DEPARTMENT OF BLAST FURNACE

ESSAR STEEL HAZIRA LIMITED


PRESSURE TESTING OF 2200 CUM HAZIRA BLAST FUNACE BY COMP.AIR
LEAK TEST STAGE - I
DATE:
I. A TEAM CONSISTING OF THE FOLLOWING MEMBERS CONSTITUTED FOR THE
PRESSURE TESTING OF 2200 CUM BF HAZIRA:
COVERAGE OF AREAS UNDER:
a. Cold blast technological line & mixing line b). Hot blast mail line
c. Bustle Main & Bustle Ring d). Tuyere stock Assembly
e. Furnace proper f). uptakes & Down comer g).Dust catcher & up to inlet of Ven-I
1. B. KRISHNA CHAITANYA
BF (O) WORKS

1. JAYACHANDRAN
BF-PROJECT(M)

1. LENKA RAVI
UTILITIES-BF

2. K.GOPAL
BF(O) WORKS

2. GOPAL KRISHNAN
BF-PROJECT(E&I)

2. PANCHAL
SAFETY-BF

3. D. RAJU
BF- (O) WORKS

3. BENARJEE
BF-PROJECT(REF)

4. BINTESH SINGH
BF-(O) WORKS

3. V UPADHYAYA
EPIL-BF-CIVIL

4. SUBHASH SARKAR
BF-PROJECT(STRL)

4. SIRKE
EPIL-BF-MEC

ACCEPTED BY:
NIRMAL PUROHIT
HOD-BF (O) WORKS

B. MISRA
CHIEF-EPIL-BF

APPROVED BY:
SANJAY SARKAR
HOD-BF PROJECT

K A NAIDU
ADVISOR-BF WORKS

II. List of officers responsible for different areas from concerned fields of organization is
given in ANNEX-1
III. The team will ascertain the completion of all civil, structural, mechanical, refractories,
electrical automation works related to furnace for stage I pressure testing by air.
iv. over all cleaning of inside the furnace and all selected areas for pressure testing/inspection/observation
is to be ensured
v. Blanking and other preparations for testing are to be made as per procedure laid down by ANNEX-2

and site instructions.


vi. Safety precautions are to be taken as per the eclosed safety protocol ANNEX-3
vii. All required instruments like thermometer, pressure gauges etc, will have to be provided by project
group in adequate numbers.
viii. Contact persons with mobile/phone nos. ANNEX-4
ix. Micro-planning for pressure testing by all concerned (ANNEX-5)
x. Activities to be done on the date of pressure testing (ANNEX-6)
Prepared by:
B. Krishna Chaitanya
D.Raju