Professional Documents
Culture Documents
Conceptual
Design and
Program
Project
Cost
Estimate
SELECTED SITES
Pine Grove Road/Central Park Drive
(YVMC)
Fox Creek US Highway 40 and Hilltop
Pkwy
Steamboat 40 US Highway 40 (south of
Hampton Inn)
CIP PRIORITIZATION
Rank 1-5
Multiplier of Multiplier
5
of 4
Multiplier of 5
Multiplier of 3
Cost effectiveness
(will it save money
immediately or if
Satisfaction of
Adopted not done now will it
legal/contractua Health and
City
have a prohibitive
cost later?)
l obligations
safety
policies
114
110
Police Station
Pedestrian Sidewalks, Bicycle, & Transit
Facilities
106
104
104
104
104
Igloo Modular
103
102
102
M O R E W A L K A B L E P L A C E S P E R F O R M B E T T E R E C O N O M I C A L LY. A S T H E N U M B E R O F
E N V I R O N M E N T A L F E AT U R E S T H AT F A C I L I T AT E W A L K A B I L I T Y A N D AT T R A C T P E D E S T R I A N S
I N C R E A S E , S O D O O F F I C E , R E S I D E N T I A L , A N D R E TA I L R E N T S , R E TA I L R E V E N U E S , A N D
FO R - S A L E R E S I D E N T I A L VA LU E S .
- C H R I S T O P H E R L E I N B E R G E R , S E N I O R F E L L O W , M E T R O P O L I TA N P O L I C Y P R O G R A M ,
BROOKINGS INSTITUTE
T O A C H I E V E A V I B R A N T, E C O N O M I C A L LY H E A LT H Y, G R O W I N G A N D V I TA L
D O W N T O W N , D E N V E R M U S T B E C O M M I T T E D T O A S U S TA I N E D E F F O R T I N E A C H
O F T H E E L E M E N T S : P RO S P E RO U S , WA L K A B L E , D I V E R S E , D I S T I N C T I V E A N D
GREEN.
-DOWNTOWN DENVER AREA PLAN
Before
Before
After
After
Before
After?
R E P U R P O S I N G A B U I L D I N G T H AT H A S T H E P O T E N T I A L T O O F F E R A F I N A N C I A L
R E T U R N F O R T H E C O M M U N I T Y, I S A L S O A N I M P O R TA N T C O N S I D E R AT I O N . T H E
F I N A N C I A L R E T U R N C O U L D B E I N T H E F O R M O F P R O P E R T Y TA X E S , J O B S , H O U S I N G ,
NEEDED PUBLIC SERVICES, OR THE POTENTIAL OF SPURRING ADDITIONAL
B U I L D I N G R E V I TA L I Z AT I O N .
- A COMMUNIT Y GUIDE TO REPURPOSING VACANT AND UNDERUTILIZED HISTORIC BUILDINGS
PROGRAMMING
PoliceFacility
15,058sf
15,058sf
Sitework/utilities/landscaping
Accessroad/parkinglot/sidewalks
Architectural/Engineering
ConstructionManagement
GeotechEngineer
Tapfees
Buildingpermitfees
FF&E
Phone&datawiring
Contingency
TotalConstructionCost
UnitCost
$350
LS
LS
10%
2%
LS
LS
LS
LS
LS
10%
Total
$5,270,300
$501,600
$541,750
$631,365
$105,406
$25,000
$47,000
$25,000
$250,000
$100,000
$631,365
$8,128,786
FUNDING SOURCES
$6,128,786
Capital Fund
$2,000,000