Professional Documents
Culture Documents
fm200 PDF
fm200 PDF
SECTION 1 - INTRODUCTION
CONTENTS
CONTENTS
SECTION 5 - INSTALLATION
General Information ...................................... 38
Container Installation ................................... 38
Single Container Installation ......................... 39
Table 11: Bracket Fixing Heights ............ 39
Multiple Container Installation ..................... 40
Manifold Bracket Installation ................ 40
Table 12: Manifold Bracket Height ........ 41
Pipe Installation ............................................ 42
Table 13: UK Steel Pipe Requirements ... 42
Table 14: UK Fittings ............................. 42
Table 15: US Steel Pipe Requirements .... 43
Table 16: US Fittings .............................. 43
Pipe Hangers ......................................... 43
Table 17: Hanger Spacing ...................... 43
Earthing & Electrical Clearance........................ 44
Table 18: Safety Clearances ................... 44
Nozzles .......................................................... 44
Actuation Installation ................................... 45
Single Container Actuation ................... 45
Multiple Container Actuation ................ 47
Ancillary Equipment ..................................... 49
Discharge Pressure Switch .................... 49
Low Pressure Switch ............................. 50
Accessories .................................................. 50
Door Notices ......................................... 50
Manual Release Notices ........................ 50
Completion Procedures ................................. 50
Pre-checks and Visual Inspections ........ 50
Final Connections .................................. 51
Handover Procedures ................................... 52
HYGOOD
SECTION 7 - SYSTEM OPERATION
General Comments ........................................ 56
System Detection & Actuation ..................... 56
General ................................................... 56
Manual System ...................................... 56
Fully Automatic System ........................ 56
Fully Automatic System with Manual Intervention .................................................. 57
Conditions During a Fire ............................... 57
FM-200Concentration .......................... 57
FM-200 Decomposition ....................... 57
FM-200 Discharge Conditions ............. 57
Actions Following a Fire ............................... 58
General ................................................... 58
Actions Immediately Following a Fire ... 58
SECTION 8 - MAINTENANCE
Introduction .................................................. 59
User's Programme of Inspection ................... 59
Contract Service & Maintenance .................. 60
Mechanical Service Procedure ...................... 61
Specialised Maintenance Duties. .................. 62
Finally .................................................... 62
SECTION 9 - RECHARGING
Valve Refurb ................................................. 63
Testing .......................................................... 63
Container/Valve Assy ................................... 64
Filling ............................................................ 64
Table 19: Fill Tolerance Table ................. 66
Table 20: Temperature Correction Chart . 66
Container/Valve Assy Leak Test ................... 67
Decanting ..................................................... 67
Transportation .............................................. 68
HYGOOD
CONTENTS
SECTION 10 - WARRANTY,
DISCLAIMERS & LIMITATIONS
Warranty ....................................................... 69
Disclaimers & Limitations ............................. 69
SECTION 11 - APPENDICES
Appendix A - Site Survey / Request Form .... 71
Appendix B - Temperature Correction Chart . 73
Appendix C - Hughes Program printout ....... 74
Appendix D - FM-200 Material Safety
Data Sheet (MSDS).................84
SECTION 1 - INTRODUCTION
HYGOOD
Introduction
Definitions
FM-200
System
Engineered
Contacts
Should any part of this manual not be understood, or
there are any queries concerning a system, please contact:
Macron Safety Systems (UK) Limited
Woodlands Place
Woodlands Road
Guildford
Surrey
GU1 1RN
England
Tel.
Fax.
HYGOOD
FM-200 Agent
u
Macron Safety Systems manufacture in strict accordance with the internationally recognised Quality assurance Standard, BS EN ISO 9000 and approved to ISO
9001.
Macron Safety Systems FM-200 Extinguishing System
Units are to be designed, installed, inspected, maintained, tested and recharged by qualified, trained personnel in accordance with The Standard on Clean Agent
Fire Extinguishing Systems, NFPA2001, 2000 edition and
to be used in accordance with Environmental Protection
Agency (EPA) Significant New Alternatives Program
(SNAP). Where determined to be appropriate by the
authority having jurisdiction, applicable BS Standards
may additionally be utilized to specific system requirements for these purposes.
SECTION 1 - INTRODUCTION
WARNING
The discharge of clean agent systems to extinguish
a fire can result in a potential hazard to personnel
from the natural form of the clean agent or from the
products of combustion that results from exposure
of the agent to the fire or hot surfaces. Unnecessary
exposure of personnel either to the natural agent or
to the products of decomposition shall be avoided.
HYGOOD
SECTION 1 - INTRODUCTION
The present understanding of the functioning of FM200 is that 80% of its fire fighting effectiveness is
achieved through heat absorption and 20% through direct chemical means (action of the fluorine radical on the
chain reaction of a flame). Complete suppression using
FM-200 has the following advantages:
First Aid
Skin
Eyes
Bank Vaults
Libraries
Rare Book Stores
Electronic Data Processing
Telephone Exchanges
Studios
Communication Centres
Transformer and Switchrooms
Control Rooms
Test Laboratories
Flammable Liquid Stores
WARNING
FM-200 shall not be used on fires involving the following materials unless they have been tested to the satisfaction of the authority having jurisdiction:
Metal hydrides.
Chemicals capable of undergoing autothermal decomposition, such as certain organic peroxidase and
hydrazine.
HYGOOD
SECTION 1 - INTRODUCTION
HFC-227ea
CF3CHFCF3
Chemical structure
Chemical name
Molecular weight
Boiling point
Freezing point
Critical temperature
Critical pressure
Critical volume
Heptafluoropropane
170.03
-16.40C (1.9oF)
-131.10C (-204 oF)
101.70C (214 oF)
2912 kPa (422 psi)
274 cc/mole
(.0258cu Ft./lb.)
621 kg/m3 (38.76 lb./Ft3)
31.18 kg/m3 (1.95 lb./ft3)
Critical density
Saturated vapour density
@ 20 oC (68 oF)
(Reference: NFPA 2001, 2000 edition)
Table 2.
Agent Physical
Properties
Chemical structure
Chemical name
Molecular weight
Boiling point
Freezing point
Critical temperature
Critical pressure
(Reference: NFPA 2001, 2000 edition)
N2
Nitrogen
28.0
-195.80C (-320.4oF)
-210.00C (-346 oF)
-146.90C (-232.4 oF)
3399 kPa (492.9 psi)
Table 3: Toxicology/Environmental
FM-200
Environmental
Ozone Depletion (ODP)
Atmospheric Lifetime (yrs)
0
36.5
Toxicology
Acute Exposure LC50 (ppm)
Cardiac Sensitization
No Observed Adverse Effect Level (NOAEL)
Lowest Observed Adverse Effect Level (LOAEL)
>800,000
9.0%
>10.5%
HYGOOD
System Components
FM-200 Container
Technical Information
Manufactured in accordance with DOT(HSE)4BW500
or 4BW450.
Material
Carbon %
Manganese %
Phosphorus %
Sulphur %
0.220%
1.250%
0.045%
0.050%
max
max
max
max
4BW500
Hydraulic test pressure:
Working Pressure:
4BW450
Hydraulic test pressure:
Working Pressure:
Paint Specification:
Nom. Volume
Kg
(Lbs.)
4.5 to 8.0
9.0 to 17.5
17.0 to 33.5
27.0 to 53.0
53.5 to 106.5
74.0 to 147.5
91.5 to 182.0
(10 to 18)
(20 to 39)
(38 to 74)
(59 to 117)
(118 to 235)
(163 to 325)
(201 to 401)
Dimension A
Outlet Size
(nominal) Diameter Empty Weight
mm
(In) mm
(In) mm (In) kg
(Ibs)
25
25
25
50
50
50
50
(1")
(1")
(1")
(2")
(2")
(2")
(2")
304
502
833
596
1021
1354
1634
(12.")
(19.8")
(32.8")
(23.5")
(40.2")
(53.3")
(64.3")
254
254
254
406
406
406
406
(10")
(10")
(10")
(16")
(16")
(16")
(16")
14.8
18.4
26.1
49.1
71.8
89.9
105.8
(32.6")
(40.6")
(57.5")
(108.3")
(158.3")
(198.2")
(233.2")
9
HYGOOD
Container Label
The container label details the weight of FM-200 contained, empty weight, fill density and charge date. Once
the label is applied to the container surface, and to avoid
possible tampering it can not be removed intact.
