in error then it should be possible to reverse
such an action where it would not be detrimental to plant safety to
do so.
The system should inform the operator of any deviations from safe
operating levels.
Alarms
All employees and contractors on site should know what each alarm
means and what the required response is, if the cause of the alarm
has the potential to affect them.
An alarm should reset automatically if the fault that generated it is
rectified.
______________________________________________________________________
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
Coding techniques
Coding should follow international conventions. Arbitrary coding by
operators can actually propagate, rather than mitigate, human
error if not carried out correctly.
Coding should be consistent across plant.
Coding should be used appropriately.
Example methods of coding are:
Colour
Flash
Brightness
Inverse video/highlighting
Sound frequency
Sound type
Shape 2D/3D
Symbols
Coding should be used redundantly where colour is one of the
coding methods.
Designing displays
Text
The language used should always be capable of being easily
understood by the operator.
Active rather than passive language should be used.
Text should be left justified.
______________________________________________________________________
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
Sans serif fonts should be used as these have been found to be the
most legible. An example of a sans serif font is Ariel.
Labels
Labelling should be used consistently across plant.
Labels should be used appropriately.
The relationship between labels and the equipment they refer to
should be clear.
Labels should be easily read.
Standard abbreviations should be used where abbreviations are
required.
Display devices
Display devices should be appropriate for the type of information
they are presenting.
Display devices should be grouped logically to improve signal
detection. It is recommended that formal task analysis methods be
performed to determine the optimum arrangement for displays and
their associated controls.
The relationship between a control and its associated display should
be obvious.
The operator should be able to easily understand display feedback.
The response to this feedback should be obvious, wherever
possible.
The control method provided for navigation around displays should
be appropriate for the task.
Graphics
Appropriate presentation methods should be used for information.
A simple guide is presented below:
Method
Numeric
Bar
charts/analog
ue dials
Advantage
Accurate
quantitative
information
Quickly read
Easy to check
whether data is
within limits
Possible to mark
alarm limits
Displays rate of
change well.
Easily compared to
other similarly
presented data.
Disadvantage
Cannot illustrate rate of change or
approach to limit
Rapidly changing data is unreadable
Difficult to locate individual data
items if presented in a list or table.
Movement can potentially distract
operators.
Slow read time.
Inaccurate if numerical value has to
be derived.
______________________________________________________________________
Control System
E & C Division
SHE Manual (Commissioning)
____________________________________________________
Pictorial
displays
Trend
displays
Provides at a glance
appreciation of
operating conditions
Ideal for showing
plant configurations.
Can improve
operator situational
awareness of plant.
Ideal for presenting
continuously
changing
information.
Presents rate of
change in an easily
understood format.
Good for comparing
data plots
Provides historical
data over time
Anthropometry
Reach
Control desk/panels should conform to reach distances for the 5th
percentile operator.
Seating
Seating should be anthropometrically sound and should be usable
by both 5th and 95th percentile operators.
Adjustment should be provided to allow the operator set up the
chair to a configuration that is comfortable.
Seating should not promote a slumped posture.
Posture
The workstation should be designed so that it allows the operator to
regularly change their posture or move around the room. This
should not however, be during primary control duties or during an
emergency scenario.
______________________________________________________________________
Control System
E & C Division
5.4
E & C Division
fine mesh wire screens, orifice plates and other items in which small
changes in dimensions are critical. Rates of corrosion can be heavily
affected by temperature changes and whilst a material of construction
may be suitable at one temperature it may not be appropriate for use at
a higher temperature with the same process fluid.
The corrosion of non-metallic materials is essentially a physiochemical
process that manifests itself as swelling, cracking or softening of the
material of construction. In many instances nonmetallic materials will
prove to be attractive from an economic and performance view.
The use of various substances as additives to process streams to inhibit
corrosion has found widespread use and is generally most economically
attractive in recirculation systems, however it has also been found to be
attractive in some once through systems such as those encountered in
the petroleum industry. Typical inhibitors used to prevent corrosion of
iron or steel in aqueous solutions are chromates, phosphates, and
silicates. In acid solutions organic sulphides and amides are effective.
Localised Corrosion
There are many forms of localised corrosion than can lead to early failure
of equipment. The prevention of corrosion should be addressed at the
mechanical design stage and proper design to minimise local corrosion
should include free and complete drainage, minimising crevices, no dead
spots in pipework and ease of cleaning and inspection. Some of the more
common types of local corrosion are briefly discussed in this section.
Pitting often occurs where certain impurities such as chlorides are present
in process streams and cooling waters. This is an extreme form of
localised corrosion. Once initiated pits are usually self-accelerating and
can result in rapid failures.
Many
metals
suffer
from
stress
corrosion
cracking
under
certain
__________________________________________________
Corrosion / Selection of Material
2
E & C Division
__________________________________________________
Corrosion / Selection of Material
3
E & C Division
Materials Selection
Corrosion rates are expressed in terms of inches per year of surface
wastage and are used to provide a corrosion allowance in the design
thickness of equipment such as vessels and pipework. Operators will
often use data based on historical experience from plant operations to aid
them in determining appropriate corrosion allowances. Alternatively
corrosion charts are widely available that give corrosion rates for many
combinations of materials of construction and process fluids and normally
a range of values will be provided for various process temperatures. In
some instances, particularly where there is a mixture of chemicals
present, appropriate data may not exist and corrosion tests may be
necessary in order to determine the suitability of equipment. Operators
should be able to demonstrate the use of corrosion allowances in
equipment specification and design. The sources of data used should be
traceable.
Whilst carbon and stainless steels are commonly used materials of
construction, increasing use is being made of non- metallic and lined or
plastic process equipment. The selection of the material of construction
should taken into account worst case process conditions that may occur
under foreseeable upset conditions and should be applied to all
components including valves, pipe fittings, instruments and gauges. Both
composition (e.g. chlorides, moisture) and temperature deviations can
have a significant direct effect on the rate of corrosion. The operator
should demonstrate that procedures are in place to ensure that potential
deviations in process conditions such as fluid temperature, pressure and
composition are identified by competent persons and assessed in relation
to the selection of materials of construction for pipework systems.
A wide range of plastics are available for use as materials of construction
and can be used in areas such as handling inorganic salt solutions where
metals are unsuitable. The use of plastic linings is widespread in
equipment such as tanks, pipes, and drums. However, their use is limited
to moderate temperatures and they are generally unsuitable for use in
abrasive duties. Some of the more commonly used plastics are PVC, PTFE
and polypropylene.
__________________________________________________
Corrosion / Selection of Material
4
E & C Division
E & C Division
be
regularly
checked
to
ensure
continued
protection.
chlorine
special
steels
are
required
to
avoid
PVDF pipework and PVDF lined steel are commonly used for handling
bromine. If the bromine is 'dry' then metals such as monel and hastelloy
can be used. Vessels are normally constructed of either lead, PVDF or
GRP lined steel.
Sulphuric Acid
Corrosion protection of mild steel vessels occurs by the formation of an
iron sulphate coating. Any condition leading to excessive turbulence can
result in the removal of the coating and corrosion. Additionally the
temperature influence on corrosion rate varies with different strengths of
acid and consequently it is necessary to define maximum operating
__________________________________________________
Corrosion / Selection of Material
6
E & C Division
__________________________________________________
Corrosion / Selection of Material
7
E & C Division
5.5
Introduction
A variety of toxic and flammable chemicals are frequently stored and
transported in drums and cylinders. Although individual containers hold
relatively small inventories, a single cylinder of a compressed or liquefied
toxic gas can present a significant hazard to personnel. Additionally large
quantities of drums and cylinders are often stored together giving rise to
potentially large inventories of hazardous materials. The movement and
connection / disconnection of drums and cylinders to process plant
requires the direct involvement of operating personnel giving rise to the
potential for human error to cause incidents.
General Principles
Storage Location
Both the hazards of the material and the size of the inventory need to be
considered in determining where a store should be located.
Considerations should include the distance from other stored materials,
process plant, traffic routes and occupied buildings.. Where separation
distances are inadequate measures such as fire walls can be employed to
reduce the impact of incidents. The operator should demonstrate that the
storage location and design has taken into account site specific security
requirements and the potential for vandalism.
Ventilation
The preferred location for the storage of drummed flammable liquids and
compressed / liquefied gases is in the open air, to allow vapours to be
dispersed effectively. When located in buildings, the operator should
demonstrate that there is an adequate level of ventilation achieved by
either the presence of a sufficient size and number of permanent
openings such as louvres or mechanical ventilation. If stored indoors,
flammable gases such as LPG may only be stored in purpose built
compartments or buildings constructed with fire resistant walls and
explosion relief.
__________________________________________________
Drum / Cylinder Handling
1
E & C Division
__________________________________________________
Drum / Cylinder Handling
2
E & C Division
Containment of Spills
Suitable precautions should be in place for the containment of leaked
materials. Where liquids are handled suitable spillage containment such
as bunding and drainage sumps should be in place. Arrangements should
be in place for the routine drainage of rainwater from sumps. Where
materials that react with water are stored outdoors, the operators risk
assessment should demonstrate the suitability of the arrangements For
the storage of toxic gases, location of the containers in a purpose
designed indoor store will reduce the rate at which gas is released to the
environment.
Control of Ignition Sources
Where flammable liquids or gases are stored, the area should be subject
to hazardous area classification for the control of ignition sources. This
requirement should be reflected both in the equipment installed and in
the control of operational and maintenance activities in the location. The
movement of drums and cylinders often involves the use of fork lift
trucks, which can provide a source of ignition for flammable vapours. Any
vehicle operating in a zoned area should be protected to an appropriate standard.
Industry Applications
Flammable Liquids
Containers should be stored in the open air where practical, but if stored
inside five air changes per hour is considered a sufficient ventilation rate.
Standard 205 litre metal drums should be stacked no more than three
high and preferably on pallets or racking. The maximum stack size should
be 300,000 litres with at least 4 metres between stacks. Storage should
be on an impervious surface such as concrete and be bunded with
drainage towards a sump or other suitable handling system.
__________________________________________________
Drum / Cylinder Handling
3
E & C Division
LPG Cylinders
Cylinders should be stored preferably in the open air on a concrete or
load bearing surface. Flammable liquids, combustible, corrosive, oxidising
materials, toxic materials or compressed gas cylinders should be kept
separate from LPG containers in general. Containers should be stored
with their valves uppermost. The maximum size of any stack should not
exceed 30,000 kg. For storage indoors, no more than 5000 kg may be
stored in each purpose designed building compartment and a maximum
of
five
compartments
may
exist
in
a
single
building.
Chlorine Cylinders
The vast majority of chlorine cylinder and drum stores are located
indoors and should be solely used for storing chlorine. Access doors
should fit closely to help contain any leak. These stores should be
protected from any nearby radiant heat hazards. The store should be at
least 5 m from any roadway. A cylinder store should be at least 20 m
from the site boundary and a drum store 60 m. Chlorine gas detectors /
alarms should normally be provided.
Risk assessments should be carried out to consider hazards arising from
mishandling (dropping of containers in transport/handling), incorrect
operation of valves and failure to connect correctly, maintenance errors
and damage by external sources (domino, vehicle impacts, etc.)
__________________________________________________
Drum / Cylinder Handling
4
E & C Division
5.6
Introduction
If pressure equipment fails in use, it can seriously injure or kill people
nearby and cause serious damage to property.
To minimise the risks when working with systems or equipment which
contain a liquid or gas under pressure. It does not cover gas cylinders
(now called transportable pressure receptacles or transportable pressure
vessels), or tanks and tank containers.
As an employer or self-employed person, you have a duty to provide a
safe workplace and safe work equipment. Designers, manufacturers,
suppliers, installers, users and owners also have duties. Employers have
a further duty to consult any safety or employee representatives on
health and safety matters. Where none are appointed, employers should
consult the workforce direct.
Examples of pressure systems and equipment are:
E & C Division
E & C Division
______________________________________________________________________
E & C Division
You must assure yourself that the competent person has the
necessary knowledge, experience and independence to undertake
the functions required of them.
The competent person carrying out examinations under a written
scheme does not necessarily need to be the same one who
prepares or certifies the scheme as suitable.
______________________________________________________________________
E & C Division
______________________________________________________________________
E & C Division
5.7
Earthing
Equipment earthing.
__________________________________________________
Static Electricity
1
E & C Division
40
7.0
50
80
6.0 3.6
100
200
400
600
3.0
1.8
1.3
1.0
__________________________________________________
Static Electricity
2
E & C Division
Powder Transfer
Powder transfer can be carried out by several different methods:
Screw conveying;
Vacuum transfer;
Pneumatic conveying;
There are two distinct types of pneumatic conveying used for powder
transfer, namely low pressure / dilute phase or high pressure / dense
phase. Low pressure / dilute phase systems tend to employ high system
velocities ranging from 10 to 25 m/s, whereas high pressure / dense
phase systems tend to employ low system velocities ranging from 0.25 to
2.5 m/s.
Intensive charging of the conveyed material and pipeline is possible
during pneumatic powder transfer potentially resulting in:
Powders can be divided into three groups depending upon the volume
resistivity of the material of which the particles are composed. These
groups are:
__________________________________________________
Static Electricity
3
E & C Division
insulating material;
Use antistatic plastic or paper bags in or around flammable gases,
vapours or dusts having minimum ignition energies of < 4 mJ;
Discharge powder into the container or silo via intermediate loading
equipment, e.g. a cyclone fabricated from conductive material to
reduce velocities and earth charge. (Alternatively rotary valves, bag
dump hoppers or scroll feeder systems can be employed).
