You are on page 1of 70

Dowel and Tie Bars in

Concrete Pavement Joints:


Theory and Practice

Lev Khazanovich
Associate Professor
University of Minnesota

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Presentation Outline

Introduction

Pavement joints, dowels, and tie bars

Benefits of dowel and tie bars


Dowel and tie bar design
Construction
Summary

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Longitudinal
joints

Transverse
joints

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel and Tie Bars

Dowel bars

Placed across transverse joints at the mid-depth of


the slab
Transfer load from one slab to another without
preventing the joint from opening
Commonly made of round, smooth, epoxy coated
steel bars
Reduce joint faulting and corner cracking

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel and Tie Bars

Tie bars

Placed across longitudinal joints at the mid-depth of the


slab
Prevent lanes from separation and differential
deflections
Made of deformed epoxy coated steel
Reduce transverse cracking

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowels and Tie Bars


Longitudinal construction
joint

Transverse contraction
joint
Tie bars

Dower bars

Courtesy of Dr. Darter


November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Presentation Outline

Introduction
Benefits of dowel and tie bars

Theory

Mechanism of load transfer


Effect on deflections and stresses
Effect on performance

Practice
Cost

Dowel and tie bar design


Construction
Summary
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Why do we need tie bars?


None or inadequate tie bar design

Lane separation

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of tie bars on pavement responses

No tie bars

Aggregate
interlocking

High stresses
High deflections

Pavement
distresses

Tie bars

Low stresses
Low deflections
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Good joint
performance

ISLAB2000 Finite Element Model

80 kN single axle load


November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Deflection

Deflections without Tie Bars

Nontied joint
Max Deflection = 0.54 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect
of Dowels
on Deflections
Deflections
with Tie
Bars

Tied joint
Max Deflection = 0.33 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of Tie Bars on PCC Stresses


Stresses in Y-direction

Principal Stresses at the Slab Bottom


Nontied joint
Max Stress = 2051 kPa

X-direction

Y-direction

Stresses in Y-direction

Tied joint
Max Stress = 1603 kPa
November 2, 2011
2nd International Conference on Best

293
269
245
222
198
174
151
127
103
80
56
33
9
-15

Why do we need dowels?


None or inadequate dowel bar design
Faulted Joint

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of dowels on pavement responses


Traffic direction

No dowels

Aggregate
interlocking

High stresses
High deflections

Pavement
distresses

Leave slab

Approach slab
Traffic direction
Rapid slab rebound

Aggregate
Interlock

Rapid movement of
materials backward
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Loss of support

Effect of dowels on pavement responses


Traffic direction

Dowels

Low stresses
Low deflections

No differential deflection,
No faulting

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Good joint
performance
Traffic direction

Effect of Dowels on Stresses and


Deflection

ISLAB2000

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of Dowels on Deflections

Nondoweled joint
Max Deflection = 1.02 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of Dowels on Deflections


Deflection

Doweled joint
Max Deflection = 0.6 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of Dowels on Stresses


Principal Stresses at the Slab Bottom
Principal Stresses

Y-direction

Nondoweled joint
Max Stress = 1120 kPa
160
142
125
107
89
72
54
37
19
2
-16
-33
-51
-68

Principal Stresses

Y-direction

X-direction

Doweled joint
Max Stress = 812 kPa
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

116
104
92
80
68
57
45
33
21
9
-3
-15
-26
-38

X-direction

Dowel and Tie Bars?


Federal Highway Administration Long Term
Pavement Performance Studies
1.
2.

Evaluation of Joint and Crack Load Transfer


(Khazanovich and Gotlif 2002)
Common Characteristics of Good and Poorly
Performing PCC Pavements (Khazanovich et al.
1997)

Almost 150 pavement sections located


throughout USA

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Cumulative Percentage of Passes

Effect on Load Transfer Efficiency


100
90
80
70
60
50
40
30
20
10
0

Doweled

Nondoweled

nondoweled

Poor
doweled

20

30

Good

40 50 60 70 80 90 100 110
LTE, Efficiency,
percentOOOO
Joint LoadMean
Transfer
percent

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

of sections
percentdistribution
Cumulative
(%)
Cumulative frequency

Effect of Dowels on Faulting


100
90
80

Doweled

Nondoweled
Doweled

70
60
50
40
30
20
10
0
0.00

Good

Normal

0.05 2.00.10

Poor

4.0
0.15

0.20

0.25
6.0

Faulting
(mm)
Faulting,
in
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Nondoweled

Doweled

0.308.0 0.35

0.40

Benefits of Dowels
Smith et al. 1990
Dowels increase the initial cost between
5 and 8 percent, but increase the load
carrying capacity over 100 percent
Gharaibeh and M. I. Darter 2001
The use of dowel bars increases the
initial pavement life by about 60 percent
and results in similar total Life Cycle
Cost reduction than not using dowels.

