Professional Documents
Culture Documents
Dowel and Tie Bars in Concrete Pavement Joints: Theory and Practice
Dowel and Tie Bars in Concrete Pavement Joints: Theory and Practice
Lev Khazanovich
Associate Professor
University of Minnesota
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Presentation Outline
Introduction
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Longitudinal
joints
Transverse
joints
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel bars
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Tie bars
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Transverse contraction
joint
Tie bars
Dower bars
Presentation Outline
Introduction
Benefits of dowel and tie bars
Theory
Practice
Cost
Lane separation
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
No tie bars
Aggregate
interlocking
High stresses
High deflections
Pavement
distresses
Tie bars
Low stresses
Low deflections
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Good joint
performance
Deflection
Nontied joint
Max Deflection = 0.54 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Effect
of Dowels
on Deflections
Deflections
with Tie
Bars
Tied joint
Max Deflection = 0.33 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
X-direction
Y-direction
Stresses in Y-direction
Tied joint
Max Stress = 1603 kPa
November 2, 2011
2nd International Conference on Best
293
269
245
222
198
174
151
127
103
80
56
33
9
-15
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
No dowels
Aggregate
interlocking
High stresses
High deflections
Pavement
distresses
Leave slab
Approach slab
Traffic direction
Rapid slab rebound
Aggregate
Interlock
Rapid movement of
materials backward
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Loss of support
Dowels
Low stresses
Low deflections
No differential deflection,
No faulting
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Good joint
performance
Traffic direction
ISLAB2000
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Nondoweled joint
Max Deflection = 1.02 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Doweled joint
Max Deflection = 0.6 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Y-direction
Nondoweled joint
Max Stress = 1120 kPa
160
142
125
107
89
72
54
37
19
2
-16
-33
-51
-68
Principal Stresses
Y-direction
X-direction
Doweled joint
Max Stress = 812 kPa
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
116
104
92
80
68
57
45
33
21
9
-3
-15
-26
-38
X-direction
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Doweled
Nondoweled
nondoweled
Poor
doweled
20
30
Good
40 50 60 70 80 90 100 110
LTE, Efficiency,
percentOOOO
Joint LoadMean
Transfer
percent
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
of sections
percentdistribution
Cumulative
(%)
Cumulative frequency
Doweled
Nondoweled
Doweled
70
60
50
40
30
20
10
0
0.00
Good
Normal
0.05 2.00.10
Poor
4.0
0.15
0.20
0.25
6.0
Faulting
(mm)
Faulting,
in
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Nondoweled
Doweled
0.308.0 0.35
0.40
Benefits of Dowels
Smith et al. 1990
Dowels increase the initial cost between
5 and 8 percent, but increase the load
carrying capacity over 100 percent
Gharaibeh and M. I. Darter 2001
The use of dowel bars increases the
initial pavement life by about 60 percent
and results in similar total Life Cycle
Cost reduction than not using dowels.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Presentation Outline
Introduction
Benefits of dowel and tie bars
Dowel and tie bar design
Diameter
Length
Spacing
Construction
Summary
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Diameter
Germany
25 mm
USA
Concrete thickness
Dowel diameter
<200 mm
25 mm
200 - 250 mm
32 mm
>250 mm
38 mm
MEPDG based on the maximum allowed faulting
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
0.20
5.00
(mm) (in)
FaultingFaulting
Nondoweled
ND
D=1
D=1.25
D=1.5
0.15
0.10
2.50
DD=25 mm
0.05
DD=32 mm
DD=38 mm
0.00
0
50
November 2, 2011
2nd International Conference on Best
Dowel Diameter, mm
25
32
38
17.3
12.7
9.3
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel length
Germany:
USA:
Minnesota:
Dowel spacing
Germany:
USA:
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
500 mm
450 mm
380 mm
250 mm in wheel path
500 mm outside of the wheel path
300 mm
non-uniform
5 @ 300 MM
900 MM
5 @ 300 MM
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
14 mm
20 mm
12.5 and 16 mm
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
700 mm
800 mm
760 mm
3 bars/slab
construction joints: 5 bars /slab
contraction joints: 3 bars/slab
table
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
3600
550
500
450
400
4800
400
400
350
325
7200
275
250
225
225
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
3600
875
775
725
650
4800
650
600
525
500
7200
425
400
350
325
Presentation Outline
Introduction
Benefits of dowel and tie bars
Dowel and tie bar design
Construction
Installation
Common problems
Evaluation
Fixing
Summary
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Installation
Dower bars
Dowel baskets
Dowel bar inserter (DBI)
A bond breaker (typically, grease) must be
applied prior to placement
Tie bars
Machine-place
Placed by hand
Chairs
Drilled and grouted
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Baskets
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
NHI
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
NHI
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Drilled
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Dowel Installation
Dowel Installation
Common Problems
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Common Problems
The tie is too close to the dowel
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Common Problems
The tie is too close to the dowel
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Common Problems
The tie is too close to the dowel
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Entrapped air
Dowel bar
The PCC mix was way too stiff
due to paving delays.
