delays the next activity. Notice the 2 days of Free Slack associated with Task B and the 3 days associated with Task C. Since Task B has a start to start relationship with Task C, it can start two days later (on the Monday rather than the Thursday) and still not affect Task C. Any time later than that will affect Task C. Task C has 3 days of Free Slack meaning that it can be delayed 3 days without affecting the next task which happens to be The End. Michael Kelly, 2007
Total Slack the slack an activity has before
it delays the end of the project. Notice the 5 days of Total Slack associated with Task B and the 3 days with Task C. First the easy one. Task C can be delayed 3 days without affecting the project end (April16). A 4-day delay will postpone the project by 1 day. Now the hard one. With Task B the total slack consists of the 3 days of total slack from Task C plus the 2 days of its own free slack (remember it can be delayed 2 days without affecting the next task).