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Presentation Outline

Introduction
Benefits of dowel and tie bars
Dowel and tie bar design

Diameter
Length
Spacing

Construction
Summary
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Diameter
Germany
25 mm
USA
Concrete thickness
Dowel diameter
<200 mm
25 mm
200 - 250 mm
32 mm
>250 mm
38 mm
MEPDG based on the maximum allowed faulting
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Effect of Dowel Diameter on Faulting


0.25
Design period: 20 years
Slab thickness: 200 mm.

0.20
5.00
(mm) (in)
FaultingFaulting

Nondoweled

ND
D=1
D=1.25
D=1.5

0.15

0.10
2.50
DD=25 mm

0.05

DD=32 mm
DD=38 mm

0.00
0

50

100 150 200 250 300 350 400 450 500


Number
of Trucks
perdirection
days
AADTT
in one

November 2, 2011
2nd International Conference on Best

Khazanovich et al. 2004

Effect of Dowels Diameter on Bearing


Stresses

Dowel Diameter, mm

Concrete Bearing Stress, MPa

25
32
38

17.3
12.7
9.3

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Length and Spacing

Dowel length
Germany:
USA:
Minnesota:
Dowel spacing
Germany:
USA:

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

500 mm
450 mm
380 mm
250 mm in wheel path
500 mm outside of the wheel path
300 mm
non-uniform

Non-uniform Dowels Spacing

5 @ 300 MM

900 MM

Dowels in the wheel paths only


November 2, 2011
2nd International Conference on Best

5 @ 300 MM

Tie bar Diameter

Tie bar diameter


Austria:
Germany:
USA:

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

14 mm
20 mm
12.5 and 16 mm

Tie Bar Length and Spacing

Tie bar length


Austria:
Germany:
USA:
Tie bar spacing
Austria:
Germany:
USA:

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

700 mm
800 mm
760 mm
3 bars/slab
construction joints: 5 bars /slab
contraction joints: 3 bars/slab
table

FHWA Tie Bar Spacing


Bar diameter: 12.5 mm
Steel yield strength: 280 MPA
PCC
thickness (mm)
225
250
275
300

Distance to free edge (mm)


3000
650
600
550
500

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

3600
550
500
450
400

4800
400
400
350
325

7200
275
250
225
225

FHWA Tie Bar Spacing


Bar diameter: 16 mm
Steel yield strength: 280 MPa)
PCC
thickness (mm)
225
250
275
300

Distance to free edge (mm)


3000
1050
950
850
775

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

3600
875
775
725
650

4800
650
600
525
500

7200
425
400
350
325

Presentation Outline

Introduction
Benefits of dowel and tie bars
Dowel and tie bar design
Construction

Installation
Common problems
Evaluation
Fixing

Summary
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Installation
Dower bars
Dowel baskets
Dowel bar inserter (DBI)
A bond breaker (typically, grease) must be
applied prior to placement

Tie bars
Machine-place
Placed by hand
Chairs
Drilled and grouted
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Baskets

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Bar Inserter

NHI
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Bar Inserter

NHI
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Tie Bar Installation

Drilled

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Tie bar chairs

Common Installation Problems

Happy families are all alike;


every unhappy family is unhappy in its
own way.
Todas as famlias felizes so iguais.
Todas as famlias infelizes so diferentes.
Lev Tolstoy Anna Karenina
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Common Installation Problems


Bars are missing or misplaced
Poorly adjusted equipment
Damaged dowel baskets
Improper basket anchoring
Concrete around bars is poorly consolidated
Poorly adjusted equipment
Too stiff mix (often caused by mix delays)

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Common Problems Problems

Dowel and tie bar misplacement


Dowel and tie bars are too close to each other
Poor consolidation of concrete around dowels
and tie bars

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Vertical Position Problem

Dowel Installation

A tie bar is too far from the


mid-depth.
Concrete cover is too low.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Vertical Position Problem

Dowel Installation

If a bar is too close to the


top surface
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Vertical Position Problem

Dowel Installation

Cracking occurred near the joint the next


morning
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Common Problems

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

Common Problems
The tie is too close to the dowel

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

Common Problems
The tie is too close to the dowel

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

Common Problems
The tie is too close to the dowel

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

Poor Consolidation of Concrete

Entrapped air

Dowel bar
The PCC mix was way too stiff
due to paving delays.
300 meters had to be
removed and replaced.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