Figure 2 - Container Label
Technical Information
Material:
Aluminum
Adhesive:
Dimensions:
(13.8")
(1.9")
10
Fixing Brackets
HYGOOD
Figure 4 - Valve Assembly
Part No.
Cont.size
Dim.A
mm (in)
9011
8-32 Ltr
254mm dia. (10 in)
400 (15.75")
9012
52-180
406mm dia. (16 in)
600 (23.6")
Material:
Body Proof Pressure:
Outlet Adaptor:
Low Pressure Port:
Gauge Port:
Pilot Pressure Port:
Solenoid Adaptor Port:
Brass CZ 121
150 bar (2175 psi)
1" BSP, 2"BSP
1/8" NPT
1/8" NPT
1/4" BSPP
1/8" NPT
Principle of Operation
Valve Assembly
The Macron Safety Systems designed and manufactured container valve is the result of extensive research
and development and incorporates many unique safety
features. The valve assembly is factory-fitted to the
container and is supplied pre-assembled with a low pressure switch, pressure gauge and burst disc.
The Macron Safety Systems FM-200 valve is a highflow-rate device specially designed for fire protection
use. Operation is by means of a pressure-differential piston. Container pressure is used within the valve to create a positive force on the piston, sealing the valve
closed. Operation of the valve occurs when the upper
chamber is vented faster than the 'make up device' in the
shuttle can replace the pressure. Thereby allowing, the
shuttle to be forced up, and free flow of FM-200 from
the valve. Upper chamber pressure is released by the
electrical, mechanical or pneumatic actuator.
11
HYGOOD
Burst Disc
A burst disc is factory fitted to every valve assembly. It
is designed to rupture when the container becomes over
pressurised when subjected to temperatures above the
designed storage temperature of the container.
Figure 5 - Burst Disc
Technical Information
Technical Information
Body:
Rating:
Body:
Brass CZ 121
50 bar (725 psi) @ 50oC
(120oF)
Thread 25mm Valve(1") : M14 x 1.25 (Pt.No. 94080)
Thread 50mm Valve(2") : M18 x 1.00 (Pt.No. 94085)
Hole Orientation:
90o to Body
Torque:
18 Nm (13.3Ibs.ft)
(M14 Thread)
Torque:
20 Nm (14.8Ibs.ft)
(M18 Thread)
12
PS20
Proof pressure:
Connection:
Max. Current:
Voltage Range:
Hermetically sealed
Stainless Steel
Open at 20 bar +/-0.7 bar
(290 psi (+/- 10psi)
Close on rise at 24 bar
+/-0.7 bar (350 psi (+/- 10psi)
345 bar (5003 psi)
Brass 1/8" NPT
Max 2.9A
5-28 vdc
Wire leads
1.82m (6Ft)
Switch point:
Switch Type:
HYGOOD
Manual Actuator
The manual actuator is a simple strike knob assembly
which is fitted to the top of the valve assembly or solenoid actuator. Inadvertent operation is prevented by a
pin which has to be removed before activation.
Technical Information
Body:
Actuation Pin:
Pipe connection:
Min. Actuation Pressure:
Brass CZ121
Stainless Steel
1/4" BSPP Female
2 bar (29 psi)
Technical Information
Body:
Knob:
Safety Pin:
Actuation Pin:
Min Actuation Force:
Brass CZ 121
Nylon
Zinc Plated Mild Steel
Stainless Steel
25.5N (5.73 Ibf)
Pneumatic Actuator
The pneumatic actuator is an assembly similar to the
manual actuator but without the strike knob. Pressure
from a master container or other sources is used to
actuate the valve, via small bore piping or, preferably, a
flexible hose.
Figure 8 - Pneumatic Actuator (Part No. 2900)
Technical Information
Body:
Swivel nut:
Actuation Pin:
Actuation Type:
Rest Requirement:
Connection:
Power requirement:
Current:
Manual Actuation Force:
Electrical connection:
Diode Type:
Temperature Range:
Life Span:
Testing:
Approval:
13
HYGOOD
The flexible discharge hose is connected to each manifold valve outlet. A swivel fitting at the inlet of the hose
enables the container to be readily coupled to the distribution system. The 32mm (1 1/4") discharge hose (Part
No.4120) requires the addition of a brass adapter (Part
No. 6412) between the valve outlet and the swivel fitting
at the inlet of the hose.
Figure 11 - 32mm (1 1/4") Hose & Brass Adapter
Assy (Part No. 4125)
Technical Information
Solenoid Enclosure:
Power Requirement:
Power Consumption:
Conduit Thread:
Pressure Connection:
Pressure Range:
Certification:
Max. Ambient Temp:
Solenoid Orientation:
Stainless Steel
24v dc
9.5 watts
1/2" NPT
1/8" NPT Female
0 - 103 bar (1500 psi)
UL
105oC (221oF)
0-30o Off Vertical
Technical Information
Construction:
Connection:
14
HYGOOD
Solenoid Adaptor
Technical Information
Technical Information
Body:
Circlip:
Max Working Pressure:
Proof Pressure:
Solenoid Connection:
Brass CZ121
Stainless Steel
75 bar (1088 psi)
150 bar (2175 psi)
1/8" NPT
Body:
Stem:
Spring:
Brass CZ122
Stainless Steel
Stainless Steel
15
HYGOOD
Manifold
Manifolds are fabricated sections of steel pipe-work. They enable multiple containers to be connected to a common
pipe network. They can be used in conjunction with check valves in situations where main / reserve containers
arrangements are required.
Technical Information
Material:
Inlet:
Outlet:
Test Press.
Finish:
BS 3601 Schedule 80
Check valve flange connection
BSP Taper
90 bar (1305 psi)
Primed, Ready to paint on site.
Table 5: Manifolds.
Part
No.
9335
9336
9337
9352
9353
9345
9346
9355
9356
9354
16
Size
mm
2 port
3 port
4 port
2 port
3 port
4 port
5 port
2 port
3 port
4 port
65 (2.5")
65 (2.5")
65 (2.5")
80 (3")
80 (3")
80 (3")
80 (3")
100 (4")
100 (4")
100 (4")
Dim. A
mm
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
150 (6")
Dim. B
mm
Pa rt
No.
350 (14")
350 (14")
350 (14")
508 (20")
508 (20")
508 (20")
508 (20")
508 (20")
508 (20")
508 (20")
9357
9358
9312
9313
9314
9315
9316
9317
9318
9319
Size
(m m )
Dim . A
(m m )
(6")
(6")
(6")
(6")
(6")
(6")
(6")
(6")
(6")
(6")
Dim . B
(m m )
508
508
508
508
508
508
508
508
508
508
(20")
(20")
(20")
(20")
(20")
(20")
(20")
(20")
(20")
(20")
HYGOOD
Part
Part
Part
Part
No.
No.
No.
No.
30460
30500
30510
30515
17
HYGOOD
Male Adaptor
The flexible pilot hose is used to connect pressure activated devices to the system, e.g. slave container, pressure switch, etc.
Technical Information
Material:
Connection:
Brass
1/4"BSPT x 1/4" BSPP
Technical Information
Outer sheath:
Inner sheath:
Max. Working Pressure:
Min. Burst Pressure:
MIn. Bend Radius:
Connections:
Length:
18
HYGOOD
Male Tee
Pressure Switch
This is used primarily in manifold systems for connecting pilot lines from one slave container to the next.
Technical Information
Material:
Connection:
Brass
1/4" BSPP x 1/4" BSPT
Male Elbow
This elbow can be used on the last slave container when
the pressure switch connection is taken from the manifold or piping networks.
Figure 19 - Male Elbow (Part No. 91101)
Technical Information
Housing:
Pressure Connection:
Switch Point:
Tolerance:
Connection:
Proof Pressure:
Technical Information
Material:
Connection:
Brass
1/4" BSPT x 1/4" BSPP
Die-cast Aluminium
Nickel Plated Brass
4 bar Rising (58 psi)
+/- 0.34 Bar (+/- 5 psi)
1/4" NPT Female
172.4 bar (2500 psi)
DC Switch Rating:
Temperature Range:
1 A 24v DC
-40oC to +71oC
(-40 oF to 160 oF)
Installation Environment: non-corrosive / indoor
19
HYGOOD
Discharge Nozzle
Part
Part
Part
Part
Part
Part
Part
No.
No.
No.
No.
No.
No.
No.