Offloading
Stringent precautions are required to prevent accumulations of static
electricity and to give protection against lightning. Standard copper strip
(25 mm x 3 mm section or equivalent) is usually employed for the main
earthing system. This should be connected to at least one copperearthing rod that has been tested and shown to have a total resistance to
earth of <10 ohms.
The operator should employ a bulk loading and offloading procedure. This
should include written instruction that state when offloading flammable
liquids, the driver must first connect the tanker to the earthing
connection at the off-loading point. The electrically conducting discharge
hose can then be connected to the liquid intake point on the storage. The
electrical resistance between the two couplings on a flexible hose must
not be higher than 106 ohms.
__________________________________________________
Static Electricity
4
E & C Division
Temporary Storage
Before temporary storage is brought on line for storage of flammable
liquids or explosible powders, an assessment of earthing provision with
associated earth testing should be undertaken. This should encompass
the
storage
vessel
and
all
supporting
ancillary
equipment.
Flexible Pipelines
When flexible hoses are employed, measures that can be adopted
include:
__________________________________________________
Static Electricity
5
E & C Division
5.8
Corrosion
Erosion
External Loading
Impact
Pressure
Temperature
Vibration
Wrong Equipment
Defective Equipment
Human Error
1. CORROSION
Corrosion is caused by electro-chemical processes in which a metal reacts
with its environment to form an oxide or compound by the formation of
cells comprising an anode (the deteriorating metal), a cathode (adjacent
metal) and a conducting solution (acid / salts). It can occur both
internally and externally to pipelines, vessels, plant, machinery,
structures and supports.
The materials selection philosophy aspect of the design phase of all plant
and structures should take into account the anticipated conditions
(pressure, temperature and atmosphere) and the contents of the system
in order to either minimise corrosion or to make adequate allowances for
it in the form of additional material thicknesses.
The initial corrosion on some metals creates an impervious coating, which
prevents further corrosion taking place.
Corrosion can be exacerbated by utilising different materials which then
set up an electrochemical cell which in turn causes wastage of the anode.
1.1 Types
1. Oxygen pitting, bi-metallic (internal and external).
2. Water lines, low velocity/stagnant conditions, under millscale
deposits, crevice-type corrosion (differential aeration), localised at
areas of dissimilar metals (galvanic action).
3. Carbon dioxide uniform loss, specific through turbulence, wet gas
Mesa type (internal). Note: Mesa type corrosion is a descriptive
word emanating from the Mesa region of Spain which is noted for
its table top sharp edged plateau with shallow broad valleys.
__________________________________________________
Causes Of Plant Failure
1
E & C Division
4. Hot aerated water lines, where CO2 partial pressure is 0.2 barg,
areas of turbulence (bends, tees, weld upsets), wet gas lines.
5. Hydrogen Sulphide (internal).
6. Sour service, partial pressure > 0.003 barg, bacterial attack on
sulphates in low acid conditions.
7. Stress Corrosion Cracking (internal and external).
8. Chloride SCC in austenitic steels at temperatures above 60C,
combined corrosive and tensile stress, externally.
9. Can be associated with damaged / wet coverings and insulation
material, inadequate or maloperating cathodic protection.
1.2 Prevention
Adequate design parameters.
1. Choice of materials, taking into accounts all envisaged conditions
and contained fluids or products.
2. Avoiding the use of dissimilar metals.
3. Suitable corrosion allowances.
4. Joint design and configuration.
5. Applied coatings (internal and external).
6. Drainage facilities.
7. Inspection and monitoring facilities.
8. Installation considerations.
1.3 Monitoring
a) Condition Monitoring (containment system):
i) Planned inspection procedures.
ii) Planned corrosion monitoring procedures, by ultrasonic thickness
measurement, probes, coupons, cathodic
protection,etc.
b) Condition Monitoring. (contained fluids):
i) Continuous process and operation monitoring.
ii) Planned application of inhibitors to contained fluids.
iii) Regular checks and monitoring that the contained fluids are
within the design parameters.
c) Monitoring at manufacture and installation:
i) Storage and protection of pipework and plant at fabrication
stage and prior to commissioning.
ii) Correct selection and usage of fabrication methods and
consumables.
iii) Satisfactory installation to avoid deadlegs, moisture traps,
environmental hazards.
iv) Proper selection and application of monitoring and inspection
procedures during fabrication and installation.
v) Suitable insulation and protection during installation. Equipment
and installation drainage points etc.
__________________________________________________
Causes Of Plant Failure
2
E & C Division
1.4 Examples
1. External Chlorine induced SCC of Oil/Gas HP Separator due to
warm, (90C) wet insulation attached to solid stainless steel
(duplex).
2. Stress Corrosion Cracking in duplex stainless steel pipe welds due
to low pH, high chloride and high hydrogen sulphide environment
(Acid washing downhole safety valves).
3. Pin-point corrosion of heat exchanger tubes in fin-fan coolers on
closed circuit cooling water systems due to inadequate addition of
corrosion inhibitors and tested alkalinity of the medium.
4. External corrosion of pipework, vessels and storage tanks in places
that usually are covered, but where insulation breaks have
occurred, particularly in harsh environments. e.g. coastal locations,
(gas terminals etc.)
5. External corrosion of boiler blowdown elbows and associated
pipework, located in floor sumps, which become fouled with wet
warm debris.
6. Cavitational corrosion caused by bubble collapse in process systems
and more commonly in boiler water tubes as scab pitting.
7. Internal corrosion occurring in dead-legs on systems which do not
have adequate draining facilities, or are not operated as frequently
as required.
8. Floor plate and lower shell plate corrosion due to smothering with
wet acidic/chlorinated waste material and debris.
9. Preferential corrosion attack in the heat affected zone (HAZ) of
welds in carbon steel gas flow lines, initiated from a fairly benign
gas output at start up of production to an inclusion of degrees of
corrosive trace elements without proper degrees of inhibition being
implemented.
1.5 Key Words
Trace elements, corrosive extraction products, oxygen bubbling, H2S
attack, damp warm conditions (under insulation), sub-surface (soil),
acidic, chlorine content, preferential attack, drainage, design, monitoring.
2.EROSION
Caused by internally by excessive fluid velocity, change in phase,
cavitation, change in flow direction, presence of particulates.
Caused externally by sand, salt, water (rain and sea), wind, cavitation,
venturi effect round buildings etc. Pressure leaks can cause impingement
and have a lancing effect at the leak itself and at areas where the leaking
fluid strikes another surface.
__________________________________________________
Causes Of Plant Failure
3
E & C Division
2.1 Prevention
Adequate design parameters:
i)
Choice of materials.
ii)
Plant layout and siting.
iii)
Coverings and coatings.
iv)
Filtration.
v)
Reduction of dissolved gases in fluids.
vi)
Avoidance of abrupt changes in pipe section and short radius
bends.
2.2 Monitoring
Routine inspection programmes (visual supported by ultrasonic thickness
measurements where appropriate).
i) Non-intrusive internal inspection and monitoring at suspected
system sites (bends, Tees, elbows etc.).
ii) Intrusive inspection and monitoring at areas where erosion is
probable.
2.3 Examples
1. Failure of bends on 50 mmNB pipework carrying pulverised
anthracite to the combustion chamber of a fluidised bed steam
generator at the Grimesthorpe European power station project.
2. Thinning of swept bends of flowlines carrying first oil from offshore
extraction due to the scouring effect of sand particulates.
3. Perforation of U bends in tubular heat exchangers.
4. Rapid perforation of adjacent boiler downcomer tubes from
tubewall leak through cracking.
5. Thinning of exposed pipe through sand blasting in desert and
seaside locations.
6. Turbulence effect created by incorrectly fitted / incorrectly sized
flange gaskets.
3. EXTERNAL LOADING
Can be caused by the effects of snow, winds, ice, floods, support failure,
system/equipment failure, environmental failures (earth movements),
filling / emptying, change in contained fluids.
3.1 Prevention
Adequately considered design parameters.
i) Adequate consideration of environmental factors, (wind, snow, ice
formations, earth tremors).
ii) Provision of spiral deflector vanes on pipework, tall vessels etc.
iii) Provision of guyed supports for tall structures.
__________________________________________________
Causes Of Plant Failure
4
E & C Division
E & C Division
5. PRESSURE
Failure due to over-pressure caused by control failure, external fire,
internal explosion, excessive reaction rate, liquid expansion, exothermic
reaction, or collapse caused by vacuum.
5.1 Prevention
1. Design parameters to include suitable process pressure controllers
for systems, particularly where multi-system inter-action is
required.
2. Installation of suitable additional pressure controlled shutdown or
warning devices where operational environments deem this a
necessity (Gas terminals, chemical plant etc.).
3. Design parameters should ensure conditions where there may be a
potential for internal explosion (e.g. through mixture of gasses) are
fully considered.
4. Design and operating procedures should take account of the
possibility of excessive reaction rates and limit the resulting rises in
pressure and / or temperature to acceptable limits.
5. Design and operating procedures should take account of the
possibility of liquid expansion to limit the resulting rises in pressure
and / or temperature to acceptable limits.
6. Design and operating procedures should take account of the
possibility of exothermic reaction and limit the resulting rises in
pressure and / or temperature to acceptable limits.
7. Design parameters should include suitable prevention devices
(vacuum breakers) and structural strength where vacuum
generation is possible unless the plant has been designed to safely
withstand vacuum conditions.
8. Fitting of suitable relieving devices to the systems and vessels
(pressure safety valves, bursting discs, fusible plugs) which have
adequate margin between system operating pressure and actuation
pressure and which prevent design parameters being exceeded.
9. System dump facilities in case of over-pressure.
5.2 Monitoring
1. Regular programmed and audited testing and calibration of
pressure control, relieving, indicating and warning devices.
2. Regular review of design codes and guidance for pressure systems.
3. Regular review of safety notices regarding incidents to pressure
systems.
4. Regular review of the operators awareness and skills.
5. A formal procedure to review operating procedures in the event of
change of use or contents of a pressure system.
6. Regular and formal testing and maintenance of vent and flare
headers.
__________________________________________________
Causes Of Plant Failure
6
E & C Division
6. TEMPERATURE
Excessive excursions of high and low temperatures due to process
upsets, fire, adverse weather conditions, fouling, blockages or phase
changes can lead to failure due to rapid or large temperature variations.
Rapid temperature changes or low temperatures can lead to cracking.
High temperatures can lead to failure due to loss of structural strength
without the design pressure being exceeded.
6.1 Prevention (internal)
1. Adequate thermostatic control of the system contents.
2. Design parameters adequate for predictable temperature
variations.
3. Provision of insulation where required.
6.2 Prevention (external)
1. Temperature sensors, gas sensors.
2. The provision of blast and fire walls where required.
3. Deluge systems provision.
4. Insulation to the systems vessels and pipe work.
6.3 Monitoring
1. Implement regular inspection and testing of all alarm, control and
shut down devices.
2. Regular surveillance and monitoring of insulation, fireproofing etc.
7. VIBRATION
Vibration can be generated through changes in phase, water hammer,
liquid slugs in gas systems, gas bubbles or pockets in liquid systems,
high pressure drop, cavitation, incorrect siting of rotating machinery,
incorrect pipe supports, loss of buffer gas in damper vessels, damaged
supports and hangers, all of which can give rise to fatigue failure.
7.1 Prevention
1. Ensure that system operation and contained fluid flow
characteristics are constantly monitored for prevention of
mechanical shocking caused by fluctuations.
2. Ensuring that provision is made for liquid systems to be vented to
prevent gas entrainment.
3. Accurately determined siting of mechanical and rotating machinery.
4. Pipelines and pipework layout is are such that the effect of vibration
is minimised.
5. All pipelines and pipework is properly supported, and such supports
and hangers are suitable for the purpose.
__________________________________________________
Causes Of Plant Failure
7
E & C Division
6. All equipment and piping holding down devices are adequate and
secure.
7. Adequate shock / vibration mountings are fitted to plant and
machinery.
8. There is adequate provision of damper vessels at pump/compressor
discharges, (especially reciprocating type).
7.2 Monitoring
1. Adequate, programmed, audited surveillance by visual and
electromechanical means.
2. Machinery vibration analysis exercises carried out, results reported
and acted on.
3. Monitoring and recording of damper vessel precharge pressure.
8. WRONG EQUIPMENT
Wrong equipment can be fitted at installation or be supplied as a
replacement during the life of the plant or at a modification. The
equipment may be wrong because it has been incorrectly specified, or
because the supplier has not supplied in accordance with the
specification.
Wrongly supplied equipment can lead to failure due to incompatible
materials, wrong design, or it may have a rating or duty other than that
which it is intended to fulfil.
8.1 Prevention
1. Formal system for ensuring that only equipment specified under the
design approval process is supplied and fitted.
2. Adequate system design parameters from inception to first
fabrication.
3. Audited and auditable TIPS (Technical Integrity Procurement
System) in place for new and replacement items, including
pipework, steelwork, fixtures and fittings.
4. Auditable obedience to design procedures during build, to include
formal design change procedures and engineering query routes to
fulfilment.
5. Manufacturer, supplier, installer, operator and maintainer
knowledge assessment and awareness systems are in place and
audited.
6. Auditable maintenance procedures, check lists, equipment lists in
place.
7. Permit to work systems in place.
__________________________________________________
Causes Of Plant Failure
8
E & C Division
9. DEFECTIVE EQUIPMENT
Defective equipment can be supplied when the plant is initially installed
or subsequently as a replacement or during a modification.