How to Avoid Problems

Three Ways to Achieve Good


Placement
Inspection
Inspection
Inspection

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

NDT for Bar Placement

Non-destructive Methods for Bar Location


Magnetic (MIT SCAN)
Ground-penetrating radar (GPR)
Ultrasound tomography

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

MIT SCAN
Advantages
Simple
Accurate
Relatively fast
Disadvantages
Must be calibrated for specific dowels and tie bars
May be have problems when dowel baskets are used
Cannot determine condition of concrete around dowel or
tie bars

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

MIT SCAN

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Ground-Penetrating Radar (GPR)


Advantages
Fast can be used for initial screening/gross bar
misplacements
Disadvantages
Data interpretation is time-consuming
Resolution is not very high

Rister and Graves 2011


November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Ultrasound Tomography
Advantages
Determines not only bar
position but also condition of
concrete around dowel/tie bar
Disadvantages
Relatively slow

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Ultrasound Tomography

Dowels

Lane 3

Measurement Point
18 in.
Longitudinal Joint

Pavement-Base Interface

Shoulder

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Ultrasound Tomography
dowels

joint

Crack Reflection

150

300

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Depth,
mm

Alignment Tolerances
Washington DOT tolerances for tie bars

Vertical translation: 25-mm

Horizontal translation: 25-mm


Vertical tilt: 25 mm
Horizontal skew: 25 mm

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Alignment Tolerances
Ministry of Transportation of Ontario (MTO 2007)
tolerances for tie bars
Depth tolerance
PCC thickness 200 mm : -6 mm / +12 mm
PCC thickness 250 mm : -15 mm/ +25 mm

Longitudinal translation: 50-mm


Vertical tilt: 15 mm
Horizontal skew: 15 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Alignment Tolerances
NCHRP 10-69 Study
University of Minnesota
(Prime Contractor)

Lev Khazanovich
Kyle Hoegh
Mark Snyder

http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_637.p
November
2, 2011
df
2nd International Conference on Best
Practices for Concrete Pavements

Alignment Tolerances
Field Testing of 60 pavement sections across USA
The majority of joints had dowel misalignments
within the following limits:
Vertical translation +/- 13 mm
Horizontal skew +/- 13 mm
Vertical tilt - +/- 13 mm
Longitudinal translation - +/- 50 mm
Dowel misalignment within these limits does not
appear to significantly affect pavement
performance.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Laboratory Testing
16 beams ,64 dowels with
precise misalignments
Pullout test
Shear test
Ultimate one time load
application
Repeated load application
Pullout Test

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Dowel Installation

Shear Test

Analytical Modeling

Dowel Installation

Plane of Symmetry
Joint

180
60

Exaggerated
joint opening

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Analytical and Laboratory Results


Dowel greasing is very important!
Dowel alignment
Good

Bad

Vertical position

Mid-depth +/- 13 mm

Concrete cover <50


mm
Concrete cover < saw
cut depth

Embedment length

>175 mm

< 50 mm

Rotation

< 25 mm/450 mm

> 75 / 450 mm

Dowel misalignment has the same apparent effect


on joint performance as a reduction in dowel
diameter
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Equivalent Dowel Diameter Concept

d eq remb rcc rvt rhs d 0


remb <1 if longitudinal translation is greater than 50 mm
rcc <1 if vertical translation is greater than 12.5 mm
rvt < 1 if vertical tilt is greater than 12.5 mm
rhs <1 if horizontal skew is greater 12.5 mm
d0 = nominal dowel diameter
Predicted Faulting

MEPDG Faulting Prediction, mm


0.14
0.12
3 mm
0.10
0.08
2 mm
10.06
0.04
1 mm
0.02
0.00

Faulting, in

D=33 mm
D=38 mm
Equivalent dowel diameter=1.32 in
Nominal dowel diameter=1.5 in
Faulting Limit
0

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

10
12
14
Pavement age, years

16

18

20

22

If the Bars Misplaced ..


It is NOT OK to have dowel positioned out of specification
Do not harm try to minimize invasive treatment
How to react
Carefully evaluate the problem (determine actual bar
location)
Evaluate short-term and long-term effects
Develop remedy plan

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

If the Bars are Misplaced ..


Case A: a dowel or tie bar is to close to the top surface
(<50 mm)
Cut the dowel through
Develop penalty and/or retrofit dowels or tie bars
Case B: Other types of misplacements
Evaluate effective dowel/tie bar diameter
Predict performance
Develop penalty and/or retrofit dowel or tie bar

November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

Summary
If properly designed and installed, dowels and tie bars
significantly improve performance of pavement joints
Although they increase the initial cost, dowel and tie bars
reduce Life Cycle Cost
Both dowel baskets and dowel bar inserters are good
installation alternatives
Improper dowel installation may reduce effectiveness of
the dowels and tie bars
Nondestructive testing methods give an opportunity to
trouble shoot the problems and determine their extent
The best approach is to use NDT during construction to
identify and fix the problem
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements

You might also like