3381/2
3391/2
3401/2
3411/2
3421/2
3431/2
3441/2
Technical Information
Material:
20
HYGOOD
Door Notice
CAUTION!
D o N O T enter unless
extingu ishing system
is lock ed off
FM 2 0 0
FM200
RELEASE
MANUAL
CONTROL
POINT
FM200
CAUTION
ENSURE ALL
PERSONEL ARE
EVACUATED
BEFORE
RELEASING
EXTINGUISHANT
FM200
C A UTIO N !
T his area is protected by
a FM 20 0 fire
extinguishing system
W hen alarm sou nds
FM 2 0 0
HYGOODSouth
LTD W OODLANDS
GULI
DFORDYarmouth
SURREY GU11RN
Denes ROAD
Road,
Great
TEL 01483
NR30
3PJ572222 FAX 01483 302180
Technical Information
Material
Finish
Technical Information
2mm (0.08 in) Craylon
Gloss, scratch resistant
Material
Finish
21
HYGOOD
22
HYGOOD
System Design
There are two main elements of system design. The first
is the risk assessment; determining the type of protection required, considerations such as ventilation, openings and restrictions; equipment location. etc. The second is calculating the quantity of FM-200 required,
including floor and/or ceiling voids, positioning of nozzles, electrical requirements, etc.
A Site Survey / Request form is a useful tool to aidememory for addressing the relevant factors, and can be
used subsequently to substantiate the design criteria.
This can be found in Appendix A. All systems are designed in accordance with the BFPSA Code of Practise
for Gaseous Fire Fighting Systems, the appropriate British Standards, currently BS5306 section 5.1. and NFPA
2001.
Hazard Analysis
The first, and one of the most important, exercises in
planning an FM-200 extinguishing system is the hazard survey. The information derived from the survey
should include risk assessment, environmental conditions, personnel considerations, system operation both
in normal conditions and after a discharge, access and
construction limitations, dimensions, volumes, and any
special requirements.
FM-200 systems are suitable for use in normal commercial and industrial environments. The design concentration for Class A & C fires is 7.17% but differs for
Class B fires. To determine other recommended design
concentrations for Class B flammable liquids, consult
Macron Safety Systems Limited as well as referring to
NFPA 2001, 2000 edition, paragraph 3-4.2 and UL -2166,
first edition, paragraph 61.2(b). However the minimum
design concentration for flammable liquids is 9%. All
design concentration calculations are based on extinguishing concentrations plus an additional 20% safety
factor for Class A & C and 30% safety factor for Class
B, and manually actuated only systems, plus an additional 3% safety factor for nozzle performance (commercial grade Heptane excluded).
All system design calculations are calculated at minimum design concentration to determine agent quantity.
Maximum design concentration should be at the maximum anticipated enclosure temperature, for comparison
see NOAEL / LOAEL values.
Calculations:
Cupburner or fire test concentration X
nozzle efficiency factor X safety factor.
Safety factor:
Class A = 1.2
Class B = 1.3
Class C = Class A
For systems with only manual actuation cupburner x 1.03 x 1.3 = design
concentration but not less than
9.0%
Rugged environments, and those requiring intrinsically safe or flameproof equipment, require special consideration and should be discussed fully with Macron
Safety Systems before finalising a system design. FM200 is suitable for use with the following materials:
Class A
Class B
Class C
23
HYGOOD
Hazard Volume
Note. Certain materials in this group may
require increased concentrations to achieve
satisfactory extinguishment. Consult Macron
for details of specific risk.
Caution. FM-200 is not effective on the following: Class A Deep seated fires.
Class D Combustible metals.
Chemicals capable of auto-thermal recomposition.
Chemicals capable of rapid oxidation.
Enclosures with hot surfaces (>400oC) (752oF)
Hazard Structure
The protected enclosure shall be bounded by rigid elements of building constrution. The ceiling should be
not less than 0.3m (1.ft) above the hazard. The rigid
elements should have a fire resistance of not less than
30 min when tested in accordance with BS476: Part 20,
Part 21, Part 22 or Part 23 as appropriate.
In total flooding applications the risk area must comprise an enclosed space with no significant openings so
that the design concentration can be achieved and maintained. Generally, the calculation is based on an empty
area; the subsequent furniture and fittings having little
effect on the actual concentration. Similarly, large equipment cabinets and control panels should not be considered in the calculation as it is assumed that the internal
area is required to be filled with agent.
Each enclosed space is considered as a risk area and
requires at least one nozzle. A floor void, ceiling void,
cable duct, etc., is treated as a separate adjacent area
and requires simultaneous discharge to occur.
Ceiling obstructions such as beams that are less than
300mm (12") below the slab need not be considered.
Obstructions greater than 300mm (12") can affect the
distribution of agent and may require additional nozzles.
Consult Macron Safety Systems if in doubt. Please note
that floor voids cannot be protected separately from the
associated room.
To determine the volume refer to the site drawings,
ensuring that the scale is accurate and that heights are
denoted, or make a sketch of the area adding dimensions and any relevant details. Calculate the volume of
each area.
24
HYGOOD
Ventilation
Hazard Fuels
If the hazard enclosure has no means of adequate venting after discharge, consideration should be given to
installing a normally closed means of ventilation with
extraction arrangements which will discharge directly to
open air.
All fuels in the hazard must be identified and the corresponding agent concentration requirements. The design
concentration (percent by volume) required for the hazard will be the highest concentration required by any
one of the fuels present in the hazard.
Personnel Safety
Natural Agent: To avoid possible injury, avoid any exposure to FM-200 in volume concentrations greater than
9% unless using self contained breathing apparatus.
Limit exposure times as in NFPA 2001, Section 1-6
"Safety."
Symptoms of overexposure to concentrations greater
than 10.5% may include dizziness, impaired coordination, reduced mental acuity, cardiac effects or unconsciousness. In the event of overexposure, remove to
fresh air immediately and summon medical assistance.
Hazard Temperature
Determine as accurately as possible the anticipated minimum and maximum temperatures likely to be experienced
within the protected area. Minimum agent quantity requirements are based on minimum hazard. At maximum
temperature, hazard concentration must not exceed the
NOAEL/LOAEL values for normally occupied spaces,
reference NFPA 2001, Section 1-6 "Safety."
Once assembled , filled and pressurised the FM-200
extinguishing system should not be exposed to temperatures other than the storage / operating temperature
range of 0 to 500C. (32oF to 120oF). This also includes
while being in storage or transported.
Agent Quantities
Normally the agent quantity is the weight required to
produce the desired concentration at the lowest temperature within the hazard enclosure.
Agent Storage
FM-200 is stored as a liquified compressed gas in
appropriate containers to meet DOT4BW500 & 450 requirements. Nitrogen in the container maintains a
superpressurisation of 25 bar at 21oC (360 psi at 70oF).
The chosen location should provide protection from
severe weather, mechanical, chemical, or other types of
damage. The ambient temperature of the storage area
must be between 0 oC to 49 oC (32 oF to 120 oF), the
optimum temperature being 21oC (70oF).
Hydraulic calculations are made at 21oC (70 oF). When
the storage temperature varies by + 5.5 oC (+ 10 oF) from
21oC (70 oF), there is a risk that the system will not supply the designed quantity of extinguishing agent.
25
HYGOOD
Manifolds
It may be necessary to manifold agent containers to
provide the required amount of agent for a hazard, or to
make available the proper increments of agent weight
for the protection of multiple hazards.
Whenever containers are manifolded, the following rules
must be observed.
1. All containers connected to the same manifold
or pipe must be the same size and filled with the
same agent weight, pressure and fill density.
2. Agent containers must be located in a single
row and spaced according to section.
3. A connected reserve may be employed in some
circumstances providing a secondary supply of
agent.
4. Flexible discharge hoses and check valves must
be used at each inlet.
Agent Distribution
Distribution piping will be installed only with approved
piping as indicated in Section 5.
Pipe size reductions may be made by using reducing
tees or reducing bushings or reducing couplings.
26
HYGOOD
Flow in Pipe
In a properly designed distribution piping network the
flow of FM-200 will consist of a two phase mixture of
liquid and vapour. The properties of this mixture will
vary with its composition; therefore, when the mixture
contacts the pipeline walls, the friction decreases the
density of the mixture resulting in a non-linear pressure
drop and an increase in flow velocity.