This category covers circumstances where the equipment was correctly
specified, but was defective in some way, such as the materials, the
duty, or it may have been wrongly assembled. It may not work in
accordance with the specification, in terms of performance, or the trips,
interlocks, protective devices etc. may not function as required.
The materials of construction may not be as per the specification, or it
may be intended for a duty other than that which was specified.
Such defects can lead to the system failing or at least not perform as
required.
9.1 Prevention
1. Formal system for ensuring that only equipment specified under the
design approval process is supplied and fitted.
2. Plant and equipment purchased from approved suppliers only.
3. Audited and auditable TIPS (Technical Integrity Procurement
System) in place for new and replacement items, including
pipework, steelwork, fixtures and fittings .
4. Recorded vendor inspections at the suppliers or manufacturers
works on all major plant and equipment.
5. Adequate and recorded commissioning tests on all new and
repaired equipment.
6. Manufacturer, supplier, installer, operator and maintainer
knowledge assessment and awareness systems are in place and
audited.
7. Auditable maintenance procedures, check lists, equipment lists in
place.
8. Permit to work systems in place.
10. HUMAN ERROR
Many of the causes of plant failure already discussed have elements of
human error built in to them, from the design stage through to operation
and maintenance. The types of failure directly covered here are those
associated with the operation of the plant, where errors of judgement or
ignorance form a major hazard.
Human error can cause overfilling, overloading through lack of or misplaced judgement and/or information giving rise to incorrect decisions by
__________________________________________________
Causes Of Plant Failure
9
E & C Division
__________________________________________________
Causes Of Plant Failure
10
E & C Division
5.9
Explosion Relief
place,
or
to
protect
__________________________________________________
Explosion Relief
1
E & C Division
Segregation;
Explosion suppression.
The concentration;
Various general rules are available for predicting vent areas based on
plant or vessel volumes. However, there is some discrepancy between
these general rules, so they should only be used with utmost caution.
__________________________________________________
Explosion Relief
2
E & C Division
These methods also depend upon the physical properties of the material
in the vessel. Two of the most common general rules are:
several
methods
to
corroborate
the
ultimate
size
selected.
__________________________________________________
Explosion Relief
3
E & C Division
The dust must have a particle size distribution that will allow the
propagation of flame;
test
apparatus.
These
groupings
are
as
follows:
Non-explosible
St 1
St 2
Strongly explosible
<300
St 3
__________________________________________________
Explosion Relief
4
E & C Division
Earthing of equipment;
E & C Division
Explosibility;
Flammability;
Toxicity;
Environmental problems.
__________________________________________________
Explosion Relief
6
E & C Division
5.10
General Principles
The methodology for classification of hazardous areas is covered by
appropriate British and European standards. All likely ignition sources
must be considered, and only equipment designed to an appropriate
standard should be employed in designated zones.
analysing
and
classifying
the
of
the
occurrence
and
duration
of
an
explosive
gas
atmosphere, as follows:
__________________________________________________
Hazardous Area Classification/Flameproofing
1
E & C Division
When the hazardous areas of a plant have been classified, the remainder
will be defined as non-hazardous, sometimes referred to as safe areas.
An area extent and classification study involves due consideration of the
following:
Presence,
degree
and
availability
of
ventilation
(forced
and
natural);
E & C Division
Zone 0
Zone 1
Zone 2
Ex ia Intrinsic safety
(IEC 79-11)
Ex n Type of
protection N (IEC
Zone 0
79-15)
Ex p Pressurised or
purging (IEC 79-2)
Ex q Powder filling (IEC
79-5)
Ex o Oil immersion (IEC
79-6)
Ex e Increased safety
(IEC 79-7)
Ex ib Intrinsic safety
(IEC 79-11)
Ex m Encapsulation (IEC
79-18)
Ex s Special protection
It should be noted that references in the table are to the equivalent IEC
79 standard Selection of electrical equipment for hazardous areas
requires the following information:
__________________________________________________
Hazardous Area Classification/Flameproofing
3
E & C Division
T1
450
>450
T2
300
>300
T3
200
>200
T4
135
>135
T5
100
>100
T6
85
>85
Group
Representative Gas
Methane
IIA
Propene
IIB
Ethylene
IIC
Hydrogen
MESG
MIC Ratio
> 0.9 mm
> 0.8
< 0.5 mm
< 0.45
__________________________________________________
Hazardous Area Classification/Flameproofing
4
E & C Division
Flames;
Hot surfaces;
Mechanical machinery;
Spontaneous heating;
Impact sparks;
Electric sparks;
Lightning strikes.
__________________________________________________
Hazardous Area Classification/Flameproofing
5
E & C Division
Lightning Protection
__________________________________________________
Hazardous Area Classification/Flameproofing
6
E & C Division
chemical composition;
particle size;
moisture content;
oxygen concentration;
In general, dusts with a particle size greater than 500 m are unlikely to
cause an explosion, and particle sizes below 50-74 m do not result in a
reduction of explosibility as size reduces. For this reason, most tests are
carried out on 75 m samples as the worst case.
Ignition due to a hot surface is particularly likely to occur. The minimum
surface temperature which can cause ignition is about 100-200C in most
cases.
Factors for assessor to consider
__________________________________________________
Hazardous Area Classification/Flameproofing
7
E & C Division
5.11
INERTING
General Principles
The partial or complete substitution of the air or flammable atmosphere
by an inert gas is a very effective method of explosion prevention.
Inerting is normally only considered when the flammable or explosive
hazard cannot be eliminated by other means i.e. substitution of
flammable material with non-flammable, adjustment of process
conditions to ensure substances are below flammable limits. Typical uses
are within storage tanks where a material may be above its flashpoint
and within reactor systems when excursions into flammable atmospheres
may occur. Inert gases are also used to transfer flammable liquids under
pressure. Inerting is applicable to enclosed plant, since plant that is
substantially open to atmosphere cannot be effectively inerted because
the prevailing oxygen concentration is likely to vary.
A major risk associated with use of inerting is that of asphyxiation,
particularly in confined spaces. In those events where people are required
to enter a confined space, a formal management control system in the
form of a Permit to Work should be in place so that appropriate
precautions and control measures can be implemented. The Permit to
Work system is covered separately.
Gases that can be used for inerting include:
Nitrogen;
Carbon Dioxide;
Argon;
Helium;
Flue gases.
__________________________________________________
Inerting
1
E & C Division
produce
an
explosion,
three
key
'ingredients'
are
required
Fuel;
Ignition;
Oxygen.
the
would
fuel
bring
cannot
the
be
material
eliminated
within
or
its
flammable
minimised,
steps
range.
must
be
E & C Division
to
find
the
worst
case
that
must
be
considered.
Asphyxiation;
__________________________________________________
Inerting
3
E & C Division
5.13
Human Factors;
IR.
detectors,
smoke
detectors,
intrinsically
safe
detectors,
heat
detectors,
specific
substance
detectors,
explosimeters) in terms of the environment in which they are
located and to perform the duty expected;
E & C Division
The
detectors
can
be
clearly
seen,
heard
and
frequency,
understood,
The level of risk associated with each potential leak source (risk
assessments, risk-rating systems) and the reduction in that
assessed risk value achieved by the use of detectors;
detectors,
temperature
detectors,
smoke
__________________________________________________
Leak/ Gas Detection
2
E & C Division
Major Hazards
The Report should address the following points:
__________________________________________________
Leak/ Gas Detection
3
E & C Division
5.14
Introduction
Active fire protection systems such as water sprinkler and spray systems
are widely used in the process industries for protection of storage
vessels, process plant, loading installations and warehouses. The duty of
the fire protection system may be to extinguish the fire, control the fire,
or provide exposure protection to prevent domino effects. For some
applications foam pourers or fixed water monitors may be a more
appropriate method of delivery than sprays or sprinklers. Other more
specialised systems using inert gases and halogen based gases are used
for flooding enclosed spaces.
Passive fire protection can provide an effective alternative to active
systems for protecting against vessel failure. This generally consists of a
coating of fire resistant insulating media applied to a vessel or steel
surface. It is often used where water or other active protection media
supplies are inadequate, such as in remote locations, or where there are
difficulties with handling firewater run-off. Firewalls are another form of
passive fire protection that are used to prevent the spread of fire and the
exposure of adjacent equipment to thermal radiation. An important
criterion in deciding which system is most appropriate for fire exposure
protection is the likely duration of the exposure to fire as passive fire
protection is only effective for short duration exposure (1-2 hours).
General Principles
The operator should be able to demonstrate that it has an effective and
practical plan for the containment and fighting of fires on its process
installations. The following site factors should be considered in
determining whether active and passive fire protection measures are
required:
inventory size;
__________________________________________________
Active / Passive fire protection
1
E & C Division
Design of System
Active fire fighting systems need to be reliable and the design of the
system should demonstrate this. The design of fire fighting systems
should conform to specified standards such as Teriff Advisory Committee
(TAC) and Fire Offices Committee 'Tentative rules for medium and high
velocity spray systems'.
The location of items such as the foam and water sources should be a
safe distance from any hazardous installation. Critical valving and
instrument cabling located on the protected installation should be capable
of withstanding the effects of fire and heat.
The system should be supplied by a secure water supply, which should
include items such as backup diesel pumps where appropriate. The
design must ensure that the active fire protection system is not starved
of water due to other demands on the water supply system during a fire.
Choice of Fire Fighting Media
The selection of media will depend on the required duty. This may be to
extinguish the fire, control the fire, or provide exposure protection. Types
of fire fighting media are:
Water;
Foams;
Inert gases;
Chemical powders;
Halons.
__________________________________________________
Active / Passive fire protection
2
E & C Division
2.
intumescent coating
3.
sublimation coating
4.
5.
earth mounds
The protective systems based on coatings are normally sprayed onto the
surface following mixing of the required components. A reinforcing glass
fiber scrim or steel wire gauze is applied to prevent cracking and peeling
__________________________________________________
Active / Passive fire protection
3
E & C Division
E & C Division
Maintenance Requirements
Active fire protection systems require to be well maintained to ensure
reliability. In particular systems using water and water based foam are
prone to rust deposits which can block sprinkler heads and spray nozzles.
Procedures should be in place to ensure regular maintenance and testing
of systems. Maintenance contracts are often placed with the supplier of
the fire protection system. Records of these activities should be kept by
site operators.
The performance of passive fire protection systems can deteriorate in
time due to weathering and corrosion. Plant operational and maintenance
activities may damage or remove the fire protection. Additionally the
protected surface itself can corrode beneath the fire protection.
Procedures should be in place to ensure that both the passive fire
protective system and the protected surface are regularly inspected and
repaired as appropriate.
Containment of Firewater
Foam and water based active fire protection systems can generate
considerable amounts of effluent with significant potential environmental
damage. Where active fire protection systems are installed the overall
design of the facility should cater for the collection of fire fighting
effluents. Operating sites should have effluent disposal plans in place as
part of their emergency plans.
Supporting Measures
Where active or passive fire protection is installed, these systems should
be supported by hydrants at suitable locations as specified in BS 5908.
Suitable portable fire fighting equipment should also be located on the
plant.
Mortar based fire protection fire protection is commonly used to protect
load bearing steel work from collapse under fire exposure. The application
of this to vessel supports and supporting structures for process
__________________________________________________
Active / Passive fire protection
5
E & C Division
Industry Applications
LPG Industry
The use of water deluge systems for the protection of bulk LPG storage
vessels and loading bays is standard in the industry for all but the
smallest installations. Passive fire protection is used as an alternative and
in particular earth mounding of LPG vessels is an established practice.
Large LPG cylinder compounds covered by canopies are normally
provided with either fixed water monitors or a sprinkler system.
Flammable Liquids / Solvent Bulk Storage
Whilst active fire protection is not a standard requirement for vessels
containing flammable and highly flammable liquids, site factors such as
inadequate separation distances from other plant or the proximity of
occupied buildings may necessitate the use of active or passive fire
protection to prevent escalation of a fire event. Where protection of
remote storage tanks is required, passive fire protection is commonly
used. However, it is not normal practice to protect storage tanks in
locations that do not represent a hazard to people directly or by domino
effect.
Process Operating Units
Both the material handled, the size of the flammable inventory and the
local fire fighting capability will influence the requirement for active fire
protection on a process structure. In particular, where process equipment
handling significant quantities of flammable material are located inside a
building and fire fighting access is poor, then fixed fire protection systems
should be provided.
Warehousing
Some significant fires have occurred in chemical warehouses, The
considerations are much the same as those for process operating units.
For the storage of high hazard materials such as organic peroxides in
__________________________________________________
Active / Passive fire protection
6
E & C Division
__________________________________________________
Active / Passive fire protection
7
E & C Division
5.15
QUENCH SYSTEMS
This Technical Measures Document covers the design and use of quench
systems
Introduction
Quenching can either be used to directly control a chemical reaction or in
the treatment of an emergency vent stream. For the direct quenching of a
chemical reaction when loss of control has occurred, the quench material
both cools and dilutes the reactants, thereby slowing down the reaction
rate and the rate of heat generation to a controllable level. Quenching
may be carried out by adding the quench liquid to the reactor or by
discharging the reactants to a dedicated dump tank.
Quench systems are used in vent disposal systems for the treatment of
streams that can not be discharged directly to atmosphere or where
continuing reaction is taking place. The process involves the mixing of a
solvent with the relief stream. This results in the condensation and
removal of volatile components from the relief stream and / or the cooling
of the vent stream which prevents further reaction from taking place.
General Principles
The operator should be able to demonstrate that it has evaluated the
options for emergency protection of an uncontrolled exothermic reaction.
Where venting has been chosen as the means of protection, the operator
should demonstrate that it has considered the consequences of a vent
emission directly to atmosphere and installed appropriate vent treatment
measures where necessary.