300 meters had to be
removed and replaced.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
MIT SCAN
Advantages
Simple
Accurate
Relatively fast
Disadvantages
Must be calibrated for specific dowels and tie bars
May be have problems when dowel baskets are used
Cannot determine condition of concrete around dowel or
tie bars
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
MIT SCAN
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Ultrasound Tomography
Advantages
Determines not only bar
position but also condition of
concrete around dowel/tie bar
Disadvantages
Relatively slow
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Ultrasound Tomography
Dowels
Lane 3
Measurement Point
18 in.
Longitudinal Joint
Pavement-Base Interface
Shoulder
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Ultrasound Tomography
dowels
joint
Crack Reflection
150
300
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Depth,
mm
Alignment Tolerances
Washington DOT tolerances for tie bars
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Alignment Tolerances
Ministry of Transportation of Ontario (MTO 2007)
tolerances for tie bars
Depth tolerance
PCC thickness 200 mm : -6 mm / +12 mm
PCC thickness 250 mm : -15 mm/ +25 mm
Alignment Tolerances
NCHRP 10-69 Study
University of Minnesota
(Prime Contractor)
Lev Khazanovich
Kyle Hoegh
Mark Snyder
http://onlinepubs.trb.org/onlinepubs/nchrp/nchrp_rpt_637.p
November
2, 2011
df
2nd International Conference on Best
Practices for Concrete Pavements
Alignment Tolerances
Field Testing of 60 pavement sections across USA
The majority of joints had dowel misalignments
within the following limits:
Vertical translation +/- 13 mm
Horizontal skew +/- 13 mm
Vertical tilt - +/- 13 mm
Longitudinal translation - +/- 50 mm
Dowel misalignment within these limits does not
appear to significantly affect pavement
performance.
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Laboratory Testing
16 beams ,64 dowels with
precise misalignments
Pullout test
Shear test
Ultimate one time load
application
Repeated load application
Pullout Test
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Dowel Installation
Shear Test
Analytical Modeling
Dowel Installation
Plane of Symmetry
Joint
180
60
Exaggerated
joint opening
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Bad
Vertical position
Mid-depth +/- 13 mm
Embedment length
>175 mm
< 50 mm
Rotation
< 25 mm/450 mm
> 75 / 450 mm
Faulting, in
D=33 mm
D=38 mm
Equivalent dowel diameter=1.32 in
Nominal dowel diameter=1.5 in
Faulting Limit
0
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
10
12
14
Pavement age, years
16
18
20
22
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements
Summary
If properly designed and installed, dowels and tie bars
significantly improve performance of pavement joints
Although they increase the initial cost, dowel and tie bars
reduce Life Cycle Cost
Both dowel baskets and dowel bar inserters are good
installation alternatives
Improper dowel installation may reduce effectiveness of
the dowels and tie bars
Nondestructive testing methods give an opportunity to
trouble shoot the problems and determine their extent
The best approach is to use NDT during construction to
identify and fix the problem
November 2, 2011
2nd International Conference on Best
Practices for Concrete Pavements