Professional Documents
Culture Documents
Background:
Two grid disturbances occurred on two consecutive days on 30th and 31st
July 2012. In the first disturbance at 0233 hours on 30th July 2012, nearly the
entire Northern Grid was affected while in the second disturbance, the Northern,
Eastern and North Eastern grids were affected to a large extent.
In both the disturbances, in the antecedent grid conditions there was
heavy power flow on the 400 kV Bina-Gwalior-Agra single circuit section crossing
1000 MW on the single circuit available. (The second circuit was under outage
since 28th July 2012 for up-gradation to 765 kV level). A similar incident at 1510
hours on 29th July 2012 had also led to a near miss situation. This section has
Quad Bersimis conductor which has a Surge Impedance Loading (SIL) of 691
MW but loaded much above the SIL. Likewise, the loading on many circuits in the
Eastern region was also of the order of 550 MW and above against the SIL of
515 MW for a twin Moose configuration line.
1.0
NLDC, POSOCO
Page 1
In several incidents over the past few years, the following concerns have
come to the fore in several disturbances involving high antecedent line loadings
in the system.
1.
Surprises in the form of protective relaying mis-operations either due to
incorrect settings, load encroachment or use of distance relays for power
swing blocking. These have led to cascading failures in the past.
2.
Sustained high loading for a period of ten minutes or more in daytime high
ambient temperature conditions have led to line tripping on transient faults
possibly due to increase in sag.
3.
Till the incidents of 30th and 31st July 2012 is analyzed in detail and any
shortcomings in different regions identified, the following action plan is being
implemented with immediate effect.
NLDC, POSOCO
Page 2
Annexe-1
NLDC, POSOCO
Page 3
Annexe-2
Power System Operation Corporation Limited
National Load Despatch Centre
Dated: 1st August 2012
Interregional
Corridor
Total Transfer
Capability
(TTC)
MW
Reliability
Margin
(RM)
MW
Available
Transfer
Capability (ATC)
MW
LTA/ MTOA
MW
Available
Margin for
STOA
MW
West to
North*
1250
200
1050
260
790
400 kV Bina-Gwalior
East to
North
3850
200
3650
1158
2492
400 kV KahalgaonBiharsharif
West to
East
850
300
550
550
220 kV BudhipadarTarkera
East-North
East
440
35
405
135
270
220 kV BTPS-Agia
East-South
900
900
170
730
400 kV Rourkela-Talcher
West to
South
1000
1000
992
Limiting Element
*only one circuit is available presently on 400 kV Bina-Gwalior-Agra. The other line is under upgradation to 765 kV
level. 400 kV Zerda-Kankroli and 400 kV Kankroli-Bhinmal lines are under forced outage.
x----x----x
NLDC, POSOCO
Page 4