Reactor Quenching
Where a quench system for the control of a reaction is installed the
following should have been considered:
__________________________________________________
Quench System
1
E & C Division
__________________________________________________
Quench System
2
E & C Division
Maintenance Requirements
Quenching systems require to be well maintained to ensure reliability.
Procedures should be in place to ensure regular maintenance and testing
of relevant instrument and control systems. The inspection and
maintenance of pipe work and vessels should be carried out to written
procedures on a regular basis. Where the quality or specification of
quenching agents may deteriorate over time so as to reduce
effectiveness, the inventory should be replenished at set frequencies.
Effluent Disposal
Control of a reaction with a quenching agent may cause irreversible
contamination of the reactants. Where a quenching agent has been used
in a vent disposal system, this will need to be removed before plant
operations can recommence. Plans should be in place for the safe
handling and disposal of effluents generated from the use of a quench
system.
__________________________________________________
Quench System
3
E & C Division
5.16
Human factors;
Poorly skilled work force;
Unconscious and conscious incompetence;
What would happen if the wrong material was used in the wrong
place; and
What would happen if contaminated or out of specification material
was used.
The following issues may contribute towards a major accident or hazard.
E & C Division
QC
tests
to
approve
stored
E & C Division
Major Hazards
The Safety Report should address the following points:
Domino effect;
Failure of safety systems manual or automatic.
E & C Division
5.17
__________________________________________________
Reaction / Product Testing
1
E & C Division
Preliminary Reviews
Screening Tests
Worst Case
Adiabatic Tests
E & C Division
Reactive Systems Screening Tool. The data from these tests is used to
determine the Time to Maximum Rate and whether the pressure
developed is sufficient to cause failure of the vessel or relevant
process equipment. The data can be used to calculate a vent size
where appropriate. The Time to Maximum Rate is the time taken from
onset of the runaway to its maximum rate of heat generation.
Polymerisation
Nitration
Sulphonation
Hydrolysis
Salt formation
Halogenation
Alkylation
Amination
__________________________________________________
Reaction / Product Testing
3
E & C Division
The screening test programme and the adiabatic tests should show
whether the normal reaction or a secondary reaction or decomposition
are capable of over pressurising the reactor. The test work should be
used as the basis for determining whether additional protective measures
need to be included in the plant design such as:
emergency cooling
quench systems
reaction inhibition
containment
__________________________________________________
Reaction / Product Testing
4
E & C Division
Batch Distillation
In a batch distillation process loss of vacuum may result in increased
temperatures
that
could
initiate
decomposition.
Additionally
batch
__________________________________________________
Reaction / Product Testing
5
E & C Division
5.18
RELIABILITY OF UTILITIES
Electrical Power;
2.
Steam / Condensate;
3.
4.
Compressed Air;
__________________________________________________
Reliability of Utilities
1
E & C Division
5.
Vacuum Systems;
6.
Cooling Water;
7.
8.
9.
10.
Refrigeration.
On some sites other more specialised utility systems may exist such as
the supply of oxygen through a distribution system from a cryogenic
plant unit.
Where a hazard assessment identifies that a plant may not continue to
operate or may not shutdown safely then back-up features may be
necessary to ensure its continued safe operation. Normally, such back-up
supplies are provided local to the plant, e.g. bottled gas supplies, but
may be via a redundant or diverse system arrangement, e.g. a parallel or
alternative supply.
Design
Based on risk assessment the operator should demonstrate that utility
systems have been designed with an appropriate level of redundancy
within the system to cope with failures and maintain the required
integrity (availability) of supply. Items such as pumps and compressors
can be expected to fail occasionally and typically this would mean the
availability of back-up pumps, compressors, or steam boilers available on
an auto start basis. To improve availability diverse equipment can be
used to avoid common mode failures.
Routing of critical utility supplies should take into account the hazards on
site and the potential for fire and impact damage on the distribution
system. Appropriate shielding should be used where necessary. The loss
of supply of a utility such as steam to a plant can often be handled safely
by appropriate trip systems, but where the continued operation of a
utility system is more critical, the design of the distribution system should
demonstrate the availability of various routes to achieve supply. Routes
for duplicate distribution lines should be segregated. Often a 'ring main'
__________________________________________________
Reliability of Utilities
2
E & C Division
E & C Division
that the test routine involves 'end to end' testing of the system. As an
example, it is insufficient to test a diesel power generator set without
testing that the auto start-up facility works and that the switchgear in the
distribution system works properly.
Examples of Industry Applications
Emergency Absorption Plants
Emergency absorption plants must be able to handle vents under all
circumstances. These plants are built with standby recirculation pumps
and suction fans. Emergency power is provided by a standby diesel
generator. This approach is used in the handling of chlorine and other
toxic gases. Operating procedures should include the shutdown of plant in
the event of failure of such systems.
Flammables Handling
Where site operations involve the handling of flammable liquids a fire
hydrant system should be provided that preferably encircles the plant and
is provided with cross over connections at appropriate points. The ring
should be maintained under pressure by e.g. 'jockey' pumps. Any fall in
pressure should automatically start the main fire pump. A diesel powered
pump should be provided on high hazard sites in case of power failure.
Centrifuging of Flammable Materials
Many industrial processes involve the centrifuging of a powder from a
flammable liquid. Centrifuges are well known for providing an ignition
source due to their high speed moving parts and a secure nitrogen source
is necessary. A local emergency back-up supply of nitrogen is often
provided
from
local
cylinders
in
case
of
site
nitrogen
failure.
Steam Heating
Where a hazard can arise from the solidification of a liquid chemical on
loss of steam heating, back-up heating is often provided by an electrical
heater or trace heating. Whilst there are not many instances of this being
__________________________________________________
Reliability of Utilities
4
E & C Division
__________________________________________________
Reliability of Utilities
5
E & C Division
5.19
General Principles
Process
plant
can
be
subjected
to
excessive
overpressure
or
External fire;
__________________________________________________
Relief System / Vent System
1
E & C Division
A dump tank;
A storage tank;
A sewer;
The atmosphere;
A knockout drum;
A scrubber;
An incinerator;
A flare stack.
E & C Division
There are various recognised methods for sizing vents. These include:
API Methods;
NFPA Methods;
Leungs method;
Stepwise method;
Nomogram method;
Fauskes method;
Two-phase method;
DIERS method;
Huffs method;
Boyles method.
__________________________________________________
Relief System / Vent System
3
E & C Division
Flame Arresters
Flame arresters are commonly installed on the vent outlet of tanks
containing liquids with flashpoints below 21C, generally where pressurevacuum vent valves are not in use. Their prime function is to prevent the
unrestricted propagation of flame through flammable gas or vapour
mixtures, and secondly to absorb heat from unburnt gas.
Flame arresters should be designed for each specific application, and due
to the likelihood of progressive blockage a rigorous inspection and
maintenance schedule should be in place.
Relief Valves
Relief valves are characterised by:
Risk of blockage;
Trace leakage.
The pressure drop before the safety valve must be low to avoid
instability;
The
relief
valve
usually
solely
determines
relief
capacity
if
__________________________________________________
Relief System / Vent System
4
E & C Division
No leakage;
surrounding
vent
pipework
should
be
adequately
sized
to
E & C Division
The composition of the gas load must be known with respect to:
Inerts loading.
The basis of the scrubber design should take into consideration the
peak gas loading, the minimum gas loading and the mean gas
loading in addition to corresponding variations in inert gas loading.
__________________________________________________
Relief System / Vent System
6
E & C Division
Control systems;
Stack Heights
The concentration of waste gases at ground level can be reduced
significantly by emitting the waste gases from a process at great height,
although the actual amount of pollutants released into the atmosphere
will remain the same.
The basis for design begins with determination of an acceptable groundlevel concentration of the pollutant or pollutants. If the waste gas is to be
discharged through an existing stack, or the stack size is restricted the
ground-level concentration should be determined and if it is unacceptable
__________________________________________________
Relief System / Vent System
7
E & C Division
For a given stack height, the effective height of the emission can be
determined by employing an appropriate plume-rise equation;
Application
of
atmospheric
dispersion
formula
enables
the
Bosanquet-Pearson model;
Wilson model
Pasquill-Gifford model;
Sutton model;
TVA model.
Humidity;
Rainfall
Flaring
Flaring may be used to destroy flammable, toxic or corrosive vapours,
particularly those produced during process upsets and emergency
venting.
Key design factors to ensure flare safety and performance include:
Smokeless operation;
Flame stability;
__________________________________________________
Relief System / Vent System
8
E & C Division
Thermal radiation;
Noise level;
Flashback protection.
BS 5908: 1990
__________________________________________________
Relief System / Vent System
9
E & C Division
__________________________________________________
Relief System / Vent System
10
E & C Division
5.20
Introduction
The good design of roadways and the control of traffic on-site are
important factors in the prevention of road traffic accidents and an
important consideration in the prevention of major accident hazards onsite. Collisions between moving vehicles, collisions between pedestrians
and moving vehicles, or the impact of a vehicle with stationary plant,
vehicles or equipment can lead to physical injuries and damage or a loss
of containment of chemicals. The detailed design and construction of
roadways is outside the scope of this technical measures document but
some of the important considerations relating to roadway design are
highlighted below.
In addition the safe and correct immobilisation of vehicles during tanker
loading and unloading operations and at other times when on site is also
an important factor in the prevention of site major accident hazards.
This technical measures document considers the following elements:
Operational Issues.
__________________________________________________
Roadways / Site Traffic Control
1
E & C Division
__________________________________________________
Roadways / Site Traffic Control
2
E & C Division
Gradient
The maximum longitudinal gradient should be 1 in 12 and the minimum
channel gradient should be 1 in 125. A crossfall or camber of 1 in 40
provides adequate drainage. If minimum gradients are not provided,
surface water will tend to pond, which will be hazardous in freezing
conditions. Standing water can also obscure road markings and lead to an
increased likelihood of accidents.
Materials of Construction
Different types of road pavements are available including flexible
pavement where surface materials are bound with a bituminous binder, a
rigid pavement which utilises pavement quality concrete for the surfacing
layers, or a flexible pavement surfaced with block paviors.
Bituminous surfacing will degrade if exposed to oil products and other
chemical spillages. Areas where spillages are likely such as loading and
unloading areas should utilise a resistant surfacing, such as concrete or
some other appropriate material, with drainage facilities that can intercept
hazardous chemicals.
The design of the road pavement will be dependent on the ground
conditions at sub-grade level and the expected traffic flow and vehicle
type during the design life of the pavement.
Kerbing
Kerbing to roadways should be provided wherever possible to clearly
define the roadway and provide a measure of protection. Dropped kerbs
should be provided at pedestrian crossing points.
Height Restrictions
Areas that are vulnerable such as pipebridges, overhead gantries etc
should be clearly identified and height restrictions clearly marked.
The standard minimum clearance over every part of the carriageway of a
public road is 16 feet 6 inches (5.03 meters). When the clearance over
any part is less than this standard, a warning sign both on and prior to the
__________________________________________________
Roadways / Site Traffic Control
3
E & C Division
structure should be provided which should be at least 75mm less than the
measured height.
Heights of vehicle likely to be encountered are 4.2 meters high (i.e. A
standard container on a suitable flatbed vehicle). Minimum headroom
provided should be 4.65 meters exclusive of any additional space required
for lighting units. Additional clearance will be required if there is a
requirement for an overlay in the future. Changes in gradient may also
reduce the effective headroom for long vehicles.
Visibility
Consideration should be given to road traffic visibility. Road traffic should
have adequate forward visibility on bends to enable a driver to stop
before an obstruction in the road. In addition, there should be adequate
visibility at junctions so those drivers emerging can see and be seen by
approaching drivers.
Visibility requirements are related to vehicle speed and stopping
distances.
Lighting
There should be adequate lighting of site locations and vehicles at all
times to enable all persons to carry out their work tasks safely and in
safety.
Lighting should be provided for junctions, plant and buildings, pedestrian
routes and areas where loading/unloading is to be carried out. Signs
should either be illuminated for night-time visibility or adverse weather
conditions, or be suitably reflective. Vehicles on site should use
lights/beacons etc in darkness or poor visibility to aid detection by other
vehicles.
Consideration should be given to the difference in light levels between
internal and external areas at the points of access to and from buildings
that may hinder detection of vehicle movement.
Adequate lighting should be provided to all areas and especially to those
areas used in darkness hours.
__________________________________________________
Roadways / Site Traffic Control
4
E & C Division
Drainage
Roadways on site should be adequately drained to ensure that standing
water is not present on-site. Connections for rainwater run-off from roads
into drainage systems may have to include interception facilities in the
case of chemical contamination.
Bridges
Bridges and other structures, which have maximum weight restrictions,
should be clearly identified.
Parking
Parking areas on site for employees, visitors and delivery vehicles should
be clearly identified and marked. Staff and visitor car parking areas
should be separate from site access routes wherever possible. Provision
for disabled users should also be made.
Parking bays should be clearly identified by surface markings in order to
avoid random parking arrangements.
Lay-bys or similar should be considered to avoid obstruction of the main
site access roads.
Secure, convenient and adequate parking areas should be provided onsite for vehicles such that the general roadway is not obstructed. Off-road
pull-in areas that are clearly identified should be provided wherever
possible. Random parking should be avoided and discouraged wherever
possible since this can introduce additional hazards and increase the
likelihood of a road traffic accident.
Loading/Offloading
Areas for loading and unloading should preferably be separate from
general access areas and loading bay edges should be clearly marked and
protected by barriers. Adequate space for vehicle manoeuvring should be
available in loading/unloading and delivery areas.
