UNIT TEST NO 2

SUB NAME

CPS

DATE
PART A

: 25-02-15
(10 marks)

1.
2.
3.
4.

Define time cost tradeoff?


What is Activity on Node network?
Draw a network with two critical path? (4m)
Define critical path ( 2 m)
PART B
5. A Project has 5 activities as shown in the table. Determine optimum cost and time.
ACTIVITY
NORMAL
CRASH
TIME (WEEKS)

1020
1030
2040
3040
4050
INDIRECT COST
SUB NAME

COST (RS)

3
6
2
4
5

(15*1 =15)

TIME (WEEKS)

12000
18000
20000
16000
30000
RS 3000/ WEEK

CPS

COST (RS)

2
3
1
2
4
DATE

PART A

16000
24000
23000
21000
35000

: 25-02-15
(10 marks)

1. What is Activity on arrow network?


2. Draw a network with three critical path? ( 4 m)
3. What is crashing ( 2 m)
4. Diff direct and indirect cost
PART B
(15*1 =15)
5. The following table gives data about duration and cost of activities of project. The overhead cost = Rs 2000/week.
find optimum time and cost
ACTIVITY
Duration
cost
Normal
crash
normal
crash
12
4
2
4000
12000
23
5
2
3000
7500
24
7
5
3600
6000
34
4
2
5000
10000
SUB NAME
1.
2.
3.
4.
5.

CPS

DATE : 25-02-15
PART A
(10 marks)
Why not we crash non critical activities justify (3 m)
Define cost slope (2m)
Construct a AON with 8 activities (3m)
Give a example for indirect cost.
PART B
(15M)
The following table gives data about duration and cost of activities of project. The overhead cost = Rs 2000/week.
find optimum time and cost
ACTIVITY

12
23
24
34

Duration
Normal

cost
normal

crash

4
6
6
4

3
2
5
2

Crash

4000
3000
3600
5000

1000
5500
7200
10000