Another consequence of two-phase flow is the potential for separation of liquid and vapour. In a properly
designed pipe network, the velocity of the mixture will
be high enough to maintain highly turbulent flow. However, if the pipeline diameter is too large for the design
flow rate, the two phases may separate, leading to alternate discharges of liquid and vapour (slugging) or layering of the two phases. Therefore, the pipeline must be
properly sized to keep the FM-200 flow turbulent
enough to prevent phase separation.
Hydraulic calculations are made at 210C (70oF). Temperatures other than 21oC (70oF) may result in variations in
system discharge characteristics. When the storage temperature varies by + 5.5oC (+ 10oF) there is a risk that the
system will not supply the designed quantity of extinguishing agent.
HYGOOD
Figure 25a -
Figure 25b -
28
HYGOOD
8.7m
(28.6ft)
10.05m
(33ft)
1 x 7 port nozzle
Computer Room:
543.3m3 (19237.1ft3)
4 x 8 port nozzles
Floor Void:
63.36m3 (2275.4ft3)
2 x 8 port nozzles
Nozzle placement and piping arrangements for the example are shown in Figure 28.
29
HYGOOD
NOTE: Incorrect orientation of side and bull tee could result in separation of the FM200 from the Nitrogen (due to FM-200
greater density). The design would also be outside the parameters permitted by the calculation software. See figures 27d and 27f.
30
HYGOOD
W = (V/S)* (C/100-C)
2275.4 X 7.2
= 80.0lbs
2.207
(100-7.2)
When the minimum quantity of FM-200 has been calculated the weight is compared to the available agent
container size. The container size must be equal to or
greater then the weight of agent (see Figure 1).
With the appropriate container selected, the previous
equation can be rearranged to determine the concentration based on the actual weight as containers are filled
to the nearest kg.
Temperature (t).
C=
100 WS
WS + V
Example:
Calculation for two rooms and floor void with the following dimensions:
Switch Room:
Computer Room:
Floor Void:
Switch Room:
4262.6 X 7.2
= 149.9Ibs
2.207
(100-7.2)
19237.1 X 7.2
= 676.3lbs
2.207
(100-7.2)
31
HYGOOD
Switch Room:
After determining the minimum weight and concentration, the maximum concentration can be determined by
recalculating the equation based on the maximum temperature anticipated in each enclosure 270C (800F) maximum design temperature. This calculation is required to
determine if the maximum concentration is below the
NOAEL limit for normally occupied areas.
Switch Room:
The minimum enclosure concentrations can be calculated based on the actual container fill (70oF minimum
design temperature).
Switch Room:
Floor Void:
C = 100 x 80 x 2.2538
(80 x 2.253) + 2275.4
= 7.34%
Floor Void:
C = 100 x 80 x 2.207
= 7.2%
(80 x 2.207) + 2275.4
32
HYGOOD
Piping Practices
Due to the two phase flow of FM-200, certain piping
practices must be adhered to. Mainly that the flow split
must be on the horizontal plane. There are two types of
tee used in FM-200 systems, a through /side tee and a
bull tee. Both have limitations on the minimum and maximum allowable flow splits which are detailed in section
4, page 36.
It should also be noted that system designers shall allow a minimum of 10 times the nominal pipe diameter
around tee splits before any change of direction.
System designers should aim to design as far as possible balanced pipe networks, use minimum lengths of pipe,
use minimum numbers of elbows, maximize pipe volume
before the 1st tee and incorporate similar pipe run lengths
to nozzles.
33
HYGOOD
Introduction
Example:
Hazard Volume:
9182ft3
Room Temperature:
70oF
Agent Concentration:
7.17%
Flooding Factor:
0.0351
1. Hazard Volume.
2. Minimum Room Temperature.
3. Hazard Type.
4. Height above sea-level.
Note: Specific Vapour Volume data shown in
Table 7 are experimentally derived values and
the specific vapour volume equation (S) has
a correlation coefficient of 0.99. However the
equation can be used to give a close approximation of required agent quantities.
Temp.
t
(oF )c
10
20
30
40
50
60
70
80
90
100
110
120
130
140
34
Specific
Vapor
Volume 6
s
(ft3/lb)d
1.9264
1.9736
2.0210
2.0678
2.1146
2.1612
2.2075
2.2538
2.2994
2.3452
2.3912
2.4366
2.4820
2.572
0.0331
0.0323
0.0316
0.0309
0.0302
0.0295
0.0289
0.0283
0.0278
0.0272
0.0267
0.0262
0.0257
0.0253
14
15
0.0391
0.0381
0.0372
0.0364
0.0356
0.0348
0.0341
0.0334
0.0327
0.0321
0.0315
0.0309
0.0303
0.0298
0.0401
0.0391
0.0382
0.0373
0.0365
0.0357
0.0349
0.0342
0.0335
0.0329
0.0323
0.0316
0.0311
0.0306
0.0845
0.0825
0.0805
0.0787
0.0770
0.0753
0.0737
0.0722
0.0708
0.0694
0.0681
0.0668
0.0656
0.0644
0.0916
0.0894
0.0873
0.0853
0.0835
0.0817
0.0799
0.0783
0.0767
0.0752
0.0738
0.0724
0.0711
0.0698
0.0451
0.0441
0.0430
0.0421
0.0411
0.0402
0.0394
0.0386
0.0378
0.0371
0.0364
0.0357
0.0350
0.0344
0.0513
0.0501
0.0489
0.0478
0.0468
0.0458
0.0448
0.0439
0.0430
0.0422
0.0414
0.0406
0.0398
0.0391
0.057
0.0563
0.0550
0.0537
0.0525
0.0514
0.0503
0.0493
0.0483
0.0474
0.0465
0.0456
0.0448
0.0440
0.0642
0.0626
0.0612
0.0598
0.0584
0.0572
0.056
0.0548
0.0538
0.0527
0.0517
0.0507
0.0498
0.0489
0.0708
0.0691
0.0675
0.0659
0.0645
0.0631
0.0618
0.0605
0.0593
0.0581
0.0570
0.0560
0.0549
0.0540
0.0776
0.0757
0.0739
0.0723
0.0707
0.0691
0.0677
0.0663
0.0650
0.0637
0.0625
0.0613
0.0602
0.0591
HYGOOD
t
(oC )c
Specific
Vapor
Volume
s
(m3/kg)d
-10
-5
0
5
10
15
20
25
30
35
40
45
50
55
0.1215
0.1241
0.1268
0.1294
0.132
0.1347
0.1373
0.1399
0.1425
0.145
0.1476
0.1502
0.157
0.1553
7.17
10
11
12
13
14
15
0.5254
0.5142
0.5034
0.4932
0.4834
0.474
0.465
0.4564
0.4481
0.4401
0.4324
0.425
0.418
0.4111
0.6196
0.6064
0.5936
0.5816
0.57
0.5589
0.5483
0.5382
0.5284
0.519
0.5099
0.5012
0.4929
0.4847
0.6357
0.6223
0.6091
0.5968
0.5851
0.5734
0.5625
0.5520
0.5420
0.5326
0.5232
0.5142
0.4919
0.4973
0.7158
0.7005
0.6858
0.6719
0.6585
0.6457
0.6335
0.6217
0.6104
0.5996
0.5891
0.579
0.5694
0.56
0.8142
0.7987
0.78
0.7642
0.749
0.7344
0.7205
0.7071
0.6943
0.6819
0.6701
0.6586
0.6476
0.6369
0.9147
0.8951
0.8763
0.8586
0.8414
0.8251
0.8094
0.7944
0.78
0.7661
0.7528
0.7399
0.7276
0.7156
1.0174
0.9957
0.9748
0.955
0.936
0.9178
0.9004
0.8837
0.8676
0.8522
0.8374
0.823
0.8093
0.796
1.1225
1.0985
1.0755
1.0537
1.0327
1.0126
0.9934
0.975
0.9573
0.9402
0.9230
0.0908
0.8929
0.8782
1.2301
1.2038
1.1785
1.1546
1.1316
1.1096
1.0886
1.0684
1.049
1.0303
1.0124
0.995
0.9784
0.9623
1.3401
1.3114
1.2839
1.2579
1.2328
1.2089
1.1859
1.164
1.1428
1.1224
1.1029
1.084
1.066
1.0484
1.4527
1.4216
1.3918
1.3636
1.2264
1.3105
1.2856
1.2618
1.2388
1.2168
1.1956
1.1751
1.1555
1.1365
C o rrectio n
F a cto r
-3 0 0 0 (-0 .9 2 km )
-2 0 0 0 (-0 .6 1 km )
-1 0 0 0 (-0 .3 0 km )
0 (0 .0 0 km )
1 0 0 0 (0 .3 0 km )
2 0 0 0 (0 .6 1 km )
3 0 0 0 (0 .9 1 km )
4 0 0 0 (1 .2 2 km )
5 0 0 0 (1 .5 2 km )
6 0 0 0 (1 .8 3 km )
7 0 0 0 (2 .1 3 km )
8 0 0 0 (2 .4 5 km )
9 0 0 0 (2 .7 4 km )
1 0 0 0 0 (3 .0 5 km )
1 .1 1
1 .0 7
1 .0 4
1 .0 0
0 .9 6
0 .9 3
0 .8 9
0 .8 6
0 .8 2
0 .7 8
0 .7 5
0 .7 2
0 .6 9
0 .6 6
sure that vary more than 11 percent (equivalent to approximately 915m (3000 ft) of elevation change) from standard
sea level pressure 760 mm Hg at 0 oC (29.92 in Hg at 70 oF).
