MATERIALS IN ROOF

Length of Purlins of the roof=24 m

A. Corrugated Sheet (using 2 corrugations)


1)

22.5/0.6=37.5 40 sheets in one row.

2)

Since length of rafter is 5.4m

3)

Order 38(2)(2)=160 pcs 32x10

B. Rivets
1)

For 10 long
160x22=3520 pcs

2)

Convert to kilograms
3520/180=19.56Kg or 20 Kg

C. Washers
1)

Double the no. of rivets


3520(2)=7040 pcs

2)

Convert to kilograms
7040/126=55.

STEEL TRUSS

For top and bottom chords:


No of truss= 6
Steel Used=2x2x1/4
Length per truss=13+13+19=45m
Using standard 6m length
Total Length=45(6)=270m
270/6=50 pcs 2x2x1/4

For web members:


No of truss= 6
Steel used=2x2x3/16
Length per truss=(1.5+1.32+2.64+3.63+3.5+3.82+4.43)2+5
=51.6852m
Using standard 6m length
Total Length=52(6)=312m
312/6=52 pcs 2x2x3/16

Sag rods:
No of lines= 6
Steel used=10mm diameter
Using standard 6m length
Total Length=6(31)=186m

186/6=31 pcs 10mm dia. sag rods

Purlins:
No of lines=14
Length per line=23.79 or 24
Total Length=14(23.79)=333m
Using standard 6m length
333/6=55.556 pcs 6m long 120x40x20x2.0

Tie Rods:
No of points=84
Total Length=84(0.051)=4.27 m
Buy 1 6m long 2.5x2.5x1/4

SUMMARY:

Corrugated GI sheets

160 pcs 32x10

Rivets

20 kg

Washers

56 kg

Top and Bottom Chords 2x2x1/4 (6m)

50 pcs

Web members2x2x3/16 (6m)

52 pcs

Sag rods (6m)

31 pcs 10mm dia.

Purlins 120x40x20x2.0 (6m)

56 pcs

Tie rods 2.5x2.5x1/4 (6m)

1 pc

ROOFING MATERIALS

Length of Rafter on 1side of the roof= 5.75m


Length of Purlins of the roof=22.5 m

Corrugated Sheet (using 2 corrugations)


22.5/0.6=37.5 38 sheets in one row.
Since length of rafter is 5.75m
use a combination of two 3m long GI sheet
Order 38(2)(2)=152 pcs 32x10
Rivets
For 10 long
152x22=3344 pcs
Convert to kilograms
3344/180=18.57kg19kg
Washers
Double the no. of rivets
3344(2)=6688 pcs
Convert to kilograms
6688/126=53.01kg54kg

STEEL TRUSS

For top and bottom chords:


No of truss= 6
Steel Used=2x2x1/4
Length per truss=13+13+19=45m
Using standard 6m length
Total Length=45(6)=270m
270/6=45 pcs 2x2x1/4

For web members:


No of truss= 6
Steel used=2x2x3/16
Length per truss=(1.5+1.32+2.64+3.63+3.5+3.82+4.43)2+5
=46.6850m
Using standard 6m length
Total Length=47(6)=282m
282/6=47 pcs 2x2x3/16

Sag rods:
No of lines= 6
Steel used=10mm diameter
Length per truss=13+13=26m
Using standard 6m length
Total Length=6(26)=156m
156/6=26 pcs 30pcs 10mm dia. sag rods
Purlins:
No of lines=14
Steel Used=120x40x20x2.0
Length per line=22.5m
Total Length=14(22.5)315m
Using standard 6m length
315/6=52.555 pcs 6m long 120x40x20x2.0

Tie Rods:
No of points=84
Steel Used=2.5x2.5x1/4
Length per point=0.051m (2)
Total Length=84(0.051)=4.27 m
Buy 1 6m long 2.5x2.5x1/4

SUMMARY:
Corrugated GI sheets

152 pcs 32x10

Rivets

19 kg

Washers

54 kg

Top and Bottom Chords 2x2x1/4 (6m)

45 pcs

Web members2x2x3/16 (6m)

50 pcs

Sag rods (6m)

30 pcs 10mm dia.

Purlins 120x40x20x2.0 (6m)

55 pcs

Tie rods 2.5x2.5x1/4 (6m)

1 pc