May 9.2015
EUTG impressed with first stages of wind farm
By Renée Meyer
The Electrie Utility Task Group
rescheduled its meeting for Monday,
April 27 to Wednesday, April 29 due
to the construction kick-off event held
in Quonset by Deepwater Wind, which
EUTG members Bill Penn and Everett
Shorey attended.
In the portion of the meeting when
the EUTG received its monthly update
from Decpwater’s Block Island liaison
Bryan Wilson, the construction ¢er-
emony was front and center. Wilson
noted that there was “full representa-
tion” on both the federal and Rhode
Island governmental levels, includ-
ing Gov. Gina Raimondo and Rhode
Island’s full congressional delegation
of Senators Jack Reed and Sheldon
Whitehouse, and Representatives Jim
Langevin and David Cicilline. From
Block Island, Second Warden Norris
Pike, and resident Henry du Pont also
attended.
Shorey wanted it known that state
Sen. Susan Sosnowski was also there.
“She's been a huge supporter of this,”
he-said. In speaking of Monday's event,
Shorey said that there were “Several
things I found impressive,” adding that
i's “huge to get the full congressional
delegation there.”
Shorey also felt that the focus on the
laborers in Quonset (from Specialty
Diving Services) “was pretty interest-
ing, Those guys were doing a good jab.”
he said referring to the welding being
done at the site, “The efforts I've seen
were working to quality.”
“This has been our mantra,” said
Wilson, emphasizing that everything
fon the project had to be done exactly
right, down to the smallest details,
such as repairing a paint scratch on a
turbine’s blade.
As Penn had noted earlier, July 18
would be the date “when barges would
be out on the southeast corner of the
island.”
Wilson elaborated: “July 18 the first
of five barges will be on-station, as well
as a crane barge.” This will be the start
‘on the construction phase when the
jacketed steel foundations are installed,
Wilson explained that pilings would be
driven through holes in the four corners
of the foundations into the seabed. But
first there will be a geophysical survey
of the areas involved by a company
named Pangea. He explained that the
survey was like taking a cat-scan image
of an area 30 meters in diameter, going
down 120 fect. He said that this would
allow the surveyors to determine if‘there were any ‘(glacial erratics” in the
area, “If we find a slew of glacial errat-
ies, we can slightly move the founda-
tion,” said Wilson,
Shorey put it in layman’s terms:
“It’s like finding the large rocks before
using the posthole digger.”
Wilson was asked about the archae-
ology research that was going on along
part of Beach Avenue, near Twin
Maples, and he said that that work
was being done under the auspices
of National Grid, not Deepwater, so
he coulda’t officially comment on it,
although he did say the group doing
the research was from the Public
Archaclogy Lab (“A leading cultural
research management firm,” according
to its website)
For a while the discussion veered
into other archaeological research
projects currently or recently having
been done on the island, unrelated to
Deepwater ot National Grid, including
a few jokes about the “archaelogical
artifacts” coming out of West Beach
due to erosion by Hurricane Sandy at
that site.
Then Wilson got back to the
Deepwater Wind project itself. He told
the group that the wind turbines are
under construction in France. On this
side of the pond, Wilson said, the “ter-
restrial work will begin in winter,”
referring to the building of the two
substations, one on Block Island and
the other on the mainland, as well as the
laying of the cable from the points of
entries at the shore to those substations,
“At this point there's a lot of stuff going
on,” he said.
Wilson elaborated on the local labor
that will be involved in the project this
summer. He said that there would be 75
people going back and forth between
Block Island and the mainland, primar
ily to Narragansett. There will also
be 24 “marine mammal observers”
and representatives from Occupational
Safety & Health Administration
(OSHA) and the Coast Guard. There
will also be “30-ish” employees from
Deepwater involved.
Wilson said that Deepwater had gone
from “12 core folks” to 45 now working,
‘out of Pravidence, and he told the group
that the company had recently moved
its offices to accommodate the growth.
After the Deepwater update, the
EUTG turned it focus to preparing for
meeting with the Town Council
to discuss future policy issues rel
to the Block Island Power Company
(BIPCo) that occured later that same
day. (See related story on page 5.)
It is anticipated that BIPCo will be
filing a rate case with the RI. Public
Utilities Commission when the wind
farin goes online and the local por
company will function as a power dis-
tributor, as opposed to a power genera-
tor and distributor, as they are now. At
prior meetings, it had! been agreed that
all parties needed to be proactive on the
subject and should work collaboratively
‘to avoid future legal costs and issues of
contention, should they arise