Preliminary Engineering Checklist

Site Survey

Stream profile (approx. 200 m each direction)


Stream Cross-sections (approx. 2 upstream and 2 downstream)
Road profile (approx. 200 m each direction)
Road cross-sections (approx. 3)

Hydrology

Existing Site Conditions (scour/erosion, high water marks)


Review other crossings on watercourse
Determine Drainage Area & Avg. Channel Slope
Rational Method
SCS Method
Channel Capacity

Hydraulics

Investigate multiple alternatives


Headwater
Freeboard
Inlet/Outlet Velocities

Select Design Road Cross-section


Determine Culvert Length
Cost Estimates
Corrosion Investigation

pH
Resistivity
Nearby structures
Choose thickness or material type

Structural Design

AASHTO or ASTM

Geotechnical

Long term settlement


Slope Stability

Utilities

Gas
Power
Telephone
Cable

Environmental Considerations