W = (V/S) * (C/100-C)
At elevations above sea-level, FM-200 has a greater specific volume because of the reduced atmospheric pressure. A system designed for sea-level conditions will therefore develop an actual higher concentration at levels above
sea-level and an actual lower concentration at levels below sea-level. The adjusted agent quantity is calculated
by multiplying W (from the equation on the left) by the
altitude correction factor. The design quantity of the clean
agent shall be adjusted to compensate for ambient presFM-200 Installation Guide/11100/01.07.01/Issue3.0:
HYGOOD
Engineered Systems
Macron Safety Systems Engineered systems are based
on a Hydraulic Flow Program developed by Hughes Associates Inc. The program predicts the two phase flow of
FM-200 and nitrogen through a pipe network. Information detailing the enclosure is entered and the program
calculates the required pipe sizes, nozzle drill sizes, average nozzle pressures and discharge time. For further information on the Flow Program, refer to the Hughes Hy-Flow
User's Manual.
As system design calculations are critical to the success of the extinguishing system, only Macron Safety
Systems or Macron Safety Systems trained personnel are
permitted to perform system calculations. If in the future,
companies other than Macron Safety Systems wish to use
the program, representatives will be required to attend a
formal training session. All system calculations are conducted either 'in house' by Macron Safety Systems or authorised suppliers.
NOTE: The calculation method has been designed for specific types of fittings, pipes, and
pipe inside diameter. When these limitations
are not maintained, there is a risk that the system will not supply the required quantity of extinguishing agent.
Program Parameters
When designing pipe network systems, the following
design parameters should be considered to avoid system
reject when running the calculation.
36
The ratio between the nozzle area and the pipe cross
sectional area immediately preceding the nozzle is
limited to a minimum of 0.20 (20%) and a maximum
of 0.80 (80%).
(For extended discharge consult Macron Safety Systems Ltd.)
Minimum flow
rate kg/s (lb/s)
Maximum flow
rate
kg/sec.(lb/s)
10 (3/8)
15( )
20 ()
25 (1)
32 (1 )
40 (1 )
50 (2)
65 (2 )
80 (3)
100 (4)
125 (5)
150 (6)
0.272 (0.60)
0.454 (1.00)
0.907 (2.00)
1.588 (3.50)
2.722 (6.00)
4.082 (9.00)
6.35 (14.00)
9.072 (20.00)
13.61 (30.00)
24.95 (55.00)
40.82 (90.00)
54.43 (120.00)
0.907 (2.00)
1.361 (3.00)
2.495 (5.50)
3.855 (8.50)
5.67 (12.50)
9.072 (20.00)
13.61 (30.00)
24.95 (55.00)
44.92 (99.00)
56.7 (125.00)
90.72 (200.00)
136.1 (300.00)
HYGOOD
90 E lbow m
(ft)
45 E lbow m
(ft)
T hru T ee m
(ft)
Side T ee m
(ft)
10 (3/8)
15 (1/2)
20 (3/4)
25 (1)
32 (1 )
40 (1 )
50 (2)
65 (2 )
80 (3)
100 (4)
125 (5)
150 (6)
0.4 (1.2)
0.52 (1.6)
0.67 (2.0)
0.85 (2.6)
1.13 (3.4)
1.31 (4.0)
1.68 (5.1)
2.01 (6.1)
2.5 (7.6)
3.26 (10.0)
4.08 (12.4)
4.94 (15.0)
0.18 (0.5)
0.24 (0.7)
0.3 (0.9)
0.4 (1.2)
0.52 (1.6)
0.61 (1.7)
0.79 (2.4)
0.94 (1.5)
1.16 (3.5)
1.52 (4.6)
1.92 (5.9)
2.32 (7.1)
0.24 (0.7)
0.3 (0.9)
0.42 (1.3)
0.55 (1.7)
0.7 (2.1)
0.82 (2.5)
1.06 (3.2)
1.25 (3.8)
1.55 (4.7)
2.01 (6.1)
2.56(7.8)
3.08 (9.4)
0.82 (2.5)
1.04 (3.2)
1.37 (4.2)
1.74 (5.3)
2.29 (7.0)
2.65 (8.0)
3.41 (10.4)
4.08 (12.4)
5.06 (15.4)
6.64 (20.2)
8.35 (25.5)
10 (30.5)
U nion m
(ft)
0.09
0.12
0.15
0.18
0.24
0.27
0.37
0.43
0.55
0.73
0.91
1.07
(0.3)
(0.4)
(0.5)
(0.6)
(0.7)
(0.8)
(1.1)
(1.3)
(1.7)
(2.2)
(2.8)
(3.3)
Nominal
pipe size
Equivalent
length M (ft)
25 mm (1 in.)
50 mm (2 in.)
See note 1
50 mm (2 in.)
25 mm (1 in.)
32 mm (1.25 in.)
50 mm (2 in.)
6.096 (20)
10.668 (35)
See note 1
5.37 (17.6)
7.593 (24.91)
15.285 (50.15)
12.02 (39.429)
37
HYGOOD
SECTION 5 - INSTALLATION
General Information
All installation shall be carried out by an approved Macron Safety Systems contractor with the correct equipment and previous experience of gaseous extinguishing
systems. Macron Safety Systems can supply this service or provide a list of their factory trained installation
contractors. Installation instructions are described under the following main headings, and in the order of
installation.
Container Installation
Piping and Nozzles
Actuation Controls
Ancillary Equipment
Completion Procedures
Container Installation
The container location is identified on the system drawings and should be protected from extremes of temperature, and be accessible for service and maintenance. The
containers must be firmly secured to a wall or bulkhead.
No Safety Outlet and Actuation Caps should be removed
at this stage.
Figure 29 - Safety Outlet and Actuation Caps
50mm(2") Safety Outlet Cap
25mm(1") Actuation Cap
25mm(1") Safety Outlet Cap
Enclosure Volumes.
Agent Quantities.
Actuation Cap
38
HYGOOD
SECTION 5 - INSTALLATION
2.
3.
4.
5.
No. of
Unirax
Channels
130
(5)
60, 330
(2.5, 13)
160, 595
(6.25, 23.5)
110, 343
(4.25, 13.5)
300, 750
(11.75, 29.5)
300, 1000
(11.75, 39.25)
300, 1200
(11.75, 47.25)
39
HYGOOD
SECTION 5 - INSTALLATION
A typical 80mm (3"), three port manifold assembly consists of the manifold, three check valves and an end
cap. Each check valve is bolted to a flanged inlet on the
manifold (50mm (2") only) using four M8 x 20mm cap
head screws.
3.
4.
5.
40
HYGOOD
SECTION 5 - INSTALLATION
V a lv e
S iz e (m m )
M a n ifo ld
S iz e (m m )
N o m in a l H e ig h t fr o m F lo o r
to to p o f c a n tile v e r (m m )
8
4 .5 to 8 .0 k g
(1 0 to 1 8 lb )
16
9 .0 to 1 7 .5 k g
(2 0 to 3 9 lb )
32
1 7 .0 to 3 3 .5 k g
(3 8 to 7 4 lb )
25
(1 )
6 5 (2 .5 )
750
(2 9 in .)
25
65
(2 .5 )
949
(3 7 3 /8 in .)
25
65
(2 .5 )
1289
(5 0 in .)
