Cooling Tower and Expansion Tank Remaining Item/Work

Scope of Works

Last update 6 Feb 2014


Item / Work

Location

Target start

Target Complete

Remark

Cooling Tower
- Material

Double UNP Support (20 nos)

28-Jan-14

4-Feb-2014

Not yet on site

Pipe Support Galvanized to workshop 4 nos

28-Jan-14

4-Feb-2014

Not yet on site

Bolt M24 170 mm 192 nos

Need Confirmation

Flange 12 " = 1 flange 10 " = 5 nos

Need lathe process ( Feb 6, 2014))

Butterfly valve (For CT Future)

Material already onsite

PVC Cap Material On site 144 nos

On site, 29 Jan 2014

Spring Mounting for Pipe Support 8 nos

Spring for Support under slab 16 nos

Flexible Joint 150, 48 nos (include Balancing)

10

Flex Joint 32 (makeup water piping)

11

PVC 200 (Balancing Pipe)

12

PVC 150 (Balancing Pipe)

13

Galvanis 100 (Makeup water piping)

14

Galvanis 80 (Makeup water piping)

15

Galvanis 50 (Makeup water piping)

16

Galvanis 32 (Makeup water piping)

17

PVC 150 (Drain pipe)

18

Butterfly Valve 150 36 nos (drain + Balancing pipe)

- Working Item

UNP for Support Repair (20 nos)

Mz 1 FL + 2800

20-Feb-2014

Pipe Support Installation

Mz 1 FL + 0

20-Feb-2014

UNP Support under slab repair 8 nos

Mz 1 FL + 2800

PVC Cap Installation

Mz 1 FL + 2800

29-Jan-14

29-Jan-2014

Butterfly valve (For CT Future) include flange installation West area

Mz 1 FL + 2800

6-Feb-14

8-Feb-2014

Bolt Installation + Pipe settings east area

Mz 1 FL + 0

Waiting M24 bolt

Flexible Joint Installation inlet outlet

Mz 1 FL + 2800

Waiting Material

Kuken Inlet outlet change (West area)

Mz FL + 2800

29-Jan-14

30-Jan-2014

PSDS 3 Pipe route change ( 450 mm)

PSDS3 at Mz 1

11-Feb-14

13-Feb-2014

10

Balancing pipe Installation

CT area

28-Feb-2014

11

Makeup water piping Install

CT area

28-Feb-2014

12

Drain pipe installation

CT area

28-Feb-2014

Marking support position

Mezzanine 2 (PS 6)

Foundation Install + Tank Installation

Mezzanine 2 (PS 6)

Galvanis Piping Installation + Ladder Installation

Mezzanine 2 (PS 6)

PVC Drain Install From 32 to Mezzanine 2

Floor 32 to PS 6

PVC Drain Piping Installation from 30 to 25

PSDS3 Floor 30 to 25

Marking support position

PSDS3 Floor 24

Finished

Foundation Install + Tank Installation

PSDS3 Floor 24

Finished

PSDS3 Floor 24

20-Feb-2014
Completed

Remaining 1 Unit

Expansion Tank
Finished
Finished
6-Feb-14

8-Feb-2014

Piping Installation

10

Galavanis Pipe Installation 24 to 12

PSDS3 Floor 24 to 12

11

Marking support position

PSDS3 Floor 14

Finished

12

Foundation Install + Tank Installation

PSDS3 Floor 14

Finished

13

Piping Installation

PSDS3 Floor 14

14

Galvanis Piping Installation 14 to 7

PSDS3 Floor 14 to 7

15

Marking support position

PSDS3 Floor 7

Finished

16

Foundation Install + Tank Installation

PSDS3 Floor 7

Finished

17

Piping Installation

PSDS3 Floor 7

18

Galvanis Pipe Install 7 to 5

PSDS3 Floor 7 to 5

Fl23,22,20,18,16,14NotyetConnected

6-Feb-14

8-Feb-14

8-Feb-2014

11-Feb-2014