If reversing or manoeuvring into position is required consideration should
be given to the provision of physical barriers or the attendance of another
__________________________________________________
Roadways / Site Traffic Control
5
E & C Division
footbridges
or
subways
may
be
considered
necessary
__________________________________________________
Roadways / Site Traffic Control
6
E & C Division
__________________________________________________
Roadways / Site Traffic Control
7
E & C Division
Rail traffic some sites may receive and dispatch goods by rail.
Rail routes may cross site access roads for vehicles or affect
pedestrian areas; and
Road users, both drivers and pedestrians, should know exactly what is
expected of them. This can be achieved by establishing a Road Hierarchy,
which is used to provide a consistent standard for each road type in
terms of design standard, signing, access constraints etc.
Traffic routes should be determined and can be classified as either
access/through routes to site for deliveries, shuttle routes between
buildings for on-site activities, or emergency access routes for fire
engines, ambulances etc. Careful planning and consideration of site traffic
control issues can result in a reduction in the likelihood of collisions
between vehicles and/or equipment.
Incompatible types of traffic should be segregated as far as possible to
avoid potential interactions between chemicals in the event of a collision
between road traffic vehicles or between road traffic and stationary
storage facilities or pipelines carrying chemicals.
This guidance is not concerned with traffic control within buildings such
as warehouses or process plant areas where special consideration needs
to be given to the potential interaction between forklift trucks and/or
pedestrians.
Road Traffic
Consideration should be given both to the hazards introduced by the
loads being conveyed and the mode of transport used. Chemical hazards
are considered elsewhere. Consideration should be given to the physical
size, the presence of ignition sources and hot surfaces, the presence of
flammable fuels, the possibility of impact caused by size or speed, and
loading/unloading issues.
The purpose of the presence of vehicles on site should be assessed.
Some vehicles may be used simply for access and the transportation of
__________________________________________________
Roadways / Site Traffic Control
8
E & C Division
personnel and others for the delivery of materials (solids, liquids and
gases) and equipment to/from site.
Some of the items that may be transported are given below:
Gas cylinders;
Mechanical equipment;
Personnel.
Mobile cranes;
Cars;
Mini-buses;
Cyclists; and
E & C Division
Roundabouts may smooth traffic flow and avoid road traffic turning
directly in front of on-coming traffic;
Physical Barriers
Physical barriers should be installed, wherever practical, adjacent to
roadways to reduce the potential impact of road traffic accidents.
Consideration should be given to the protection of vulnerable pipework,
storage tanks and other plant and equipment.
When considering the installation of barriers it is important that visibility
is not reduced
pedestrians.
below
acceptable
standards
for
road
users
and
Signs/Road Markings
Signs and signals should be used on-site to clearly identify hazards,
restrictions and to give directions. Chemical hazards should be identified
along with height, width and loading restrictions for pipebridges, arches,
bridges etc.
__________________________________________________
Roadways / Site Traffic Control
10
E & C Division
with
appropriate
disciplinary
action
taken
as
necessary.
Operational Issues
A number of on-going measures should be considered when considering
roads and traffic control.
Spillage Clean-up
Adequate facilities and materials should be readily available on-site for
clean-up of spillages. Any materials used should not directly affect the
road surface.
Maintenance
Roads on site should be adequately maintained and free from pot-holes
and other surface defects which may affect vehicles
__________________________________________________
Roadways / Site Traffic Control
11
E & C Division
E & C Division
vehicles.
Visitors should be the subject of suitable reception and security checks
prior to access to site. Visitor vehicles should be separated from site
operations as far as possible. Prior to access to site visitors should be
made aware of vehicle restrictions and safety considerations. Pedestrian
visitors should be accompanied whilst on-site in operational areas.
Site based vehicles should be routinely inspected and maintained to set
standards and procedures to ensure roadworthiness and the effectiveness
of safety systems such as brakes, lights, horns, indicators etc. Daily preuse checks for site based vehicles such as fork lift trucks should be
considered. There should be a clear procedure for reporting and
correcting defects in vehicles and maintenance records should be
available for inspection.
Systems should be in place to ensure effective communication between
gatehouse and operators accepting delivery on-site to warn of the arrival
of delivery vehicles.
CCTV systems can be considered as a mechanism for managing and
controlling road traffic systems.
Training
Training is an essential component of site traffic control and should cover
not only those engaged in driving vehicles on site, but also pedestrians
and those responsible for monitoring and enforcing traffic control on site.
Training of site personnel engaged in driving site-based vehicles is an
essential part of the prevention of site traffic accidents. Site based
personnel should be made aware of the hazards of driving fork lift trucks
for example and should be routinely checked for competence and licensed
as appropriate. Unauthorised personnel should not be allowed to drive
vehicles on site.
Training for all site staff should cover technical issues such as vehicles,
equipment, hazard awareness, speed limits, parking and loading
requirements, safe operating practices etc, site layout, traffic routes,
reporting procedures etc.
The competence of third party delivery drivers on site can be assessed by
checking the health & safety standards of contractors and their subcontractors in relation to their selection and training procedures,
__________________________________________________
Roadways / Site Traffic Control
13
E & C Division
__________________________________________________
Roadways / Site Traffic Control
14
E & C Division
5.21
SECONDARY CONTAINMENT
Bunds
Drip trays
Interceptors/Sumps
Expansion vessels
Concentric pipes
Building structures/ventilation
Bunds
Bunds are generally used around storage tanks or drum storage areas
where flammable or toxic liquids are held. Alternative measures may be
earth dikes (usually for very large tanks), sumps and interceptors. Bunds
are also sometimes used within plant buildings for reactors and other
process vessels. For materials that are normally gases at ambient
conditions, bunds are used where flash fractions are sufficiently low to
__________________________________________________
Secondary Containment
1
E & C Division
merit them. Therefore they are often used for refrigerated gases but not
for the same gases stored under pressure.
It is normal to limit the number of tanks in a single bund to 60,000 m3
total capacity. However, incompatible materials should have separate
bunds. Tanks often have individual bunds.
Bunds should be sized to hold 110% of the maximum capacity of the
largest tank or drum. This will allow some latitude for the addition of
foam during response to the emergency. There are no set rules on the
ratio between wall height and floor area and codes vary greatly with
respect to recommendations of bund wall height. Low wall heights (1-1.5
m) are often used to facilitate firefighting but are poor defense against
spigot flow (where a leak in the wall of a tank passes over the bund wall)
or the tidal wave effect of a catastrophic tank failure. In some cases
bunds up to height of the tank are used, but these are quite unusual. For
high walled bunds, consideration will need to be given to the possibility of
tanks floating as the bund fills, causing catastrophic failure.
Bunds are generally fabricated from brick/mortar or concrete but where
liquids are being stored above their boiling point additional insulation,
e.g. vermiculite mortar, may be added as cladding to reduce the
evaporation rate. Such materials provide adequate chemical resistance to
most liquids.
E & C Division
Scrubbers
Flares
Catchpots/Knock-out drums
Electrostatic precipitators
E & C Division
Sewers
Stormwater drains
In many cases these functions are combined and often firewater and
process effluents are drained into main sewerage systems. Where there
is a possibility that hazardous substances could be discharged into a
drainage system, interceptors or sumps should be provided of sufficient
capacity to ensure that an offsite major accident does not occur. HAZOP
studies or an alternative hazard identification methodology should be
used to identify such hazards.
For process effluents arising from leaks or plant washdown, good practice
is to provide a local sump which is sampled before emptying. Such sumps
normally incorporate level indicators/alarms for monitoring. Discharge
can be to drums via submersible or mobile pumps for onward disposal or
via manual or manually operated automatic valves into main drainage
systems if the contents are non-hazardous. As for bund drainage
consideration will need to be given in the Safety Report on the possibility
of valves being left open.
A particular concern is the discharge of non-water miscible flammable
liquids, which form a top layer. These could ignite considerable distances
from the plant after discharge. More sophisticated interceptors can be
provided to facilitate removal of floating flammable liquids. These tend to
be designed to meet individual needs and may incorporate conductivitybased level sensors to distinguish between layers.
Firewater run-off is likely to involve very large quantities of contaminated
water (Lees quotes 900-2700 m3/hr). Risk Assessments should be
__________________________________________________
Secondary Containment
4
E & C Division
Expansion Systems
Expansion systems are used to prevent pressure build up, leading to loss
of containment, in the event of overfilling or temperature increases. They
are used mainly on liquefied gas storage systems, reactors and long runs
of pipelines.
Codes of practice for chlorine systems include the use of an expansion
vessel to allow for overfilling of the main storage tank. Depending upon
the arrangement, pressure, level or weight detection/alarms on the
expansion vessel may included to alert operators if liquid reaches this
point. Capacity of the expansion vessel is recommended as 10% of the
capacity of a storage tank.
Expansion vessels are sometimes provided for atmospheric storage
tanks, particularly where substances are particularly toxic or noxious. A
liquid scrubbing medium may be included in the expansion vessel to
provide for removal of fumes from air displaced on filling. The vent
stream is sparged into vessel below the liquid surface. The expansion
vessel itself then vents to either atmosphere or a scrubber. An
alternative, where a number of tanks are used for the same substance, is
to arrange overflows from one tank to another.
Expansion tanks for reactors are described in the Technical Measure
Document Quench Systems.
Long pipelines containing liquids that have a high coefficient of expansion
should be provided with relief systems or expansion chambers to prevent
loss of containment due to overpressure. Relief systems should be
discharged into expansion vessels or off gas treatment plant if discharge
rates are within the design limits for such systems. Expansion chambers
should have a capacity of 20% of the pipeline volume. Chlorine is a
particular case to consider. Codes of practice recommend pressure relief
valves or bursting discs for liquid chlorine pipelines venting to the
expansion vessel or use of expansion chambers.
__________________________________________________
Secondary Containment
5
E & C Division
Building Ventilation
Building ventilation systems can be arranged such that flow is maintained
from less contaminated to areas that may become contaminated
following a loss of containment, before discharge via off-gas systems, to
__________________________________________________
Secondary Containment
6
E & C Division
__________________________________________________
Secondary Containment
7
E & C Division
5.22
following
aspects
should
be
considered
with
respect
to
the
Human factors;
Plant siting.
__________________________________________________
Segregation of Hazardous Material
1
E & C Division
substances,
strong
acids,
cyanide
__________________________________________________
Segregation of Hazardous Material
2
E & C Division
(fire
PPE,
Major Hazards
Major hazards could arise from the following:
__________________________________________________
Segregation of Hazardous Material
3
E & C Division
5.23
WARNING SIGNS
Human factors;
Ergonomic design;
General Issues
__________________________________________________________
Warning Signs
1
E & C Division
__________________________________________________________
Warning Signs
2
E & C Division
Dyslexic
or
illiterate
employees
should
be
considered
when
Viewing
Height
distance (mm) in mm
501-900
901-1800
1801-3600
18
3601-6000
30
__________________________________________________________
Warning Signs
3
E & C Division
Viewing
Height
distance (mm)
in
mm
500
700
4 .3
1000
4.8
Background
Black
White
Yellow
Dark Blue
White
Green
Black
Light Grey
White
Dark Grey
White
Red
All employees and contractors on site should know what each alarm
means and what the required response is, if the cause of the alarm
has the potential to affect them.
__________________________________________________________
Warning Signs
4
E & C Division
Adequacy
of
management
systems
to
identify
when/where
__________________________________________________________
Warning Signs
5
E & C Division
Suitability of warning signs for the area in which they are located
e.g. use of non-flameproof electric/electronic signs in flameproof
areas;
__________________________________________________________
Warning Signs
6
E & C Division
5.24
PROTECTIVE DEVICES
Contents
1. Introduction
2. Pressure
3. Level
4. Temperature
1. INTRODUCTION
Process equipment, including storage tanks and vessels, are usually
provided with protective devices in order that system safe operating
limits are not exceeded. In addition to protective devices, other devices
will perform a controlling function (e.g. pressure control, level control or
temperature control) and others will perform an alarm and / or shut down
function (e.g. high-pressure alarm, high level alarm, emergency
shutdown etc.). The latter function is usually actioned as a result of the
failure of a controlling function (e.g. emergency shutdown of a process
vessel due to high liquid level). The protective devices as described here
are the ultimate devices which are the last line of defense against safe
operating limits being exceeded.
The most common processing parameters that require to be controlled,
or against which process equipment needs to be protected are:
temperature
level
______________________________________________________________________
Protective Device
E & C Division
2. PRESSURE
All pressure systems must be provided with protective devices to prevent
the system being subject to pressures in excess of the safe operating
pressure. The safe operating pressure is the pressure quoted on the last
report of thorough examination made by the competent person, which
must be the same as or below the design pressure. Where the current
condition has deteriorated since manufacture, the safe operating pressure
may have been reduced below the design pressure by the competent
person. This applies equally to positive pressure and to negative pressure
(vacuum) - some large storage tanks and vessels can fail due to
inadvertently experiencing a vacuum. The only exception to the provision
of pressure protection/relief is in the case of a vessel (or system) that
has been specifically designed to withstand the maximum (or minimum)
pressure that can be generated within it - inherently safe (pressure)
design.
Over pressure protection for process pressure vessels usually involves a
hierarchy of passive and reactive protection devices. These devices range
from simple pressure indicators or gauges, through pressure transmitters
providing alarms, to pressure switches providing alarms and invoking
automatic shutdowns, and finally through to mechanical pressure relief
devices (e.g. pressure safety valves and bursting discs). Pressure
monitoring via gauges and automatic alarms is typically used to check
that the process system is operating at, or close to, the intended
operating pressure. Automatic shutdown systems are designed to shut
the system down before the Safe Operating Pressure is reached, or to
react to loss of pressure situations (e.g. vessel leakage). Pressure relief
(protective) devices are designed to prevent the system exceeding the
Safe Operating Pressure.