52
2 7 .0 to 5 3 .0 k g
(5 9 to 1 1 7 lb )
106
5 3 .5 to 1 0 6 .5 k g
(1 1 8 to 2 3 5 lb )
106
50
(2 )
80
(3 )
1133
(4 4 5 /8 in .)
50
80
(3 )
1601
(6 3 .0 )
50
147
7 4 .0 to 1 4 7 .5 k g
(1 6 3 to 3 2 5 lb )
147
50
100
(4 )
80
(3 )
1601
(6 3 in )
1931
(7 6 in .)
50
147
50
180
9 1 .5 to 1 8 2 .0 k g
(2 0 1 to 4 0 1 lb .)
180
50
100
(4 )
150
(6 )
100
(4 )
1931
(7 6 in .)
1931
(6 7 in .)
1931
(7 6 in .)
150
(6 )
2210
(8 7 in )
50
41
HYGOOD
SECTION 5 - INSTALLATION
Pipe Installation
Fitting Description
Pipe Size
In general, the installation should commence at the union elbow / manifold assembly and progress along to
the discharge nozzles. Install the Pipework to the installation drawings provided, ensuring that the following is
adhered to:
up to &
including
20mm
above 20mm
up to &
including
80mm
above 80mm
Publication
Type of Pipe1)
Grade of Steel
Minimum Wall
Thickness2)
BS1387
BS3601
BS3602 : Pt 1
ASTM A106-77
BS3601
BW
S
HFS or CFS
HF or CD
S
430
360 or 430
A or B
430
Heavy
BS3602 : Pt 1
ASTM A106-77
BS3601
BS3602 : Pt 1
HFS or CFS
HF OR CD
S
HFS or CFS
360 or 430
A or B
430
360 or 430
ASTM A106-77
HF or CD
A or B
Schedule 40
(Schedule 80
for screwed
joints)
Schedule 80
Schedule 40
(Schedule 80
for screwed
joints)
1) Abbreviations:
BW butt welded / CD cold drawn / HFS hot finished seamless / CFS cold finished
seamless / S seamless
2) Where schedule numbers are given, these determine the minimum wall thickness in
accordance with BS1600. Where the specified pipe is not obtainable in these dimensions,
the next larger thickness should be used.
42
HYGOOD
SECTION 5 - INSTALLATION
Connection
Pipe Type
Threaded
Threaded
Threaded
Threaded
Threaded
Threaded
Welded
Welded
Welded
Welded
Welded
Welded
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Schedule 40
Nominal Pipe
Size
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
3/8 - 6 NPS
Pipe Size
Up to or < 3 NPS
> 3 NPS
All
Note: Cautionary information indicating the calculation method has been investigated for specific types of
fittings, type of pipe and pipe inside diameter. Also that
when the specified limitations are not maintained there
is the risk that the system will not supply the required
quantity of extinguishing agent. The Flow Program contains pipe & fittings options together with Equivalent
Length information for UK / US pipe & fittings.
Pipe Hangers
Pipe hangers must be spaced according to the size of
pipe (see table 17).
Maximum Spacing
m
10 (3/8)
15 (1/2)
20 (3/4)
25 (1)
32 (1 )
40 (1 )
50 (2)
65 (2 )
80 (3)
100 (4)
150 (6)
1. (3 ft)
1.5 (5 ft)
1.8 (6 ft)
2.1 (7 ft)
2.4 (8 ft)
2.7 (9 ft)
3.4 (11 ft)
3.5 (11.5 ft)
3.7 (12 ft)
4.3 (14 ft)
5.2 (17 ft)
43
HYGOOD
Figure 32 - Nozzle Fixing
SECTION 5 - INSTALLATION
Min. Section
Clearance
(m)
2.59 (8.5ft)
2.74 (9ft)
2.89 (9.5ft)
3.05 (10ft)
3.20 (10.5ft)
3.35 (11ft)
3.50 (11.5ft)
3.81 (12.5ft)
4.27 (14.0ft)
4.57 (15ft)
Min. Ground
Clearance
(m)
2.44 (8ft)
2.44 (8ft)
2.44 (8ft)
2.44 (8ft)
2.44 (8ft)
2.44 (8ft)
Nozzles
All nozzles require the installation of a dirt trap comprising 1 side tee, 2 nipples, and 1 pipe cap. Fit the nozzle to
the nipple on the dirt trap and check the nozzle orifice to
ensure proper orientation. Dirt trap lengths should be
no more than 10 times nominal pipe diameter.
44
SECTION 5 - INSTALLATION
Actuation Installation
HYGOOD
Figure 36 - Side Mounted Electrical Actuator
Location (No Solenoid Adaptor Fitted)
The method of actuation depends on the system configuration and any specific contract requirements and
can be broken down as follows:
45
HYGOOD
SECTION 5 - INSTALLATION
The electrical signal from the detection and/or control equipment is connected in accordance with the wiring diagram detailed in Figure 40 when all other installations have been completed.
Figure 40 - Electrical Actuator Wiring Diagram
4.5-5.0 mm
(.177-.197 in)
WITH NUT
AGAINST
BODY
SOLENOID
CAN BE
LOCATED
ANY 9Oo
ANGLE
The Solenoid Actuator is fitted with a suppression diode in parallel to the coil as indicated. Connect +ve from
control panel to terminal 1 and -ve from control panel to
terminal 2, on plug connector. End of line monitoring
device (if required) to be fitted on site.
46
HYGOOD
SECTION 5 - INSTALLATION
Manual Actuator
Caution. Before attaching the strike knob to the electrical actuator or valve, ensure that the firing pin is retracted and the safety pin is in place (see Figure 41). The
strike knob must be hand-tight only.
Figure 41 - Manual Actuator Non-Fire Position
Pneumatic Actuator
Check that the actuating plungers are in the raised position (see Figure 43). Remove the actuation cap from the
top of the valve assembly (see Figure 29) and carefully
screw the pneumatic actuator to the valve on each slave
container.
Note. The actuator must be hand-tight only.
Figure 43 - Pneumatic Actuator Non-Fire Position
6.4mm (1/4")
MINIMUM
6.4mm (1/4")
MINIMUM
47
HYGOOD
SECTION 5 - INSTALLATION
48
Install the pilot line tee, Part No. 91109 on to all pneumatic actuators (wrench tight). Connect one end of the
pilot hose Part No. 6490 to the adaptor on the master
container and one end to the pilot line tee on the pneumatic actuator. Connect pilot hoses between pilot line tees
on all pneumatic actuators (see Figure 45). The maximum
number of slave actuated containers is 9 (10 containers
system in total).
SECTION 5 - INSTALLATION
HYGOOD
Ancillary Equipment
Discharge Pressure Switch
49
HYGOOD
Discharge Pressure Switch continued...
To wire the discharge pressure switch to the control
panel, unscrew and remove the switch cover plate. Connect to the appropriate terminals on the microswitch or if
supplied with wires, to the coloured wires which are labelled as follows:Common (C) (violet)
SECTION 5 - INSTALLATION
NOTE: When the device (i.e. pressure switch) is connected to a standard supervisory input circuit, there will
be no distinction between a wiring fault and device actuation . This device is to only be utilised when accepted
by the authority having jurisdiction.
Accessories
Door Notices
Completion Procedures
For ease of reference completion procedures may be
subdivided into the following sections;
Final Connections.
CAUTION:
50
HYGOOD
SECTION 5 - INSTALLATION
General
When the installation is complete, and before making
the final connections, the following checks should be
made:
Mechanical Checks
Inspect protected area closely for conformance to original risk specifications and for enclosable openings or
sources of agent loss which may have been overlooked
in the original specification.
Pneumatic Checks
Final Connections
Discharge Piping
Electrical Checks
The electrical systems may include interfaces with many
other systems for alarm, indication, actuation, shutdown,
etc. For complex electrical systems the scope and operating requirements will be described in other documents.
Electrical checks are given below for a basic system using electrical actuation of the container valve;
51
HYGOOD
SECTION 5 - INSTALLATION
Hand-over Procedures
The entire system shall be thoroughly inspected to make
sure that it is complete and that all tests required during
installation have been properly carried out. In addition,
the following items are particularly important.
1.
2.
3.
52
HYGOOD
Introduction
The hazard integrity is the ability to retain the discharged
FM-200. For a total flooding extinguishing system to
be effective, the design concentration must be achieved
and then maintained for at least ten minutes. The only
method of testing the agent retention within the protected area is to verify the integrity of the enclosure by
applying proven test procedures.