2.1 Pressure Relief Devices
Pressure relief devices typically take the form of a pressure, vacuum or
pressure/vacuum relief device. There are 2 types of common relief
devices - relief valves and bursting (or rupture) discs. These devices are
normally installed at the top of the vessels or tanks that they are
______________________________________________________________________
Protective Device
E & C Division
Protective Device
E & C Division
______________________________________________________________________
Protective Device
E & C Division
Protective Device
E & C Division
Protective Device
E & C Division
Protective Device
E & C Division
3. LEVEL
Correct level control, and indication, is often critical to the safe and
efficient operation of process plant. Many process vessels, such as
separators and distillation columns, require liquid levels to be strictly
controlled in order to effect product separation (e.g. separation of oil, gas
and water) and to prevent product carry over.
Level indication is usually accomplished by displacer/float instruments
and sight glasses. Other level indicators include differential pressure
gauges, ultrasonic, microwave, radiological, and fibreoptic instruments.
Providing that it is appropriate for the particular application, the method
of level indication is of less importance than the use of the level
information and / or measurement for control and protection purposes.
A typical level control function would be accomplished by using a level
transmitter which feeds control signals to a level control valve (LCV). The
LCV will open or close (modulate) to maintain the level within, say, the
vessel within pre-defined limits.
When it has not been possible to control the correct level within, say, a
process vessel, protective devices are provided to prevent hazardous
conditions arising. These protective devices, which usually take the form
of level transmitters and level switches, provide alarms and/or effect
shutdown of the process or individual vessel. A hierarchy of monitoring
and automatic shutdown is employed with vessels typically being
provided with high level and low level alarms and high/high level and
______________________________________________________________________
Protective Device
E & C Division
Protective Device
E & C Division
______________________________________________________________________
Protective Device
10
E & C Division
6.0
MSDS CONTENTS
The MSDS for the chemicals are part of the process and Basic
Engineering Design Document of the licensor. As per OSHA (USA)
manufacturers, importers and distributors are required to provide the
MSDS for each hazardous chemical they produce or handle. The
purchaser of these chemicals (Client) is entitled to receive these MSDS
from the supplier.
Each member of the commissioning team is required to read the MSDS
carefully before undertaking the commissioning activity. Although the
format of MSDS can vary, they should all include the following
information:
1. Chemical and common name
2. Ingredient information
3. Physical and chemical characteristics
4. Physical hazards - Potential for reactivity, fire and/or explosion.
5. Health hazard
6. Symptoms of exposure
7. Primary route of likely entry into the body upon exposure.
8. OSHA permissible exposure levels.
9. Precautions for use
10.
Waste disposal
11.
12.
13.
14.
____________________________________________________
Material Safety Data Sheet (MSDS)
1
E & C Division
1.
http://www.ucop.edu/riskmgt/ohp/msds.html
2.
MSDS SEARCH
http://www.msdssearch.com
3.
http://www.osh.nct
4.
http://www.ksu.edu/area/irml/safetv/msds.html
5.
The
Hong
Kong
Occupational
Safety
&
Health
Association
____________________________________________________
Material Safety Data Sheet (MSDS)
2
E & C Division
1 - Low
F Fire
2 - Medium
R Reactivity
3 High
4 - Extreme
____________________________________________________
Material Safety Data Sheet (MSDS)
3
E & C Division
RATING SUMMARY:
Health (Blue):
4 Danger
3 Warning
2 Warning
1 Caution
May be irritating
0 - No unusual hazard
Flammability (Red):
4 Danger
3 - Warning
2 Caution
Combustible if heated
Not combustible
Reactivity (Yellow):
4 Danger
3 Danger
2 Warning
____________________________________________________
Material Safety Data Sheet (MSDS)
4
E & C Division
1 Caution
0 Stable
Water Reactive
Oxy
Oxidizing Agent
____________________________________________________
Material Safety Data Sheet (MSDS)
5
E & C Division
____________________________________________________
Material Safety Data Sheet (MSDS)
6
E & C Division
7.0
2.
__________________________________________________
On site Emergency Plan
1
E & C Division
8.0
STORAGE
AND
IMPORT
OF
HAZARDOUS
__________________________________________________
Environmental Preservation Acts in India
1
E & C Division
with
protection
and
improvement
of
the
environment.
Table 2
Table 3
Table 4
Table 5
Table 6
Table 7
__________________________________________________
Environmental Preservation Acts in India
2
E & C Division
Table 1
The Air (Prevention & Control of Pollution) Rules, 1982 and 1983
Manufacture, Use, Import, Export and Storage of Hazardous MicroOrganisms, Genetically Engineered Micro-organisms of Cells Rules,
1989
__________________________________________________
Environmental Preservation Acts in India
3
E & C Division
1.0
Following are the specific obligations, under this Act, which are to be
complied with:
Obligations
-
Provide access to the PCB, or any officer empowered by it, for taking
samples of water or effluents from the industrial establishment for
the purpose of analysis
Allow entry to the PCB or any person empowered by it, at any time,
for the purpose of performing any of the entrusted functions; or for
seizing of any plant, records, registers, documents or any material
object, in case there are reasons to believe that provisions of the Act
are being contravened
__________________________________________________
Environmental Preservation Acts in India
4
E & C Division
Comply with the directions issued in writing by the PCB, within the
specified time, as mentioned in the order. The directions may
include:
1. the closure, prohibition or regulation of any industry,
operation or process; or
2. the stoppage or regulation of supply of electricity, water
or any other service
Responsibilities
Rights
__________________________________________________
Environmental Preservation Acts in India
5
E & C Division
__________________________________________________
Environmental Preservation Acts in India
6
E & C Division
Obligations
Pay penalty for non-payment of cess, within the specified time, not
exceeding the amount of cess, in arrears, after being given a
reasonable opportunity of hearing.
Responsibilities
Submit the " Water Cess Return" in the prescribed form, at specified
intervals, to the PCB.
Right
ii)
__________________________________________________
Environmental Preservation Acts in India
7
E & C Division
__________________________________________________
Environmental Preservation Acts in India
8
E & C Division
Obligations
Provide access to the PCB or any officer empowered by it, for taking
samples of air or emissions from the industrial plant for the purpose
of analysis
Comply with the directions, issued in writing by the PCB, within the
specified time as indicated in the order. The directions may include :
1. the closure, prohibition or regulation of any industry,
operation or process or
2. the stoppage or regulation of supply of electricity, water or
any other service
Industry to provide all facilities required by the PCB official for the
purpose of sampling.
__________________________________________________
Environmental Preservation Acts in India
9
E & C Division
Responsibilities
Rights
__________________________________________________
Environmental Preservation Acts in India
10
E & C Division
industry, within the specified time (15 days from the date of service
of notice)
__________________________________________________
Environmental Preservation Acts in India
11
E & C Division
Obligations
2.
__________________________________________________
Environmental Preservation Acts in India
12
E & C Division
Responsibilities
Rights
__________________________________________________
Environmental Preservation Acts in India
13
E & C Division
THE
HAZARDOUS
WASTES
(MANAGEMENT
AND
Responsibilities
Rights
__________________________________________________
Environmental Preservation Acts in India
14
E & C Division
__________________________________________________
Environmental Preservation Acts in India
15
E & C Division
6
MANUFACTURE,
AND
IMPORT
OF
HAZARDOUS
Responsibilities
Occupier
to
submit
"Safety
Report"
containing
the
prescribed
__________________________________________________
Environmental Preservation Acts in India
16
E & C Division
Occupier
to
prepare
on-site
"emergency
plans"(refer
__________________________________________________
Environmental Preservation Acts in India
17
E & C Division
2.
Site,
Construction design,
Accessibility of plant.
3.
4.
Process description,
Chemicals
(quantities,
substance
data,
safety-related
data,
The form in which the chemical may occur on or into which they
may be transformed in the event of abnormal conditions.
5.
6.
Types of accident
Hazards
Safety-relevant components.
__________________________________________________
Environmental Preservation Acts in India
18
E & C Division
Quick-acting valves.
Sprinkler system,
Identification of hazards,
Safety systems,
10.
Fire brigade
Alarm systems,
__________________________________________________
Environmental Preservation Acts in India
19
E & C Division
Coordination with the District Emergency authority and its off site emergency plan,
__________________________________________________
Environmental Preservation Acts in India
20
E & C Division
150mg/Nm3
Sulfur dioxide
50mg/Nm3
II.
Distillation
Feed
indicates
the
feed
for
that
part
of
the
process
under
consideration
III.
200/210 - 150 MW
<200/210 MW
__________________________________________________
Environmental Preservation Acts in India
21
E & C Division
Pollutants
Time
Method of
weighted
average
measurement
Industrial
Residenti Sensitive
area
al , Rural Area
& other
Sulfur dioxide
Annual
average*
80 pg/m3
50 pg/m3 15 pg/m3
Gaeke
24
2. Ultraviolet
hours**
Oxides of
Nitrogen (as
N02)
Annual
average*
Fluorescence
80 pg/m3
60 pg/m3 15 pg/m3
3
30 pg/m
(Na-Arsenite) method
24
2. Gas phase
hours**
Suspended
Particulate
Matter (SPM)
Respirable
Particulate
matter (size)
less than
Annual
average*
Chemiluminescence
360 pg/m3 140
3
70 pg/m3
3
24
200
hours**
pg/m3
Annual
average*
2. Respirable
particulate Matter
50 pg/m
75 pg/m
24
1. High volume
3
pg/m
sample
hours**
10pm)(RPM)
Lead (Pb)
Annual
average*
1.5 pg/m
0.50
3
pg/m
pg/m
24
1.00
0.75
hours**
pg/m3
pg/m3
hour
1.00
3
10.0
pg/m
pg/m
infrared Spectroscope
2.00
__________________________________________________
Environmental Preservation Acts in India
22
E & C Division
**
__________________________________________________
Environmental Preservation Acts in India
23
E & C Division
Pollutant Characteristics
Max. Permissible
Concentration*
6.0-8.5
Suspended solids
20
14.
15
10.5
10
Phenols
0.70
Sulphides
0.5
0.35
PH
__________________________________________________
Environmental Preservation Acts in India
24
E & C Division
TABLE: 5
The standards proposed by the Central Board were reviewed by the Core
and Peer Groups constituted by the Central Board. The Standards
recommended by the Core and Peer Groups are presented below:
Parameter
PH
6.5-8.5
*BOD5, 20C
50
COD
250
**Phenol
Cyanide as CN
0.2
Sulphide as S
***Fluoride as F
15
****Hexavalent Chromium as Cr
0.1
Total chromium as Cr
100
State Board may prescribe the BOD value of 30mg/l, if the recipient
system so demands
**
***
**** " The limits for total and hexavalent chromium shall be conformed
to at the outlet of the chromate removal unit. This implies that in
the final treated effluent, total and hexavalent chromium shall be
lower than prescribed herein
__________________________________________________
Environmental Preservation Acts in India
25
E & C Division
Parameter
Standards
Inland surface
Waters
Public
Sewers
Land for
Irrigation
(a)
(b)
(c)
(d)
2.
Suspended solids,
100
600
200
3.
4.
pH value
5.5 to 9.0
5.5 to 9.0
5.
Temperature
receiving water
temp.
6.
7.
10
temperature
20
10
20
1.0
8.
50
50
50
9.
100
100
10.
5.0
5.0
11.
Biochemical Oxygen
Demand(5 days at 20C),
Mg/l, Max.
30
350
100
100
12.
250
250
13.
0.2
0.2
0.2
0.2
14
0.01
0.01
0.01
15.
0.1
1.0
2.0
16.
1.0
2.0
__________________________________________________
Environmental Preservation Acts in India
26
E & C Division
Table: 6 Contd.....
S. No. Parameter
Standards
Inland surface
Public Sewers
Waters
17
Land for
Marine
Irrigation
coastal
Areas
0.1
2.0
2.0
Cr+6),mg/l, Max.
18.
2.0
2.0
2.0
19.
3.0
3.0
3.0
20.
5.0
15
15
21.
0.05
0.05
0.05
22.
3.0
3.0
5.0
23.
0.2
2.0
0.2
0.2
24.
2.0
15
15
25.
5.0
26.
2.0
5.0
27.
1.0
5.0
5.0
28.
Radioactive materials
(a)
10-7
10-7
10-8
10-7
(b)
10-6
10-6
10-7
10-6
29.
Bio-assay test
90%survival of
fish after 96
hours in 100%
effluent
90%survival of
fish after 96
hours in 100%
effluent
90%survival of
fish after 96
hours in 100%
effluent
90%surviv
al of fish
after 96
hours in
30.
31.
32.
Vanadium (as V)
0.2
0.2
0.2
33
10
'
20
100%
__________________________________________________
Environmental Preservation Acts in India
27
E & C Division
Preservative
Acidity-alkalinity
Refrigeration at 4 "C
24hrs
BOD
Refrigeration at 4 "C
6hrs
Calcium
None required
COD
2 ml/LH2S04(Conc.)