The enclosure integrity test has been developed to
locate the source of leaks and, from the data collected,
predict the retention time, proving system performance
and removing the need for actual FM-200 discharge.
In order to determine with any degree of confidence that
the hazard area will hold the gas for the required time
period, where necessary an Enclosure Integrity Test in
accordance with BS5306:Part 5: Section 5:1 / NFPA 2001
appendix B. must be conducted.
Principle
The test is conducted with a device known as a door
fan, which has been used in the energy conservation
field for over 25 years. It has three basic components as
follows:
53
HYGOOD
Integrity Test Procedure
Evaluation. The enclosure and immediate surrounding
area is initially examined visually to assess the readiness for testing, the existence of any attached spaces
that could affect the results, and that there is an adequate relief area and return air path. The volume of the
enclosure is confirmed and the highest equipment measured to ascertain the required level for retention time.
Enclosure Evaluation
Static Pressure Measurements. With the door fan equipment fully installed and set up, but with all openings
closed, a measurement of any pressure difference between the enclosure and the relief area is made. If the
measurement is unduly high its causes are ascertained
and if possible permanently reduced or eliminated.
Total Enclosure Leakage Method. Using an adequate
range on one fan, or a number of fans, a pressure difference of between column pressure and column pressure
plus 30% is created. The pressure difference, and the air
flow required to generate this, is then recorded. This is
carried out for both pressurisation and depressurisation
modes. The total equivalent leakage area and the predicted retention time is calculated.
Suspended Ceiling Leakage Neutralisation Method.
This procedure is used to improve the accuracy of the
predicted retention time where a reasonable air-tight ceiling exists, whether or not the ceiling is protected with
FM-200.
Note. Leak paths through the ceiling may be temporarily
sealed.
The volumes above and below the false ceiling are
depressurised to the same extent but using separate fans.
This is confirmed by using cool chemical smoke to check
that no air is flowing through the false ceiling.
Readings of the pressure difference between the enclosure, relief area, and the air flow through the fan(s)
used to depressurise the room and false ceiling are made,
and then the procedure is repeated in the pressurisation
mode. The below ceiling leakage area is then calculated
and used in conjunction with the ELA to predict a revised retention time.
HYGOOD
Calculation
Leakage Location
A portable computer is used to collate the data and calculate the values. The associated printer provides a detailed hard copy of the data on site.
Location:
Hygood. Test Enclosure
Room Name:
Test House
Testing Company:
HYGOOD LIMITED
Technician:
C Uzzell
Date:
12.12.96
Whole Room Test.
All Outputs are in METRIC Units.
Location:
R oom Nam e:
Tem p erature IN : 20
Static Pressure @ Fan Test:
DEPR ES SUR E
FM200
17.00
30.00
3.20
2.90
10.00
7.22
0.00
0.0050
0.0025
0.0025
RM=
AT=
C 3=
GD=
AR =
PA=
C F=
EL=
1.639
0.003
3.019
7.260
9.374
13.7
1.000
0.000
PC =
ALLC 4=
K1T=
FA=
K2=
TD=
OUT
14.0
-14.0
0.1
45.0
31.0
13.4
13.4
0.0046
0.0050
20
PR ESS UR E
OUT
14.0
14.0
0.1
45.0
45.0
16.2
16.2
0.0055
13.7
0.002
0.000
1.8850
605.679
0.500
0.0046
20.000
X
Software Conforms to 1992 NFPA 12A/2001 TCD Room Integrity Procedure.
Maximum Allowable ELA (m2):
Interface Height @ 10 minutes:
0.005
2.903
55
HYGOOD
General Comments
Personnel required to work in the protected area should
be conversant with the detection and extinguishing
equipment installed, and trained in fire procedures. All
life-saving equipment must be properly maintained.
The method of system operation is chosen at the
design stage to suit the protection required for the hazard area and the environmental factors appropriate to
that area. This part of the document provides information relevant to ALL the standard operational systems
to cover the eventuality of changes to, or expansion of
the original design.
Manual.
Fully Automatic.
Automatic with Manual Intervention.
Detectors shall be UL Listed for the intended application. Control Panels shall be UL Listed for releasing device service and compatible with detection and MACRON SAFETY SYSTEMS FM-200 Engineered Total
Flooding Fire Extinguishing System.
Manual System
Manual systems depend on human detection of a fire in
the hazard area and prompt action to actuate the local or
remote strike knob for the FM-200 system to discharge
and flood the protected area and extinguish the fire.
All other instructions associated with manual operation form part of the users procedures on safety
precautions and fire drill. If required MACRON SAFETY
SYSTEMS can assist the user to prepare the procedures
for safety and fire precautions.
56
HYGOOD
FM-200 Decomposition
FM-200 decomposes when exposed to temperatures
exceeding 482oC (900oF); such as flames, hot metal
surfaces, etc. The rate of this decomposition is dependent upon the size of the area where extreme temperatures
are found, and also upon the length of FM-200 exposure
time.
To avoid decomposition, MACRON SAFETY SYSTEMS are designed to discharge and extinguish the fire
quickly. The average duration of discharge for these
systems at 21oC (70oF) is less than 10 seconds, so the
minimum amount of decomposition occurs. Hydrogen
Fluoride is the most toxic decomposition product. This
material generates a sharp acrid odour, which is easily
detected and acts as a warning and a good safeguard to
personnel.
FM-200 has low boiling point, consequently the discharge is very cold at the point where it leaves the nozzle. Care should be taken to avoid working within 1 metre (3.ft) of FM-200 discharge nozzles.
The velocity of discharge of FM-200 from a discharge nozzle is very high, care should be taken to insure that objects which may become dangerous projectiles are secured or removed from the hazard area.
FM-200 Concentration
FM-200 total flooding systems greater than 9% design
concentration should only be used with manual actuation in normally occupied areas. A normally occupied
area is defined as an area intended for occupancy.
Any area protected by FM-200 should be evacuated prior to start of system discharge. Where egress of
normally occupied areas cannot be accomplished within
one minute, FM-200 total flooding systems shall be
designed not to exceed 9.0% concentration.
Refer to NFPA 2001, Paragraph 1-6.1.2.1 for additional
information.
57
HYGOOD
Should it be necessary to enter a space containing FM200 or decomposition products the following precautions should be taken;
Do Not enter space unless you are under observation from outside the space, or tethered by a lifeline.
58
SECTION 8 - MAINTENANCE
HYGOOD
Introduction
Weekly Check of Containers
This section provides user inspection and maintenance
guidance for FM-200 Engineered Systems. A log book
will be provided to record all inspections, maintenance,
measurements and actions taken. The continued capability for effective performance of an FM-200 Total
Flooding Fire Suppression System depends on fully
adequate maintenance procedures, with periodic testing. Reference NFPA 2001 section 4-1 to 4-6.
Inspect the hazard area, access routes, container storage area, floor voids and areas above suspended ceilings to ensure housekeeping is good and that no refuse
has accumulated. Ensure that access to the system container assemblies and local remote controls is unobstructed.
Contents of area.
Inspect system and protected spaces to ensure that warning signs, safety precautions and operating instructions
are posted and clearly visible.
Use of area.
Air Handling equipment in area.
Openings in area.
Floor/ceiling voids.
Partitioning.
59
HYGOOD
SECTION 8 - MAINTENANCE
60
HYGOOD
SECTION 8 - MAINTENANCE
Personnel Training
Check all manual and pneumatic actuators for free movement of the piston. Replace whole unit where appropriate. Check all control valves for correct manual function
and automatic valves additionally, for correct automatic
function.
All persons who may be expected to inspect , test, maintain or operate the fire extinguishing system shall be
kept adequately trained in the functions they are expected to perform.
Personnel working in an enclosure protected by a gaseous extinguishant shall receive training in the operation,
use of the system and safety issues.
a.
c.
61
HYGOOD
i) Remove solenoid actuators from valve
assembles.
ii) Activate the detection system in accordance
with procedures provided with the system.
When this test is performed, the release circuit
of the detection system must operate the
electric actuators causing the plungers to be
firmly extended.
SECTION 8 - MAINTENANCE
Finally
Carry out a final visual inspection of the system and the
protected area to ensure that all equipment has been
reinstalled and reconnected properly. Ensure that any
associated control/indication panel is displaying normal operation. Complete the site log book, recording
work carried out and parts used. Inform the responsible
person that the work is complete and that the system is
back on-line.
d.
e.