7days
Chloride
Refrigeration at 4 "C
24hrs
Cyanide
NaOH to pH 10
24hrs
Dissolved oxygen
Determine onsrte
Fluoride
None required
Metals, total
5 ml/L HN03
6months
Metals .dissolved
6months
Nitrogen .Ammonia
7days
Nitrogen, Kjeldahl
Unstable
7days
24hrs
Organic carbon
2 ml/L H2S04,
7days
PH
None available
Phenolics
24hrs
pH 4.0, 4 "C
Solids
None available
Specific conductance
None available
Sulfate
Refrigeration at 4 "C
7days
Sulfide
2 ml/L Zn acetate
7days
Threshold odour
Refrigeration at 4 "C
7days
Turbidity
None available
__________________________________________________
Environmental Preservation Acts in India
28
E & C Division
Safety Procedures
Note: Some of the safety procedures followed in operating chemical
complex are given here these are for information purpose. The activities are
generally carried out by the maintenance personal of the plant in
consultation with operations department.
Procedural Control
E & C Division
9.1
2.
3.
The person collecting the sample should be fully aware about the
hazards of the plant and also the properties of chemical being collected.
4.
When sampling hot or corrosive liquids the person collecting the sample
must wear safety equipments like face shield, gloves, goggles, apron
etc.
5.
Ensure that the sampling point system is not damaged and physically in
good shape. Damaged sampling lines could be hazardous.
6.
7.
8.
9.
10. Purge volume of the sampling line of toxic should be collected in sample
bottle or bladder to be disposed in a controlled manner as per
procedure 8.2.
11. While collecting toxic sample wear gas mask specified for the chemical
or use breathing apparatus.
12. While collecting samples under pressure care should be taken to avoid
splashing of liquid or toxic gas jet formation.
13. Samples should be labeled and dispatched for analysis promptly.
Procedural Control
E & C Division
9.2
DISPOSAL OF WASTE
The waste material during commissioning may contain flammable, toxic and
hazardous chemicals it is recommended that the waste is disposed in
consultation with the environmental control department of the plant.
Handling precautions are as follows:
Solid Waste
Liquid
Disposal of liquid waste into the OWS done after consultation and with the
knowledge of the plants environmental central department.
Gases
Procedural Control
E & C Division
9.3
PROCEDURE
PIPELINES
CLEANING,
GAS
FREEING
PROCEDURE:
Tank Cleaning:
a) Drain/pump out the contents
b) Fill the tank with water & drain.
c) Purge with steam if containing solvents or hydrocarbon liquids.
d) Purge with inert gas if containing fire hazardous gases.
e) Purge with air after purging with inert gas before entry. (Entry
with fire Safety Permit only).
f) Remove all sludge, deposits inside the tanks.
When closed piping systems are parted for replacing valves, servicing pump
replacing sections of lines etc this is called "Opening Lines". This type of
work not properly planned can lead to serious accidents.
To protect against such accidents the following rules must be followed while
performing such work:
1
Procedural Control
E & C Division
2
Check to make sure all valves are properly positioned. All drain valves
should be opened.
Although the previous steps have been taken, the job should be
performed as though the line is full and under pressure.
a)
A sloping line may have a plug, a valve and another plug. You can
open the valve to drain the line, but it could still be full between
the plugs.
b)
A horizontal line may have sag or dip in it. You can open the line
up and blow it out, but there could still be acid or other material
where the line is sagging, if that section of the line is taken out
and tilted, the material will run out.
c)
You can't drain a line if the valve, you are trying to use is lower
than the discharge end of the line.
d)
5.
6.
a)
Protective suit.
b)
Face shield.
c)
PVC gloves.
b)
These are the edges of the flanges that should be opened first.
c)
Keep the bolts near, you tight, and slowly open the ones away
from you. A quarter of a turn at a time is not too little.
d)
If the flange stays tight, start a wedge between the flange on the
side where the bolts were loosened.
Procedural Control
E & C Division
e)
When you are sure the flange is open and that any drip is over,
remove the rest of the bolts and nuts.
Lines taken out or brought to the shop can also be hazardous. Further
handling or dismantling in the shop could release material. The only
fitting or section of line that is safe is one that has been blowout,
washed out and looked through and tested.
After a section of line has been removed the remaining open flanges
should be blinded.
2.
3.
4.
Rate of release.
b)
Sources of ignition
c)
Wind direction
d)
Procedural Control
or
E & C Division
5.
6.
7.
8.
9.
10.
Procedural Control
E & C Division
9.4
2.
The procedure outlined shall be to first try to clear the line by applying
a solvent directly in to the closed line. Normally this is done with
steam or water applied to permanent connection of hose.
Compatibility of the de-plugging liquid with the fluid contents
of the pipe should be verified before using the technique
(remember Bhopal)
3.
4.
Procedural Control
E & C Division
5.
If the plug does not respond to the above clearing procedure, probably
it will be necessary to dismantle the line.
6.
7.
All tracing and jacketing should be shut off and the line allowed to
cool.
8.
Protective suit.
b.
Face shield over the helmet and glasses (if a full cover one piece
suit is available the same should be used).
c.
10.
If the cleaning can be carried out by attaching valves and hoses and in
a closed manner the same should be attempted.
11.
12.
b.
c.
d.
e.
Procedural Control
E & C Division
concerned.
f.
13.
Procedural Control
10
E & C Division
9.5
2.
3.
The following safe maintenance procedures are followed for undertaking the
job.
1.
Keep the sealing plate (as per figure 1 below) and special bolts ready,
suitable for the size of the flare pipe to be isolated. The special bolts
have a small head, which will pass through the bolt-holes of safety
valve flange, but not through the holes of sealing plate.
2.
Keep gaskets, nuts & bolts & proper size of spanners & tools ready for
the job.
3.
Rouse one by one all the bolts & nuts of the flange of the pipe.
4.
5.
6.
7.
8.
Insert special bolts in the holes where bolts 'A' were to hold the seal
plate tight to the flare pipeline.
9.
When the small bolts are tight remove bolts 'B' Ensure that seal plate is
holding property.
b)
Procedural Control
11
E & C Division
c)
d)
e)
f)
Special Precautions
Before undertaking removal of S. V., ensure proper access and working
platform or scaffolding.
1.
2.
3.
4.
5.
6.
Make use of Brass hammer if required or Non sparking Tools for such
jobs.
7.
8.
Keep water hose & fire extinguishers ready for use, in case of any
emergency.
Procedural Control
12
E & C Division
9.6
Note:
Work Permit system specified in Oil Industry Safety Directorate guidelines is
reproduced here. The purpose is to familiarize with the work permit system
prevailing in Hydrocarbon industry. The actual formats may vary; however,
the procedure is to be based on the OISD -105 guidelines.
9.6.1
INTRODUCTION
9.6.2
SCOPE
The Work Permit System shall cover all hydrocarbon processing / handling
installations such as onshore / offshore processing platforms, gas treating
units, crude terminals, refineries, pipelines, marketing installations, and LPG
bottling plants.
Procedural Control
13
E & C Division
9.6.3
a)
DEFINITIONS
Hot work: Hot work is an activity, which may produce enough heat to
ignite a flammable air hydrocarbon mixture or a flammable substance.
b)
Cold Work : Cold Work is an activity which does not produce sufficient
heat to ignite a flammable air hydrocarbon mixture or a flammable
substance.
9.6.4
Two types of permits, one for cold work and the other for hot work, are the
minimum requirements, which must be fulfilled before commencing work.
Based on the nature of the work that is to be undertaken, permit should be
obtained either under Hot Work Permit or Cold Work Permit. For jobs like
excavation, road / dike cutting, electrical lockout / energizing etc. where the
work permit issuing authority may have to take clearances from other
sections / personnel, organizations may introduce supplement formats
for these purposes. If they wish, format for electrical lockout energizing
is given in OISD-Std. 137 (on Inspection of Electrical Equipment).
9.6.5
b)
c)
Separate forms shall be used for Hot Work and Cold Work.
d)
For
simplification
of
procedure,
Hot
Work
Permit
also
covers
Procedural Control
14
E & C Division
g)
Permit should be issued only for a single shift and its validity should
expire at the termination of the shift. However, where the work has to
be continued, the same permit may be revalidated in the succeeding
shift by authorized person, after satisfying the normal checks.
Procedural Control
15
E & C Division
j)
Where gas free conditions are not fully assured for the duration of hot
work, a system of monitoring either by automatic or by manual
periodic verification shall be resorted to depending upon the prevalent
conditions of the operating area.
k)
9.6.6
Specimen Work Permit forms for the two types of permits illustrating the
suggested colour code, layout, and size are exhibited in pages 5-14 of OISD
105.
9.6.7
The check-listed items in the Work Permit Forms are elaborated below to
amplify the underlying concepts and highlight their significance.
i)
Procedural Control
16
E & C Division
ii)
conditions
for
performance
of
work
may
arise
from
gases
may
be
released
from
nearby
sewers.
Hot
v)
vi)
vii)
viii)
Procedural Control
17
E & C Division
containing
liquid
hydrocarbons
should
be
drained
xi)
xii)
Procedural Control
18
E & C Division
(a)
(b)
(c)
19
E & C Division
precaution
against
static
electricity
generation,
portable
Procedural Control
20
E & C Division
Procedural Control
21
E & C Division
9.6.8
E&C division has an elaborate work permit system and has following work
permits:
1. Hot Work Permit
2. Cold Work Permit
3. Confined Space Entry Permit
4. Electrical Lines / Equipment Work Permit
5. Radiography Work Permit.
Formats:
Formats for each type of work permit are reproduced of at the end of this
Chapter.
Validity:
The permit is to be renewed each day only after checking all the compliance
jointly by the E&C Site Engineer and the contractor site-in-charge. The
permit can be renewed for not more than 7 times including the issue date.
Safety Instructions:
Specific Safety Instructions to be followed strictly during the work are
printed on the backside of the work permit and are reproduced here.
Hot Work:
1.
2.
Materials which can catch fire / get damaged due to sparks, metal
globules falling on them during Hot Work shall be covered with "Fire
Procedural Control
22
E & C Division
blanket".
3.
One DCP type 5 Kg. Capacity portable fire extinguisher shall be kept
near Hot Work Place.
4.
All persons engaged in "Hot Work" shall be provided with all necessary
Personal Protective Equipment like; Welding Screen; Asbestos hand
gloves; Safety Shoes; respiratory mask; and Apron and they shall wear
these while working.
5.
While doing Hot Work in confined space one stand-by person shall be
kept outside the vessel, to assist in case of emergency, and the
emergency exit shall be kept open.
6.
b)
7.
Empty drums shall not be used instead of ladder for standing on it.
8.
9.
10. This permit shall be cancelled if any deficiencies are noticed during the
work.
11. Explosimeter reading shall be taken before starting of hot work and
must be entered in the space provided in the permit.
Procedural Control
23
E & C Division
__________________________________________________
Personnel Protective Equipment(PPE)
1
E & C Division
10.1
NON-RESPIRATORY
These equipment are used to protect following non-respiratory body
parts
10.1.1
HEAD PROTECTION : INDUSTRIAL SAFETY HELMET:
Presently available with cushioned end adjustable suspension cradles
and two-three different sizes with IS certificates. These helmets are
impact resistant, electrical shock-proof & comparatively light in weight
(400 to 500 gms). This gives protection for common hazard of striking
objects, falling objects as well as chemical splashes.
Up-keep and maintenance
Safety helmets are individually issued to all employees. The
suspension cradles are washable and replaceable. Drilling of holes or
tampering with the shell is unsafe, as this will reduce the strength of
the helmet against impact. For proper fitting and grip, the chin-straps
should also be tied after wearing the helmet.
10.1.2
EYE - PROTECTION :
Industrial eye injuries are caused due to flying objects like chips,
splinters, etc. dusts, liquid chemical splashes, glares due to harmful
radiation etc. Following charts show the requirements of specific type
of goggles / eye protection for specific use:
Types
Safely spectacles with
frame
clear lens
glass
Brief Description
Combustion resistant plastic
or
metal
Recommended use :
Babbiting, butting, chipping, minor dust hazards, grinding machine
shop
operations, spot and butt welding, etc.
Safety spectacles with
frame
coloured or filter lens
Combustion
resistant
plastic
or
metal
__________________________________________________
Personnel Protective Equipment(PPE)
2
E & C Division
Impact goggles
glass or
plastic
lenses.
Ventilation
is
provided
through
sides of the cup and slots in the lens
retaining
rings.
Recommended use
Chipping, fitting, grinding, riveting, boiler & other fabrication work,
hand & power tools, machine shop operations, wood working, spot
and butt welding, dusts etc.
Welding goggles
adjustable
Combustion
resistant
plastic
cups
and
__________________________________________________
Personnel Protective Equipment(PPE)
3
E & C Division
Recommended use
Extremely fine dusts and particles.
Chemical Goggles
rolled
fabric of
the cups.
Recommended use
Acids, caustic and other chemicals, dusts and particles, light impacts
etc.
Eye screens and face shields
the
visor may
be clear or tinted plastic or fine wire
mesh or
a combination of tinted plastic and wire
mesh.
Recommended use
Babbiting, Chemicals, furnace operations spot and butt welding, flying
particles, frontal splashes, glare molten metals etc. and for additional
protection over the gogglesWelding shields
window
with
clear cover glass to protect the filter
glass
from pitting. The shield may be held in
hand
or suspended in front of the face by a
head
__________________________________________________
Personnel Protective Equipment(PPE)
4
E & C Division
shield
can
be
raised
off
the
face
when
protection is
not required and dropped back into
position
by a sharp downward motion of the
wearer's
head.
Recommended use
Arc welding, atomic hydrogen welding.
10.1.3
HAND PROTECTION
About 22% of industrial accidents injure hands.
The following chart gives an idea of how to select the proper type of
gloves for the
specific job and hazard.