62
HYGOOD
Recharging
This section describes the procedures to enable the
refilling of a container that has been discharged and will
require recharging. This covers both 25mm(1") and
50mm(2") container valve assemblies.
Valve Refurb
Figure 50
50mm (2") Valve exploded View.
Testing
On completion of a valve refurb the valve assy is
subjected to two tests - Valve Assy Pre-dome and Leak
Test. (test required if burst disc was replaced)
The tests are conducted on a Nitrogen rig using a
outlet filling adapter cap, test bottom cap and closing
down adaptor. (See figure 51)
63
HYGOOD
1. The valve assy is assembled to the nitrogen rig
bottom cap using PTFE/silicon greased O ring on the
valve neck thread. The outlet adapter cap is also fitted,
ensuring that the vent tap is closed.
2. The nitrogen regulator is opened to 40 bar (580psi)
and the pressure to the valve is slowly increased to this
pressure, this is to pre-dome the burst disc. This pressure is held for 1 minute ensuring that there is no drop in
pressure indicated by nitrogen rig gauge.
3. A Water /soap solution is poured into the top cap
schrader and leak detection spray is applied to all ports
on the valve to check for leakage. If no leaks are present
the pressure to the valve must be reduced to 25 bar
(362.5psi) and the closing down adapter fitted. To close
the valve shuttle down, 40 bar (580psi) is applied through
the closing down adapter.
4. Once again check for leaks.
5. Slowly release the gas from the test rig, vent from
closing down adapter and ensure that the outlet cap
adapter tap is opened before attempting to remove the
adapter.
If a leak is identified it should be rectified, if the leak
persists the valve assembly should be rejected.
FILLING
1. With the Container ready for filling a check is
made to the filling instruction sheet and the container
fill weight, time, date and fill details record.
2. The container is placed on a scales and the
appropriate filling adapter attached to the container valve
discharge port.
Figure 51
3. Attach the fill hose / vent line from the filling rig
outlet to filling adapter.
64
HYGOOD
13. Remove the closing down line adapter.
14. If valve does not close after 5 applications, the
cylinder must be de-pressurised. Refer to section on
"Decanting Containers through rig." Ensure vent valve
is closed when not required to prevent contamination
on fill line.
15. Test all ports with leak detection spray, and
Schrader with water/soap solution.
If a leaks is observed, minor leaks may be cured by
tightening the offending components.
16. Remove fill hose and filling adapter, leak test the
outlet and attach safety cap. Note : When leak testing
outlet with spray, do not look directly into port, examine
quickly from an angle.)
17. Reset scales and note down gross weight.
18. Make certain all safety caps are in place, schrader
protection cap Part No' 91185.
19. Attach label to container stating the following
information. Job number, Customer, Project, Container
size, Fill weight, Gross weight, Date filled, Type of agent.
20. Place container in bonded area for leak monitoring for at least 24 hours prior to dispatch.
21. After 24 hours a Leak Test on the container is
conducted - see section on Container / valve assy leakage test.
22. Insert fill information on to container label.
8 Ltr Container:
65
HYGOOD
Container Size
8ltr
16ltr
32ltr
52ltr
106ltr
147ltr
180ltr
Fill Tolerance
+0.04, -0 kg
+0.08, -0 kg
+0.16, -0 kg
+0.26, -0 kg
+0.50, -0 kg
+0.75, -0 kg
+1.00, -0 kg
Charging Pressure
(+0.09, -0 lb)
(+0.18, -0 lb)
(+0.35, -0 lb)
(+0.57, -0 lb)
(+1.10, -0 lb)
(+1.65, -0 lb)
(+2.21, -0 lb)
+0.75, -0 bar
+0.75, -0 bar
+0.75, -0 bar
+0.75, -0 bar
+0.75, -0 bar
+0.75, -0 bar
+0.75, -0 bar
(+11, -0 psi)
(+11, -0 psi)
(+11, -0 psi)
(+11, -0 psi)
(+11, -0 psi)
(+11, -0 psi)
(+11, -0 psi)
19.9 (288.1)
20.0 (289.9)
20.1 (291.7)
20.2 (293.6)
20.4 (295.4)
20.5 (297.2)
20.6 (299.0)
20.8 (300.9)
20.9 (302.7)
21.0 (304.6)
21.1 (306.4)
21.3 (308.3)
21.4 (310.2)
21.5 (312.1)
21.6 (313.9)
21.8 (315.8)
21.9 (317.7)
22.0 (319.5)
22.2 (321.4)
22.3 (323.3
22.4 (325.2)
22.6 (327.1
22.7 (329.0)
12.8
13.3
13.9
14.4
15.0
15.6
16.1
16.7
17.2
17.8
18.3
18.9
19.4
20.0
20.6
21.1
21.7
22.2
22.8
23.3
23.9
24.4
25.0
(55)
(56)
(57)
(58)
(59)
(60)
(61)
(62)
(63)
(64)
(65)
(66)
(67)
(68)
(69)
(70)
(71)
(72)
(73)
(74)
(75)
(76)
(77)
22.8
22.9
23.1
23.2
23.4
23.5
23.6
23.8
23.9
24.0
24.2
24.3
24.4
24.6
24.7
24.8
25.0
25.1
25.3
25.4
25.6
25.7
25.8
(331.0)
(332.9)
(334.8)
(336.7)
(338.6)
(340.5)
(342.5)
(344.4)
(346.4)
(348.4)
(350.4)
(352.3)
(354.3)
(356.3)
(358.2)
(360.2)
(362.3)
(364.3)
(366.4)
(368.4)
(370.5)
(372.6)
(374.6)
25.6 (78)
26.1 (79)
26.7 (80)
27.2 (81)
27.8 (82)
28.3 (83)
28.9 (84)
29.4 (85)
30.0 (86)
30.6 (87)
31.1 (88)
31.7 (89)
32.2 (90)
32.8 (91)
33.3 (92)
33.9 (93)
34.4 (94)
35.0 (95)
35.6 (96)
36.1 (97)
36.7 (98)
37.2 (99)
37.8 (100)
26.0
26.1
26.3
26.4
26.6
26.7
26.9
27.0
27.2
27.3
27.4
27.6
27.7
27.9
28.1
28.2
28.4
28.5
28.7
28.8
92.0
29.2
29.3
(376.7)
(378.7)
(380.8)
(383.0)
(385.1)
(387.3)
(389.4)
(391.6)
(393.7)
(395.9)
(398.0)
(400.2)
(402.3)
(404.6)
(406.9)
(409.1)
(411.4)
(413.7)
(416.0)
(418.3)
(420.5)
(422.8)
(425.1)
38.3
38.9
39.4
40.0
40.6
41.1
41.7
42.4
42.8
43.3
43.9
44.4
45.0
45.6
46.1
46.7
47.2
47.8
48.3
48.9
(101)
(102)
(103)
(104)
(105)
(106)
(107)
(108)
(109)
(110)
(111)
(112)
(113)
(114)
(115)
(116)
(117)
(118)
(119)
(120)
29.5
29.6
29.8
30.0
30.1
30.3
30.5
30.6
30.8
31.0
31.1
31.3
31.5
31.7
31.9
32.0
32.2
32.4
32.6
32.7
(427.5)
(429.9)
(432.3)
(434.7)
(437.1)
(439.5)
(441.9)
(444.3)
(446.7)
(449.1)
(451.6)
(454.2)
(456.7
(459.3)
(461.9)
(464.5)
(467.0)
(469.6
(472.2)
(474.8)
66
HYGOOD
If the valve has been shut down, ensure that the line
is shut off and activate the valve. Open the ball valve on
the line that is direct to the storage vessel and flush the
FM200 back into it. Shut off line and vent remaining
pressure to atmosphere.
Label up cylinder with appropriate instructions i.e.
Refit or rejection.
67
HYGOOD
Transportation
Containers that have passed all required tests and
have been filled or recharged must be stored, transported and installed in the vertical position. A warning
label will be placed on a container to indicate this requirement. See figure 52.
This only applies to 8 - 52 Ltr containers only.
Figure 52.
Transportation Warning Label.
68
HYGOOD
Warranty
Following the commissioning of the system, all equipment will be covered by the company's twelve month
parts warranty (excluding parts accidentally or maliciously damaged by others). For further information, refer to MACRON SAFETY SYSTEMS 'Terms and conditions' document.
69
HYGOOD
70
SECTION 11 - APPENDICES