HAZARDS
Sustained heat
MATERIALS
Asbestos
Asbestos
reinforced
with
leather
Aluminium faced fabric
Sparks
Asbestos
Asbestos
reinforced
with
leather
Fire resistant fabric
Leather
Glass fibre
Hot metal splash
Leather
Fire resistant fabric
Glass fibre
Dust
Fabric
Coated fabric
__________________________________________________
Personnel Protective Equipment(PPE)
5
E & C Division
Sharp object
Fabric
Abrasion
Leather
Coated fabric
Teflon
NBR
(Nitric
Butadiene
Rubber)
Cuts
steel
Leather
reinforced
with
staples
Metal Mesh
Electric Circuit
Rubber
Moisture
Coated fabric
Natural rubber
Synthetic rubber
Plastic
Glass
fibre
Acids, alkalis and other natural
materials
rubber chemicals
Petroleum products
plastic
X-ray
In
some
cases
synthetic
10.1.4
FOOT & LEG PROTECTION
Manual as well as mechanical handling of materials are part of the
day-to-day industrial activities. The statistics on occupational injuries
show that about 23% of the accidents occur during material handling.
__________________________________________________
Personnel Protective Equipment(PPE)
6
E & C Division
Toe and foot injuries are common in industry while handling materials
or getting struck on obstructions while working.
Adequate foot protection against impact on toes as well as exposure of
foot to chemicals, dusts, dirty materials etc. will go long way in
reducing injuries. Most common foot protection in industries are :
1) Safety shoes and boots
2) Legging
3) Foot guards and leg guards
1)
Safety (Toe) Shoes:
They appear just like any other normal leather shoes except for the
additional provision of a concealed steel cap above the toe portions.
This provides additional protection from impact and crushing force. In
few cases a steel innersole is provided for protections against
punctures from nails, glass pieces etc. But, now a days, sturdy rubber
soles are available which serve the above purpose. Common utility of
safety shoes is in construction sites, engineering industries, foundries
as well as chemical operating plants. The soles are also provided with
Non-Slip strips at the bottom.
2)
E & C Division
5)
Asbestos overshoes:
These may be with leather sole and recommended for protection
against heat, sparks and for operation at coke, asphalt & steel plants.
6)
Leggings:
The leggings may be knee high or hip high or they may be spats which
shield the lower shin, ankle and instep. Knee leggings are held in place
by metal spring clip or may wrapped round the leg and fastened with a
snap button or similar quick release device. Hip leggings are
suspended by straps from waist belt. The spats are generally held in
position by straps. The leggings and spats are made of appropriate
material depending upon the hazard as choosing gloves and shoes.
7)
Foot guards & leg guards :
Foot guard is a steel / plastic guard, which may be attached to the
shoe when circumstances require. Foot guard is held in place by a heel
strap. Leg guard is similar to a foot guard. It is a metal sheet, which
protects the skin and ankle. This is strapped to the leg and offers
protection against falling weights & impacts from striking objects.
10.1.5
BODY PROTECTION :
Even after protecting head eyes, face, ears and limbs, some times
injury may occur to the trunk portion of the body. Aprons, overalls
jackets and some time complete head to toe suits are used to protect
the trunk.
Aprons :
These may be bib type, covering the chest, waist, knees, or ankles or
up to waist only. Aprons may be used to protect against heat, sparks,
hot metal splashes, impact cut hazards and liquid splashes or
radiations.
Jackets and coats:
Jackets are for protection of the general upper section of the body.
covering the body and attending to the hips. Coats are longer then
jackets and may be of knee or ankle length.
__________________________________________________
Personnel Protective Equipment(PPE)
8
E & C Division
Complete suits :
These units cover the wearer from head to foot. Generally this consists
of overalls or trousers topped by short jackets and hoods. Suits may
be made of materials such as oiled fabric, plastic coated fabric, glass
fibre, conductive plastic, natural rubber, synthetic coated fabric
asbestos and fire resistant fabric.
10.1.6
EAR PROTECTION :
Continuous exposure to excessive noise can often result in serious
hearing impairment or deafness. High noise levels endured over long
period also result in fatigue, loosening of efficiency and making
persons irritable and may even result in loss of hearing. Hearing loss
varies with the type of exposure and the total duration of exposure. A
committee formed under the American Conference of Government
Industrial Hygienists in USA have agreed to the following points to
establish threshold limit values for noise :
1.
Exposure to 90 dBA (i.e. 'A' scale reading of sound level meter)
for an eight hours per day, five days a week is not injurious to
about 90% of the people exposed. It may be stated here that 'A'
scale reading is used for hazard rating only but if studies are
made for the purpose of engineering control, the octave band
analysis should be made of the noise.
2.
Equal energy will produce equal damage to the ear. Based on
this assumption if sound level is increased by 3 decibels the
exposure time should be reduced to half. If noise is intermittent,
ear can tolerate more acoustical energy than for a single
exposure to continuous noise.
3.
Considering these two factors, the limit is increased to 5 decibels
for each halving of the exposure time.
The following table may be taken as a guide to control the noise
hazard. The
exposure should not exceed the duration shown below against each
sound level:
Duration per day (hours)
Sound level (dBA)
8
90
6
92
4
95
3
97
__________________________________________________
Personnel Protective Equipment(PPE)
9
E & C Division
2
1
1
When noise levels exceed the above values, ear protectors have to be
used.
Common types of ear protectors are ear plugs and ear muffs. Ear
plugs attenuate a large part of the noise when properly fitted in the
outer portion of the ear canal. These are usually made of rubber,
plastic or similar non-porous pliable material. It is important that ear
plugs fit properly and remain correctly seated because even the
slightest leakage will lower the amount of attenuation. Ear plugs if
properly fitted and used, generally reduce noise reaching the ear by
25-30 dB in the higher frequencies, which are more harmful.
EARMUFFS
Earmuffs are designed to cover the external ear. These are suspended
from
adjustable head band or nape bands. The attenuation provided by ear
muffs varies due to difference in size, shape, sealing material, shell
mass and type of suspension. The type of cushion used between the
shell and the head has a great deal to do with attenuation efficiency.
Liquid or grease filled cushions give better results than plastic or foam
rubber type Better type of ear muffs may have 10-15 dB better
attenuation than that of ear plugs.
10.2
INTRODUCTION
There are three modes of entry of matter into human body.
(1) Inhalation through nose / mouth.
(2) Ingestion through mouth.
(3) Skin absorption.
In the simplest physiological term, respiration is "taking oxygen from
atmosphere, converting it into energy by circulation through blood and
__________________________________________________
Personnel Protective Equipment(PPE)
10
E & C Division
venting out carbon dioxide, the by product and waste in this reaction."
The tireless lungs do this function at a rate of 20-24 times a minute
and repeats through out our life term. Since this is such an automatic
function proceeding unknowingly, many of us take it for granted that
there is nothing particular. The fact is reverse. Even a slightest change
in the flow of quality or quantity of air we breathe makes lot of
difference. As we all are aware the air we breathe is a mixture of about
22% oxygen and remaining Nitrogen with traces of carbon dioxide,
moisture, rare gases etc. A difference of 10-12%, oxygen below 20%
for about 6-8 minutes means a difference between life and death. The
chart shown below illustrates this fact in a better way.
Signs and symptoms from reduced level of oxygen in atmosphere are
as below :
% O 2 in air
Effect
Above 20
Normal
12-15
Muscular co-ordination for skilled
movements is lost.
10-14
Consciousness
continues,
but
judgement
is faulty and muscular effect leads to
fatigue.
6-8
Collapse occurs rapidly but quick
treatment
prevents
fatal
outcome.
Below 6
Death occurs in 6-8 minutes.
In a chemical industry where different types of toxic gas, vapours,
dusts, fumes, etc and asphyxiating gases like Nitrogen, Carbon
dioxide, etc. are likely to be present the importance of identifying the
hazards, controlling / confining and using proper effective breathing
protective gears need not be over emphasized.
10.2.1
DESCRIPTION OF HAZARDS :
i)
Type of hazard-whether toxic/poisonous or asphyxiating.
Toxic / poisonous - Chlorine Ammonia, Cyanides, hydrocarbon, etc.
which react with blood and makes it impure.
__________________________________________________
Personnel Protective Equipment(PPE)
11
E & C Division
Asphyxiating - Nitrogen, C02 etc. which do not react with blood but
obviously stop the oxidation process in the blood by reducing oxygen
content.
ii)
Dusts, fumes, etc
Asbestos, Catalyst fine, Glass-wool Insulation fines, silica, carbon, etc.
which block the respiratory track and deposit foreign particles in the
lungs.
While choosing a personal protective equipment for respiration we
should consider the type of hazards as mentioned above and select
the correct type equipment. Remember using a wrong equipment may
mean immediate danger to life. That is why invariably respiratory
protective equipment are known as emergency equipment also.
10.2.2
1.
2.
3.
4.
5.
6.
7.
8.
E & C Division
organic vapours are also available, covering mouth & nose portion,
which is lighter and easy to wear.
Limitations :
i)
It shall not be used where oxygen content in the
atmosphere is less than 18% by volume in the air.
ii)
The gas mask should not be used where gases are
present at more than 2% by volume or the figure
indicated by the manufacturer.
Operation and Use:
i)
Check for proper type of canister to be used.
ii)
Remove the seal from the bottom of the canister and put
on the headpiece.
iii)
Adjust the head strap until the mask fits closely and
comfortably to avoid leaking.
After Use:
Enter in the card the duration of use of canister Gas Mask.
CAUTION: NEVER USE A CANISTER WHOSE SELF LIFE (MENTIONED
ON
THE SHELL) HAS BEEN EXPIRED.
10.2.2.2
__________________________________________________
Personnel Protective Equipment(PPE)
13
E & C Division
Limitations:
1. It has got the service life of maximum one hour.
2. It can be used only at a temp. above 32F, provided hard
work is not to be performed.
3. It can not be used in the explosive atmosphere where the
auto-ignition temp. is 600F.
4. This equipment cannot be used under water and in open
fires.
Preparation for use:
Install canister into apparatus before wearing the apparatus.
i)
Installing Standard Type Canister:
Be sure that the copper foil seal must be fully exposed before
inserting Canister. Lift up on tip of plastic cap until seal is broken
completely. Remove the remaining of the cap exposing the air
tight copper foil canister seal. With the hand wheel screwed
down far enough for the bail to be swung outward, and insert
canister fully into canister holder with the smooth side to the
front.
It is to be inserted in a way so that the copper foil seal is
punctured and the rubber gasket fits against the V-shaped
recess in the plunger casting. Screw the hand wheel clockwise
until it is tight against the canister.
ii)
iii)
The canister will produce more oxygen than needed and hence
the breathing bags will become over inflated and resist
exhalation. The excess volume can be vented out by depressing
the button valve on the face piece, but do not over vent.
iv)
__________________________________________________
Personnel Protective Equipment(PPE)
14
E & C Division
E & C Division
Compressed
Air
Cylinder
E & C Division
E & C Division
__________________________________________________
Personnel Protective Equipment(PPE)
18
E & C Division
10.2.2.5
E & C Division
i)
ii)
Use:
i)
ii)
iii)
Limitation :
This is not a completely dependent system.
10.2.2.7 Resuscitator:
To restore normal breathing when accidents or illness interferes with
respiration, two different devices / equipments are used. They are as
follows:
a) LA-IF resuscitator.
b) Pneolator.
a) LA - IF resuscitator :
This is a bellow type hand operated equipment used for giving artificial
respiration. It has also got a provision at one end of the aspirator bulb,
to connect extra 02 cylinder so that pure oxygen can also be
administered.
Limitation :
i)
Limited quantity of air-blow can be achieved.
ii)
Continuous manual administering of compressed air is
required without any interruption.
Operation and use:
i)
Before use, remove the air from the aspirator bulb by
squeezing it. Repeat the same 2 to 3 times.
__________________________________________________
Personnel Protective Equipment(PPE)
20
E & C Division
ii)
Precaution :
The aspirator bulb should be checked and cleaned prior to use of
equipment.
b) Pneolator:
Introduction:
Pneolator is an instrument that automatically performs artificial
respiration with a gentle predetermined pressure on inhalation and
without suction on exhalation. When the victim is breathing, this
instrument is very much effective for applying Oxygen by a simple
adjustment. If the air passage is obstructed by mucous or any foreign
material, immediately a warning is given by a chattering sound from
the valve. This obstruction can be removed by using the ejector
provided with the Pneolator.
Operating instructions (for the non-breathing victim) :
i)
Open the lid of the case and turn on cylinder valve
fully.
ii)
Remove cycling valve assembly from holder and
select and attach the proper size of mask.
iii)
Turn the pressure adjusting knob, so that the low
pressure gauge needle is set (at Infant, Child or
Adult) as required. The pressure increases as the
knob is turned anti-clockwise.
iv)
Place the mask on the victim's face holding it
secured, so that air tight seal is obtained. The
exhalation valve cover murt be hand tight for the
purpose of cycling valve.
Caution:
i)
__________________________________________________
Personnel Protective Equipment(PPE)
21
E & C Division
ii)
__________________________________________________
Personnel Protective Equipment(PPE)
22
E & C Division
11.0
General
Besides the fixed installations for identifying, monitoring and
controlling hazards such as flammability, toxicity and Oxygen
deficiency, portable and robust instruments are needed during the
commissioning period as well.
Various types of portable instruments such as Explosive meter, Toxic
Gas detector are available. They are to periodically checked and
ensured that they are in good working conditions, before being put
into actual use by the commissioning team.
11.1
E & C Division
__________________________________________________
Gas Detection Devices
2